DOI : 10.17577/IJERTV14IS110214
- Open Access
- Authors : Pancham Kr Ray, Dr. Ram Singh, Dr. Lalgi, Er. Manish Raj, Er. Samar Mahato
- Paper ID : IJERTV14IS110214
- Volume & Issue : Volume 14, Issue 11 , November – 2025
- DOI : 10.17577/IJERTV14IS110214
- Published (First Online): 29-11-2025
- ISSN (Online) : 2278-0181
- Publisher Name : IJERT
- License:
This work is licensed under a Creative Commons Attribution 4.0 International License
Assessing the Impact of Microsoft Project on Planning and Execution of Electrical Infrastructure Project: A Case Study on Chemical Earthing in Jamshedpur
Pancham Kr Ray , Dr Ram Singh , Dr Lalgi , Er Manish Raj, Er Samar Mahato
Jharkhand university of Technology, Ranchi
ABSTRACT – The study evaluates the role of Microsoft Project in the planning and execution of electrical infrastructure work, using a chemical earthing project undertaken by SMG Electrical at the N-Town VIP section of Tata Main Hospital, Jamshedpur. The moto was to assess how MSP contributes to more accurate cost estimation, realistic scheduling, and structured resource allocation in small to medium-scale electrical projects. The analysis draws on actual site records and Microsoft Project outputs, including cost tables, Gantt charts, and resource reports, resource work overview report.
The comparison between planned values and project outcomes shows that Microsoft Project upgrade the clarity and precision of project planning. The baseline cost generated through MSP 188,600 was almost identical to the actual implementation cost (187,910), resulting in a very small variance of 690. The activities were completed in line with the planned schedule, and no delays were recorded. Resource deployment was also consistent with the MSP plan, with all labor categories closing the project with zero pending work hours. A very important observation is the difference between MSPs calculated cost and the contractors billed amount 218,660, which underlines the usefulness of MSP as a tool for cross-verification and cost control.
Our findings suggest that MSP offers a structured and dependable approach for managing electrical fieldwork by supporting better cost control, schedule observance, and resource coordination. This study also indicates that same projects could benefit from wider integration of MSP with digital monitoring and cost management systems to further improve accuracy and transparency.
-
INTRODUCTION
-
Background
The electrical and infrastructure projects often face delays, cost overruns, and resource imbalance due to weak planning and lacking monitoring systems [1],[2]. These issues underline the need for structured project management practices that can support predictable and transparent execution. Tools such as Oracle Primavera P6 and Microsoft Project have become important in this context. Primavera applies methods like the Critical Path Method and Enterprise Project Structure for schedule and resource control, improving overall project performance [3]. Despite such advances, studies continue to note that insufficient planning remains a major contributor to overruns in construction and electrical works [4].
Earthing systems play a central role in electrical infrastructure by safely dissipating fault currents and preventing hazardous voltages. Failures caused by high soil resistivity and poor earthing arrangements have led to operational issues in utilities such as the Al Ain Distribution Company, underscoring the need for reliable grounding practices [5],[6]. Chemical earthing has gained very importance in such conditions because grounding enhancing materials maintain lower and more consistent resistance levels across varying soil properties [8].
-
Planning and Project Management Tools
Project planning software supports scheduling, resource allocation, and monitoring. Primavera P6 is broadly used in high-value and technically complex projects due to its advanced tracking and performance-measurement tools [3],[4]. MSP, however, is increasingly preferred for medium-scale and field-based projects because it offers a simpler interface, efficient resource leveling, and effective progress tracking [1],[2]. Its flexibility makes MSP suitable for case studies focusing on project execution and cost control.
-
Chemical Earthing in Electrical Infrastructure
Conventional earthing systems often show inconsistent performance where soil resistivity is high, creating reliability and safety concerns [5]. Chemical earthing addresses these challenges by using conductive backfills that stabilize resistance and enhance current dissipation, making it suitable for industrial regions with varied soil conditions such as Jamshedpur [6],[8].
-
Integration of MSP with Earthing Works
While chemical earthing ensures technical reliability, its successful implementation depends on coordinated planning. MSP supports this by helping track material procurement, manpower scheduling, activity sequencing, and cost flow. Integrating MSP into earthing work improves schedule adherence and financial control, reducing the likelihood of delays and overruns [1],[3].
-
Aim of the Study
The aim of this study is to evaluate the impact of Microsoft Project (MSP) on the planning and execution of chemical earthing work in Jamshedpur. The study focuses on:
-
Assessing MSPs role in scheduling, resource coordination, and cost control.
-
Evaluating the performance of chemical earthing in variable soil conditions.
-
Proposing a combined framework linking MSP-based planning with field execution of grounding systems.
-
-
-
LITERATURE REVIEW:
-
Literature Review
Project-planning studies consistently show that software-supported scheduling improves accuracy and coordination. Research on multi-project environments demonstrated that resource leveling and what-if simulations reduce demand peaks and help managers select feasible timelines [1]. Case-based work using Microsoft Project (MSP) reports clearer CPM scheduling, better visibility of labor and materials, and improved forecasting when compared with manual planning methods [2]. Primavera P6 studies similarly show stronger workload balance, earlier detection of conflicts, and reduced delay risk through CPM and EPS structures [3]. Broader reviews confirm that weak planning and poor monitoring remain major causes of overruns, and that digital tools substantially reduce coordination errors [4].
In electrical infrastructure, studies highlight the safety implications of poor grounding. Research on earthing design stresses soil resistivity testing, proper grid sizing, and the use of enhanced backfills to maintain safe step and touch potentials [5],[9]. Distribution-network studies directly link grounding adequacy to system reliability and mis-operations [6]. Work on chemical earthing and ground-enhancement materials (GEMs) shows that performance varies with moisture retention, corrosion behaviors, and installation quality, and that engineered materials generally provide more stable resistance across seasons [8],[12],[15]. Several authors also recommend selective use of enhancement materials and adherence to proper installation practices for long-term performance [11],[13],[17] . Comparative studies on project-management tools show that structured tracking of baselines, actuals, and earned-value metrics reduces delay and financial loss in construction projects [7]. Primavera-based evaluations highlight strengths in predicting cost deviations, although many studies focus mainly on timecost interactions without integrating risk [14]. MSP-specific research shows consistent benefits in dependency management, progress tracking, schedule crashing, and productivity improvements, particularly for small- to medium-scale projecs where usability and quick adoption are essential [16],[18],[19],[20]. Recent reviews emphasize MSPs overall suitability for project-level planning and its growing relevance in electrical and construction workflows [10].
-
Gap Identification
Studies on project-management tools show clear benefits for scheduling and cost control, but most work focuses on Primavera P6. Research on chemical earthing, meanwhile, deals with soil behavior, grounding design, and enhancement materials, but does not explain how these tasks are planned, resourced, or monitored within an actual project. The two research streams operate separately. Evidence on using Microsoft Project (MSP) for electrical-infrastructure activitiesespecially earthingis almost absent. No studies link MSPs WBS structure, cost baselines, or progress tracking with the technical steps of chemical earthing. Case-based work from Indian urban settings like Jamshedpur is entirely missing, even though soil conditions, procurement delays, and field practices strongly affect outcomes. The core gap is the lack of an integrated framework that connects chemical-earthing workflows (soil testing, material selection, installation, QA, and maintenance) with MSP-based planning elements such as schedule logic, resource/cost baselines, and earned-value indicators. Prior studies also do not provide planned-versus-actual comparisons or quantify time, cost, and reliability impacts for earthing projects. This study addresses the gap by applying MSP to a real chemical- earthing project in Jamshedpur and evaluating its effects on schedule adherence, resource use, and cost variance.
-
Objectives
-
Primary Objective
To evaluate how Microsoft Project (MSP) influences the planning and execution of electrical infrastructure projects, with a specific focus on chemical earthing in Jamshedpur.
-
Secondary Objectives
-
To identify key challenges in planning and executing electrical-infrastructure works, especially chemical earthing.
-
To assess the effectiveness of MSP in scheduling, resource allocation, and cost management.
-
To examine how MSP supports monitoring and control through time and cost performance indicators.
-
To understand how technical requirements of chemical earthing can be incorporated into MSP-based planning workflows.
-
To develop a structured approach for improving the planning and execution of chemical earthing projects using MSP.
-
-
-
-
PROBLEM STATEMENT
Electrical infrastructure in cities like Jamshedpur is expanding quickly, yet projects continue to face delays, cost overruns, and poor resource management due to traditional planning methods that do not properly connect scheduling with material and cost allocation [3],[2],[1]. Earthing systems are especially critical, and research shows that inadequate grounding can create unsafe voltages and equipment failures [5],[6]. Chemical earthing offers more stable resistance under varied soil conditions, but its integration into structured project planning remains largely unexplored [8],[15].
Project-management tools such as Microsoft Project (MSP) provide strong scheduling, resource, and cost-control features, but their application in electrical-infrastructure projectsparticularly chemical earthinghas received very limited academic attention [4]. As a result, there is a clear gap in combining technical earthing practices with software-based planning and monitoring.
This study aims to address this gap by evaluating how MSP can improve planning, execution, and material-cost alignment for chemical-earthing works in Jamshedpur.
-
METHODOLOGY
-
Research Design
This study uses a mixed-methods case study approach to assess how Microsoft Project (MSP) supports the planning and execution of a chemical-earthing project in Jamshedpur. Quantitative project data (time, cost, resources) are combined with qualitative insights from engineers and field observations.
-
Data Collection
-
Primary Data
-
MSP project schedules including WBS, task links, and critical-path identification.
-
Resource and cost inputs for labor, electrodes, chemical backfill, and related materials.
-
Feedback from site engineers, project managers, and electrical contractors.
-
Field observations on soil conditions, installation challenges, and handling delays.
-
-
Secondary Data
-
Project documents, tender specifications, and government guidelines.
-
Literature on MSP, Primavera P6, and chemical-earthing practices.
-
-
-
Tools and Techniques
-
MSP for scheduling, resource planning, cost estimation, and performance tracking (SPI, CPI).
-
Comparative analysis of baseline versus actual progress to assess delay reduction and cost control.
-
CPM for timeline analysis and EVM for costtime performance.
-
Earthing assessment using IS 3043 and relevant IEEE grounding guidelines.
-
Data Analysis
-
Quantitative Analysis
-
Plannedversusactual performance tracking in MSP.
-
Calculation of SPI, CPI, and budget variance.
-
Assessment of material usage and cost deviations.
-
-
Qualitative Analysis
-
Thematic coding of interviews and site notes to identify execution challenges.
-
Incorporation of expert feedback to refine MSP models.
-
-
-
Validation
-
Cross-verification of MSP outputs with on-site execution results.
-
Review by project managers and electrical engineers.
-
Comparison with findings from prior studies on project-management tools and earthing design.
GI Electrodes Digging Pit Electrodes Installation
Connect Electrodes through GI Patti Connect machine and Electrodes through GI Patti
Source: SMG Electrical Dimna Jamshedpur
-
-
-
RESULT AND DISCUSSION
-
Result
-
This study assessed how Microsoft Project (MSP) supported the planning and execution of a chemical-earthing project carried out by SMG Electrical (JUSCO vendor) in the N-Town VIP area of Tata Main Hospital, Jamshedpur. The findings show that MSP contributed to better cost accuracy, on-time delivery, and efficient use of resources.
-
Cost Performance
MSP provided a close match between planned and actual expenditure. The baseline cost in MSP was 188,600, while the project was executed at 187,910, resulting in a very small variance of 690. Most activities finished with zero deviation, and only the electrode installation task showed a slight reduction in cost. This consistency indicates reliable budgeting and controlled field execution. A key observation is that the contractors billed amount was 218,660almost 16 percent higher than MSPs actual cost. This difference shows how MSP can help identify billing discrepancies and support transparent financial verification.
-
Schedule Performance
According to the MSP Gantt Chart, the project ran exactly as planned. Work started on 20 August 2025 and finished on 19 September 2025 with no delays. Tasks such as excavation, electrode installation, GI patty connection, RCC chamber construction, testing, and handover followed their scheduled dates. The absence of slippage suggests that MSPs task linking, activity sequencing, and critical-path visibility helped maintain a stable and predictable timeline.
-
Resource Utilization
MSPs resource reports showed accurate estimation and smooth deployment of labor. All assigned resourcestechnicians, skilled and unskilled labor, supervisors, and safety staffcompleted their tasks with zero remaining hours. This alignment between planned and actual usage indicates balanced workload distribution, minimal idle time, and effective labor` management.
-
Overall Project Performance
Across cost, schedule, and resource indicators, MSP created a structured and transparent project environment. The software enabled:
-
Realistic forecasting of cost and duration,
-
Continuous monitoring of progress,
-
Early visibility of deviations,
-
Better coordination among field teams,
-
Reliable documentation for verification and billing
The project was delivered on time, within estimated cost, and with efficient resource use. Overall, the results confirm that Microsoft Project significantly improved the planning and execution quality of the chemical-earthing work.
Gantt Chart of Chemical Earthing
Activity-wise Cost Table
Resource Cost Distribution repor
Resource Work Overview report
Cost Overview Report
Cntractor Bill
-
-
Discussion
The results clearly show that Microsoft Project (MSP) contributed to better planning and execution of the chemical-earthing work carried out by SMG Electrical in Jamshedpur. The strong match between the baseline and actual cost indicates that MSP supported realistic estimation and effective cost control. A variance of only 690 demonstrates that the planned budget was appropriate and that field execution closely followed the financial plan. The schedule-related findings further highlight the usefulness of MSP. All activities started and finished as planned, showing that task sequencing, dependency mapping, and critical-path visibility were well managed. The absence of delays is noteworthy, given that electrical-infrastructure projects often face disruptions related to material handling, labor availability, and site conditions. MSPs ability to structure dependencies and track progress appears to have contributed to stable execution. Resource utilization also aligned well with expectations. Zero remaining work hours for all labor categories suggest that workforce planning was accurate and balanced. The software enabled clear visibility of labor requirements, minimized idle time, and supported efficient coordination among technicians, supervisors, and support staff.A significant observation is the gap between MSPs actual cost (187,910) and the contractors billed amount (218,660). This difference of about 16 percent highlights MSPs practical value in financial verification and billing review. Such insights strengthen
accountability and reduce the likelihood of disputes between contractors and clients. It also reinforces the argument that digital tools are essential for transparent project governance. Overall, the discussion shows that MSP functions as more than a scheduling tool. It supports integrated planning, cost management, resource coordination, and progress monitoring. The findings suggest that MSP can enhance execution quality and provide measurable benefits in electrical-infrastructure projects, especially those involving technical tasks such as chemical earthing.
CONCLUSION
This study concludes that Microsoft Project has a positive and measurable impact on the planning and execution of electrical infrastructure projects. In the case of the chemical earthing project in Jamshedpur, MSP contributed to accurate cost forecasting, precise scheduling, efficient resource management, and transparent project monitoring. The strong alignment between planned and actual performance across all major indicators demonstrates that MSP enhances project control and reduces uncertainties .The findings confirm that MSP helps project teams maintain budget discipline, adhere to timelines, and achieve high levels of execution efficiency. Additionally, the discrepancy observed between MSP-estimated cost and contractor billing highlights the practical importance of MSP for cost validation and governance. Overall, MS Project proves to be an effective and dependable tool for managing small to medium-scale electrical infrastructure projects and can be scaled to larger projects with similar benefits.
REFERENCES
-
[1] Pradhan, S., Rajendra, S., & Vijay, K. (2016). Planning, scheduling and resource optimisation of multiple projects using Oracle Primavera P6.
International Journal of Research in Engineering and Technology, 5(6), 374379. http://ijret.esatjournals.org
-
[2] Pawar, N., & Kulkarni, P. (2024). Study of building planning and scheduling using Microsoft Project. International Journal of Novel Research and
Development (IJNRD), 9(5), 285289. https://www.ijnrd.org.
-
[3] Singh, S., & Bhatia, S. (2022). Resource allocation using Oracle Primavera P6. International Journal of Innovative Research in Computer Science &
Technology, 10(3), 165170. https://doi.org/10.55524/ijircst.2022.10.3.27
- [4] Sudarshan, S., & George, G. (2021). Comparison of project planning and scheduling softwares Primavera and Microsoft Project used in the construction industry. International Journal of Engineering Technologies and Management Research, 8(9), 7887. https://doi.org/10.29121/ijetmr.v8.i9.2021.1039.
- [5] Kumar, V., Kumar, N., Chaulya, S. K., & Banerjee, G. (2019). Earthing system design for electrical installations of building construction and laboratory equipments. International Journal of Scientific Engineering and Research (IJSER), 7(4), 2630. https://www.ijser.in.
- [6] Mariappan, V., Mohamed Rayees, A. B. S., & AlDahmi, M. (2014). Earthing system analysis to improve protection system performance in distribution networks. In Proceedings of the 12th International Conference on Developments in Power System Protection (DPSP 2014) (pp. 17). IET. https://doi.org/10.1049/cp.2014.0092.
-
[7] Rajat, & Reza, M. (2019). Time and cost control using Primavera P6 in construction of buildings. International Journal of Engineering Research &
Technology (IJERT), 8(11), 767771. https://doi.org/10.17577/IJERTV8IS110408.
-
[8] Gomes, C., & Abdul Sattar, M. Q. (2022). Backfill materials for enhancing the performance of electrical grounding systems: An analytical revisit. In 2022
IEEE Conference on Electrical and Power Engineering (ICEPE) (pp. 19). IEEE. https://doi.org/10.1109/ICEPE56265.2022.00000.
-
[9] Rahi, O. P., Singh, A. K., Gupta, S. K., & Goyal, S. (2012). Design of earthing system for a substation: A case study. International Journal of Advanced
Computer Research,2(4),228233,Retrieved from.https://accentsjournals.org/PaperDirectory/Conference/ICETT-2012/42.pdf.
-
[10] Wallecha, D. R., & Mata, M. D. (2020). A review on application of Microsoft Project software in multi-storeyed buildings. International Journal fo
Research in Applied Science & Engineering Technology (IJRASET), 8(5), 372377. https://doi.org/10.22214/ijraset.2020.5061
- [11] Halim, N. H., Hairuddin, M. F., Arshad, S. N. M., Isa, M., Adzis, Z., & Khang, A. W. Y. (2019). Analysis on topology of grounding system using bentonite and coconut husk as additive material. Universal Journal of Electrical and Electronic Engineering, 6(5A), 5058. https://doi.org/10.13189/ujeee.2019.061506
-
[12] Malewar, H. (2021). Application of Marconite as a good ground enhancement material than Bentonite in transmission lines: A case study. Proceedings
of the North East Transmission Company (NETC) Technical Conference, 110. Retrieved from https://www.netcindia.in
- [13] Shuhada, N. H., Ahmad, N. A., & Adzis, Z. (2016). Grounding enhancement material using bentonite. Journal of Advanced Research in Materials Science, 24(1), 18.Penerbit, Akademia Baru. https://www.akademiabaru.com/doc/ARMSV24_N1_P1_8.pdf.
- [14] Dodamani, S. M., & Kelkar, A. A. (2021). Application of Primavera P6 for cost overrun prediction. International Research Journal of Engineering and Technology (IRJET), 8(9), 10321036.https://www.irjet.net.
- [15] Lim, Z. K., Lim, S. C., Muhammad, U., Aman, F., & Mohamad Nor, N. (2024). Comparative field assessment of grounding enhancement material for electrical earthing system. Bulletin of Electrical Engineering and Informatics, 13(5), 30133020. https://doi.org/10.11591/eei.v13i5.7303
-
[16] Krishna, K. S. (2022). A case study on planning and scheduling of a project PIPLMC of a package-6A using Microsoft Project 2016. International Journal
of Science and Research, (IJSR), 11(4), 11871197 https://doi.org/10.21275/SR22425235646.
- [17] MartĂnez Ăngeles, H., RĂos Moreno, J. G., VelĂĄzquez Castillo, R. R., & Trejo Perea, M. (2024). Influence of the use of ground enhancement materials on the reduction of electrical resistivity in grounding systems: A review. Indonesian Journal of Electrical Engineering and Computer Science, 36(3), 13651378. https://doi.org/10.11591/ijeecs.v36.i3.pp1365-1378.
-
[18] Wale, P. M., Jain, N. D., Godhani, N. R., Beniwal, S. R., & Mir, A. A. (2015). Planning and scheduling of project using Microsoft Project (Case study of
a building in India). IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE), 12(3), 5763. https://doi.org/10.9790/1684-12335763.
-
[19] Kamble, U., & Vanakudari, S. U. (2018). Implementing time and cost optimization in commercial building using project management techniques in
Microsoft Project. International Research Journal of Engineering and Technology (IRJET), 5(6), 465470. https://www.irjet.net
- [20] Divekar, T. (2021). Enhancing construction productivity by Microsoft Project for planning, scheduling and resource allocation. Journal of Emerging
Technologies and Innovative Research (JETIR), 8(7), 7077. Retrieved from http://www.jetir.org
