Risk Management in Commercial Building Construction using PESTEL and SWOT Analysis

DOI : 10.17577/IJERTV10IS060349

Download Full-Text PDF Cite this Publication

Text Only Version

Risk Management in Commercial Building Construction using PESTEL and SWOT Analysis

Hasina P T

PG Student Dept. of Civil Engineering MGM College of Engineering and Pharmaceutical

Sciences, Valanchery, Malappuram Kerala, India

Fazil P

Assistant Professor Dept. of Civil Engineering MGM College of Engineering and Pharmaceutical Sciences, Valanchery, Malappuram

Kerala, India

Abstract The aim of this paper is to manage risks in the commercial building construction. Since construction is highly risk prone industry, proper management of the risks is the key to the success of the project. First step in the risk management is the identification of risks. Risk identification is done by questionnaire survey, separate questionnaires are prepared for internal (SWOT- Strength, Weakness, Opportunities, and Threats) and external (PESTEL- Political, Economic, Social, Technological, Environmental, and Legal) risks. Risk analysis is done by using SPSS software based on PESTEL and SWOT analysis. Risk management is thus done based on the analysis report.

Keywords Risk identification; risk analysis; risk management;

  1. INTRODUCTION

    Studies confirm that construction is a highly risk-prone industry because of certain distinctive characteristics of construction projects. Construction projects are characterized by their varying degrees of uniqueness and complexity, the active involvement of multiple stakeholders, capital intensiveness, dynamic environments, non-tradability of output, long production durations, and exposure to external environment and weather conditions.

    Risks and uncertainties are indeed inherent in every construction project from initiation through to completion and even during the operation phase of the constructed facility regardless of the size, nature, complexity, and location of the project. Failure to deal sufficiently with potential risks and uncertainties throughout the project life cycle can often have detrimental consequences on project objectives. Risk management, therefore, should be applied as an integral part of project management for the successful completion of construction projects in terms of time, cost, quality, safety, and environmental sustainability.

  2. OBJECTIVE OF THIS STUDY

    The main objective of this study is to manage the risks in the commercial building construction, through which the productivity and the quality of the commercial building construction can be improved. If the risks in the construction is properly managed and mitigated then, a project can complete within the scheduled time and cost. So risk management become a tool to ensure delay and quality management.

  3. LITERATURE REVIEW

    A number of Studies have been carried out to understand risk identification tools and techniques.

    Shubham Sharma (2021) conducted a research on risk identification and management in construction projects and found out that risk management is still very less among the construction industry. The most commonly used risk classification method was based on the nature of the risk and the most commonly used tool and technique for the risk identification was a questionnaire survey.

    Abroon Qazi (2021) conducted a research on Prioritizing risks in sustainable construction projects using a risk matrix- based Monte Carlo Simulation approach and concluded that two risk ranking schemes revealed significant differences relative to the identification of critical risks and their relative importance. It also says that assessment of sustainable related risks are difficult than normal risks.

    Huseyin Erol (2020) in this study of exploring the relationship between complexity and risk in mega construction projects concluded that Complexity and risks are interconnected by several dynamic links affected by uncertainties and management strategies. Risk analysis involves examining how project outcomes and objectives might change due to the impact of risks. The results showed that a high level of complexity makes it more difficult to predict the impact of risks on the megaprojects.

    Kerim Koc (2020) conducted a research on stakeholder- associated life cycle risks in construction supply chain and found out that the supplier, main contractor, and client were the key stakeholders for successful supply chain management. Assessment of risks considering interdependencies can be valuable to determine the most significant risk.One of the main reasons to determine risks of a project is to deliver effective management practices.

    Nasir B. Siraj (2019) this paper examines common risk identification tools and techniques, risk classification methods, and common risks for construction projects. The majority of the selected articles concentrated on the identification of negative risks and overlooked opportunities that could have a beneficial effect on achieving project objectives. The findings of the content analysis show that a combination of two or more risk identification tools and techniques were widely used.

    Wei Pan (2019) this paper examines the nature of the constraints on productivity enhancement and explores the rationale underpinning the productivity enhancement strategies at the industry level. A comprehensive literature review used a political, economic, social, technological, environmental, and legal (PESTEL) framework to reveal the major strategic themes of construction productivity enhancement.

    Dimosthenis Kifokeris (2019) conducted a research on analysis of impartial implementation in practice of risk identification in technical projects and found that the consideration of risk sources in the risk identification process as a means to bridge the identified gap and reduce discrepancy. The paper presents the results of the process-in and analysis of real projects risk data through unstructured interviews with the experts who provided the data, and examines their correlation with a comprehensive risk sources checklist drawn from previous research.

    A.Q. Adeleke (2018) concluded from the research on the influence of organizational external factors on construction risk management among Nigerian construction companies and concluded that Political, economy, and technology factors helped the construction companies to reduce the chance of risk occurrence during the construction activities. Rules and regulations also helped to lessen the rate of accidents involving construction workers as well as the duration of the projects.

    Tengyuan Chang (2018) conducted a research on political risk management strategies in international construction projects and found that all the strategies were important for political risk management in international construction projects. Five strategies including (1) choosing suitable projects, (2) building proper relations with host governments,

    (3) conducting market research, (4) avoiding misconduct, and

    (5) choosing a suitable entry mode were the most important strategies according to their average values.

    Ahmed Mohamed Keshk (2017) concluded through this research that Risk management team should continue its work in any project and do not stop until end of project because risks may emerge their indicators at different stages of project life cycle. Extraordinary interest of capabilities development of risk management team in project in the field of methods of diagnosis, qualitatively and quantitatively assessment of risks, whenever, skills are more high- in this field, results were more accurate and therefore it can be over-come risks or reduce their severity at least.

  4. RISK MANAGEMENT

    Risk Management (RM) is a systematic appoach to dealing with risk. A RM system should establish an appropriate context, set goals and objectives, identify and analyze the risks, influence risk decision-making and monitor and review risk response. Risk management in construction industry is an important part of the project planning and management. Risk management in construction is designed to plan, monitor and control those measures needed to prevent exposure to risk. To do this it is necessary to identify

    the hazard, assess the extent of the risk, provide measures to control the risk and manage any residual risks.

    1. Risk Management Cycle

      Risk management is a cyclic process. There are several steps involves in the risk management process. Fig.1 shows the steps involved in the risk management cycle. Risk identification is the first step in the risk management cycle. During the risk management process new risks may appear in the construction or the risks which are already appear in the construction cease to exist. Each segment in the risk management cycle is equally as important, hence each process should be carried out in a proper way to manage risks in construction.

      Fig. 1. Risk Management Cycle

    2. Risk Classification

    Risk classification (or categorization) is the important part of risk identification. The structured classification of risks contributes to the effectiveness and quality of the risk identification process and creates a better understanding of the nature of risks and their sources. Moreover, a logical and structured classification of risks assists in the reduction of redundancy and ambiguity in the risk identification stage and provides for easier management of risks in the later stages of risk management.

    There are various methods for classifying risks on construction projects. Risks can be categorized based on their source, nature, occurrence at different stages of the project, impact on project objectives and the party who might be the originator of the risk. Risks can be classified in to two main categories: internal risks (those that are project-related and that usually fall under the control of the project management team) and external risks (those risks that are beyond the control of the project management team).

    Construction

    Design

    1. Disputes between labors

    2. Changing sequences in construction activity

    3. Non availability of resources

    4. Revision of design

    5. Availability of camp for labors

    1. Complexity of project design.

    2. Design changes by owner or his agent during construction.

    3. Design errors and omissions made by designers.

    4. Insufficient data collection and survey before design.

    Construction

    Design

    1. Disputes between labors

    2. Changing sequences in construction activity

    3. Non availability of resources

    4. Revision of design

    5. Availability of camp for labors

    1. Complexity of project design.

    2. Design changes by owner or his agent during construction.

    3. Design errors and omissions made by designers.

    4. Insufficient data collection and survey before design.

    TABLE 1. RISKS UNDER INTERNAL RISK CONSTRAINTS

    Financial

    Management

    Consultant

    Contractor

    approving major changes in scope of work by consultant.

    communication and coordination between owner and contractor.

    Client

    1. Change in quantities of work

    2. In Time work permissions for executing work

    3. Safety of workers

    4. Stoppage of work due to Medical outbreak

    1. Lack of design team experience in construction projects.

    2. Mistakes and delays in producing design documents.

    3. Misunderstanding of owners requirements by design engineer.

    4. Poor use of advanced engineering design software.

    5. Unclear and inadequate details in drawings.

    6. Incomplete project design.

    7. Defective design made by designers.

    1. Delay from clients.

    2. Increment for staff benefits.

    3. Unprecedented price in raw materials.

    4. Fluctuations in Estimated finance than expected

    1. Documents and process directed as per agreement for mitigation of risk

    2. Project team discussions on risk

    3. Use of WBS and project milestones to help identify project risks

    4. Documented process for identifying project risks

    1. Lack of consultant experience in construction projects.

    2. Conflicts between consultant and design engineer.

    3. Delay in

    4. Delay in performing inspection and testing.

    5. Inaccurate site investigation.

    6. Inadequate project management assistance.

    7. Late in reviewing and approving design document.

    8. Poor

    1. Frequent change of subcontractors.

    2. Inadequate contractor experience.

    3. Inappropriate construction methods.

    4. Incompetent project team.

    5. Ineffective project planning and scheduling.

    6. Poor communication and coordination between owner and consultant.

    7. Poor site management and supervision.

    8. Unreliable subcontractors.

    9. Inadequate site investigation.

    10. Inappropriate contractors policies.

    11. Poor financial control on site

    1. Clients cash flow problems.

    2. Slow decision making.

    3. Delay in revising and approving design documents.

    4. Change order by owner during construction.

    procedures)

    Social

    Technological

    Environmental

    Legal

    1. Outbreak of hostilities (wars, revolution, riots, and terrorism)

    2. Corrupt local government officials demand bribes or unjust rewards

    3. High level of bureaucracy of the authority

    4. Expropriation and nationalization of assets/facilities without reasonable compensation

    5. Governments improper intervention during construction

    6. Poor relations with related government departments

    7. Government restrictions on foreign companies (e.g., import/export restrictions, mandatory technology transfer, differential taxation of foreign firms, etc.)

    1. Changes in tax regulation

    2. Poor financial market or unavailability of financial instrument resulting in difficulty of financing

    3. Unfavorable economic situations in the country (instability of economic conditions)

    4. Market demand changes

    1. Land acquisition and compensation problems (the cost and time for land acquisition exceeds the original plans)

    2. Public opposition to the project (public objections, social grievances)

    3. Differences in social, cultural, and religious backgrounds

    4. Insecurity and crime (theft, vandalism, and fraudulent practices)

    5. Strikes and labor disputes

    6. Poor public relations with local contacts

    7. Unfavorable social environment

    8. Societal conflict and/or public unrest

    9. Poor public decision-making process

    10. Disturbances to public activities

      Design errors and poor engineering.

    1. Poor constructability.

    2. Complexity of design.

    3. Technology changes.

    4. Incomplete design.

    5. Delay in design.

    6. Inadequate study and insufficient data before design.

    7. Unclear and inadequate details in design drawings and specifications.

    8. Unanticipated engineering and design changes.

    1. Force majeure (natural and man-made disasters which are beyond the firms control, e.g., floods, thunder etc.

    2. Adverse environmental impacts of the project

    3. Pollution associated with construction activities (dust, harmful gases, noise, solid and liquid wastes, etc.)

    4. Strict environmental regulations and requirements

    5. Poor environmental regulations and controls

    6. Changes in environmental standards and permitting

    7. Poor preliminary assessment and evaluation of environmental impacts of the project

    8. Prosecution due to unlawful disposal of construction waste

    9. Failure to obtain environmental approval

    1. Recycling, minimum wage increase

    2. Disability discrimination

    3. Adhering with transportation rules, import / export procedures.

    4. Complement with standard and metrology authority.

    5. The labors office conditions (labor rate).

    6. Migration rules.

    7. Difficulty to get permits.

    8. Ambiguity of work legislations.

    9. Legal disputes during the construction phase among the parties of the contract.

    10. Delayed disputes resolutions.

    11. No specialized arbitrators to help settle fast.

    procedures)

    Social

    Technological

    Environmental

    Legal

    1. Outbreak of hostilities (wars, revolution, riots, and terrorism)

    2. Corrupt local government officials demand bribes or unjust rewards

    3. High level of bureaucracy of the authority

    4. Expropriation and nationalization of assets/facilities without reasonable compensation

    5. Governments improper intervention during construction

    6. Poor relations with related government departments

    7. Government restrictions on foreign companies (e.g., import/export restrictions, mandatory technology transfer, differential taxation of foreign firms, etc.)

    1. Changes in tax regulation

    2. Poor financial market or unavailability of financial instrument resulting in difficulty of financing

    3. Unfavorable economic situations in the country (instability of economic conditions)

    4. Market demand changes

    1. Land acquisition and compensation problems (the cost and time for land acquisition exceeds the original plans)

    2. Public opposition to the project (public objections, social grievances)

    3. Differences in social, cultural, and religious backgrounds

    4. Insecurity and crime (theft, vandalism, and fraudulent practices)

    5. Strikes and labor disputes

    6. Poor public relations with local contacts

    7. Unfavorable social environment

    8. Societal conflict and/or public unrest

    9. Poor public decision-making process

    10. Disturbances to public activities

    1. Design errors and poor engineering.

    2. Poor constructability.

    3. Complexity of design.

    4. Technology changes.

    5. Incomplete design.

    6. Delay in design.

    7. Inadequate study and insufficient data before design.

    8. Unclear and inadequate details in design drawings and specifications.

    9. Unanticipated engineering and design changes.

    1. Force majeure (natural and man-made disasters which are beyond the firms control, e.g., floods, thunder etc.

    2. Adverse environmental impacts of the project

    3. Pollution associated with construction activities (dust, harmful gases, noise, solid and liquid wastes, etc.)

    4. Strict environmental regulations and requirements

    5. Poor environmental regulations and controls

    6. Changes in environmental standards and permitting

    7. Poor preliminary assessment and evaluation of environmental impacts of the project

    8. Prosecution due to unlawful disposal of construction waste

    9. Failure to obtain environmental approval

    1. Recycling, minimum wage increase

    2. Disability discrimination

    3. Adhering with transportation rules, import / export procedures.

    4. Complement with standard and metrology authority.

    5. The labors office conditions (labor rate).

    6. Migration rules.

    7. Difficulty to get permits.

    8. Ambiguity of work legislations.

    9. Legal disputes during the construction phase among the parties of the contract.

    10. Delayed disputes resolutions.

    11. No specialized arbitrators to help settle fast.

    TABLE 2. RISKS UNDER EXTERNAL RISK CONSTRAINTS

    Political

    Economic

    1. Changes in government laws, regulations, and policies affecting the project

    2. Political instability of the government (unfavorable political environment)

    3. Delay or refusal of project approval and permit by government departments (excessive approval

    1. Unpredicted changes in the inflation rate.

    2. Project-funding problems.

    3. Fluctuations in currency exchange and/or difficulty of convertibility

    4. Unpredicted changes in interest rates

    5. Escalation of material prices

    6. Delay in payments

  5. DATA COLLECTION

    Risk identification is done by questionnaire survey. Questionnaire is designed based on PESTEL and SWOT analysis. For the questionnaire survey thirty commercial construction sites are selected. Respondents for the survey includes engineer, contractor, consultant, client, supervisor, project manager and labors. Like hood and the impact of risks are identified through this questionnaire survey.

    1. PESTEL Analysis

      PESTLE is a shortened form for political, economic, social, technological, legal and environmental. Pestle is a strategic management tool and is used in the construction industry and its objective is to find out how the external environment affects the industry. The external environment affects industries in many ways, but there is not much that can be done to change the external environment whereas the internal environment can be changed to a certain extent. The Pestle technique can be used successfully and effectively in external risk identification process.

    2. Questionnaire for PESTEL Analysis

      Questionnaire for PESTEL analysis is designed based on six external risk factors, political, economic, social, technological, environmental, and legal. There are certain risks are listed under each risk factor. Ranked questionnaire is prepared as the probability of each risk noted as never, rare, sometime, often, very frequent, starting from one to five ranges . Impact of risks range is very low, low, somewhat high, high, and very high numeric range from one to five.

    3. SWOT Analysis

      SWOT analysis is a strategic management tool, mainly employed in the internal risk management. SWOT stands for Strengths Weaknesses, Opportunities, and Threats. It is a framework by which organizations and teams assess the pending internal and external influences that can affect a project, product or institutio positively or negatively.

      Strengths and weaknesses are generally related to issues that are internal to the organization. Strengths examine what the organization does well or its assets, skill, core competencies. Weaknesses are areas the organization could improve upon that is lacking or missing from the organization. Typically negative risks are associated with the organizations weaknesses and positive risks are associated with its strengths In terms of Risk Management, we call negative risks as threats and positive risks as opportunities. Opportunities and threats are usually external to the organization.

    4. Questionnaire for SWOT Analysis

      Questionnaire for SWOT analysis is designed based on seven internal risk factors, so that all the internal risks can be identified.

    5. Risk Analysis

      Risk analysis is regarded as the procedure involving the critical evaluation of prospective risks, arranging them according to importance, and allowing the management team to select the important ones. Risk analysis is the most tasking procedure in managing risk.

      This is due to the fact that it involves assessing the chances of the event of a risk and their outcomes on a projects objectives. Its main aim is to evaluate risk by separating the unnecessary events, the chances of the unwanted event happening, and the size of such events.

    6. Risk Analysis Using SPSS Software

    SPSS software is used for risk analysis. In the analysis like hood and impact of each risk both external and internal is considered. For each risk factor its possibility of occurrence and the impact will not be same range. Some risks happen frequently in the construction industry but the impact will be low. There for the method used for the analysis are descriptive statistics -frequencies and compare means paired sample T test. Like hood of the risk and its impact is compared using compare means paired sample T test.

  6. RESULTS AND DISCUSSION

    Risks in the construction industry can be managed by ranking of the risks, which are most frequently affect the commercial building construction. Risk ranking enable to understand and mitigate the major risk in construction industry.

    A. Risk Ranking

    Through the questionnaire survey and risk analysis it is found that, some risks are frequently happening in the construction industry and some risks have high impact on project objectives. These risks can be properly managed and mitigated by risk ranking. It will helps to identify and categorize risks according to their occurrence and their impact. The major risks under each risk factors both external and internal are ranked based on their like hood and impact. Top ten risks in commercial building construction is listed in the table 3 below.

    TABLE 3. TOP TEN RISKS IN COMMERCIAL BUILDING CONSTRUCTION

    Risk

    Rank

    Escalation of material prices

    1

    Unfavorable economic situations

    2

    Design changes by owner or his agent during construction

    3

    Market demand changes

    4

    Unpredicted changes in the inflation rate

    5

    Clients cash flow problems

    6

    Adhering with transportation rules

    7

    Changing sequences in construction activity

    8

    Force majeure

    9

    Inaccurate site investigation

    10

  7. CONCLUSION

    From the above study it is clear that construction industry possess a complex environment, which has many uncertainties in the form of risk. Proper risk management contribute to the successful completion of the project and can improve the quality of the project. There are many kinds of risks in the construction firm. Complete risk avoidance is not practical but risks can be mitigated and reduced to an acceptable level. The top ten risks listed are the risks which need immediate care since they are frequently appearing in the construction industry and having high impact.

    There are four alternative strategies for managing risks namely, risk avoidance, risk transfer, risk mitigation, and risk

    acceptance, for treating risks in a construction project. There are certain risks which cannot be avoided completely, so such risks need to transfer or mitigate or sometimes accept under control, in a view that doesnt harm the project. Reviewing the previous project is an effective way to understand about risk, its impact and control measures have taken.

  8. SUGGESTIONS

    Risks in the commercial building construction can be treated by various methods. These methods are chosen based on the type, nature, and source of the risk. In this study it is seen that escalation of material price is the most frequent risk in the commercial building construction. Hike in the material prices can be cured by the following methods

    1. Risk Reduction By Barter Trading

      Barter trading is known from ancient times, in which trading of good or services between two parties is done without the use of money or a monetary medium such as credit card. Bartering involves the provision of one good or service by one party in return for another good or service from another party. In the construction industry construction materials are exchanged between two parties.

    2. Economic Risk Reduction by Barter Trading

    Bartering involves the provision of one good or service by one party in return for another good or service from another party. In the construction industry construction materials are exchanged between two parties.

    Covid pandemic has made many changes in our lifestyle. Many businesses turn in to online platform. Covid brings a new world in front of us. All things are going to be digitalized in the post Covid world. So the barter system can also be implemented by digital marketing. A website is made to sell the construction materials. It will connect a pair of people; who can exchange their products according to their needs and economic situations.

  9. ACKNOWLEDGMENT

The author thankfully acknowledge to Dr. Indiradevi K.P, Principal MGM College of Engineering and Pharmaceutical Sciences, Valanchery. Mr. Fazil P Head of Department and all other staff members of Department of Civil Engineering for giving the opportunity to present this project.

REFERENCES

  1. Sharma, Shubham, and Ashok Kumar Gupta. "Risk identification and management in construction projects: Literature review." International Journal of Humanities, Arts and Social Sciences 5, no. 6 (2019): 224-231.

  2. Qazi, Abroon, Abdulrahim Shamayleh, Sameh El-Sayegh, and Steven Formaneck. "Prioritizing risks in sustainable construction projects using a risk matrix-based Monte Carlo Simulation approach." Sustainable Cities and Society 65 (2021): 102576.

  3. Erol, Huseyin, Irem Dikmen, Guzide Atasoy, and M. Talat Birgonul. "Exploring the Relationship between Complexity and Risk in Megaconstruction Projects." Journal of Construction Engineering and Management 146, no. 12 (2020): 04020138.

  4. Koc, Kerim, and Asli Pelin Gurgun. "Stakeholder-Associated Life Cycle Risks in Construction Supply Chain." Journal of Management in Engineering 37, no. 1 (2021): 04020107.

  5. Siraj, Nasir B., and Aminah Robinson Fayek. "Risk identification and common risks in construction: Literature review and content analysis." Journal of Construction Engineering and Management 145, no. 9 (2019): 03119004.

  6. Pan, Wei, Le Chen, and Wenting Zhan. "PESTEL analysis of construction productivity enhancement strategies: A case study of three economies." Journal of Management in Engineering 35, no. 1 (2019): 0501801.

  7. Kifokeris, Dimosthenis, and Yiannis Xenidis. "Analysis of impartial implementation in practice of risk identification in technical projects." ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering 5, no. 3 (2019): 04019010.

  8. Adeleke, A. Q., Ahmad Yusni Bahaudin, A. M. Kamaruddeen, J. A. Bamgbade, Maruf Gbadebo Salimon, Muhammad Waris Ali Khan, and Shahryar Sorooshian. "The influence of organizational external factors on construction risk management among Nigerian construction companies." Safety and health at work 9, no. 1 (2018): 115-124.

  9. Chang, Tengyuan, Bon-Gang Hwang, Xiaopeng Deng, and Xianbo Zhao. "Identifying political risk management strategies in international construction projects." Advances in Civil Engineering 2018 (2018).

  10. Keshk, Ahmed Mohamed, Ibrahim Maarouf, and Ysory Annany. "Special studies in management of construction project risks, risk concept, plan building, risk quantitative and qualitative analysis, risk response strategies." Alexandria engineering journal 57, no. 4 (2018): 3179-3187.

Leave a Reply