COCOMO II Implementation Using Perceptron Learning Rule

DOI : 10.17577/IJERTV2IS60721

Download Full-Text PDF Cite this Publication

Text Only Version

COCOMO II Implementation Using Perceptron Learning Rule

Ridhika Sharma1 , Dr. R. Rama Kishore2 1M.Tech (IT) Scholar , 2Asstt. Prof.

Guru Gobind Singh Indraprastha University , New Delhi

Abstract:

Software cost and effort estimation is the most critical task in handling software projects. Since it is very difficult to bridge the gap between estimated cost and actual cost, hence the accurate cost estimation is one of the challenging tasks in maintaining software projects. In software industry the most widely used model for effort estimation is Constructive Cost Model (COCOMO). In this paper, the author explores the use of perceptron learning rule to implement COCOMO II for effort estimation. This work proposes an estimation model that incorporates COCOMO II with perceptron learning rule to provide more accurate software estimates at early phase of software development, so that the estimated effort is more close to the actual effort.

Keywords: COCOMO II, Neural Networks, Perceptron learning rule.

  1. Introduction

    Software cost and effort estimate is one of the most important activities in software project management [35]. It is the accuracy of cost and effort calculation that enable quality growth of software at a later stage [1, 9]. With an effective estimate of software cost and effort, software developers can efficiently decide what recourses are to be used frequently and how efficiently these resources can be utilized. For efficient software, accurate software development parameters are required, these include effort estimation, development time estimation, cost estimation, team size estimation, risk analysis, etc.

    .Since the effort and cost estimation is done at an early stage of software development; hence a good model is required to calculate these parameters accurately [19].

    In past few decades several researchers have worked in the field of software effort estimation, and many conventional models were designed to estimate software, size and effort [6]. The models developed were based on mathematical formula and software development factors. One of the most frequently used model to estimate software effort is COCOMO developed by Berry Boehm. These models require inputs which are difficult to obtain at early stages of software development. Moreover these models take

    Values of software development factors based on experience and approximation, with zero reasoning Capability [2, 3]. Due to few such limitations of conventional algorithmic models,non- algorithmicmodels [21, 22, 23, 24] based on Soft Computing came into picture, which include Neural Network, Fuzzy logic and Genetic algorithms.

    The non-algorithm based algorithm [10,12,and 14] work with real life situations and a vast flexibility for software development factors was provided. In this paper a neural network technique using perceptron learning algorithm for software cost estimation which is based on COCOMO II model is proposed. Perceptron model is supervised model of neural network where weights are updated depending on the teachers response. Many researchers are working in implementing software effort and cost estimation in neural networks [4,5,and 13].

    The paper is organized in following sections: section 1 describes introduction, sections 2 and 3 describes COCOMO II model and neural network using perceptron learning rule. Section 4 discusses the related work and proposed neural network model and its algorithm is described in section 5. Experimental results and evaluation criteria are shown in section 6. Section 7 ends the paper with a conclusion.

  2. COCOMO II Model

There are many software cost estimation techniques

[27] and models which are classified as algorithmic and non-algorithmic approach [14,25,and 26].Software development efforts estimation is the process of predicting the most realistic use of effort required to develop or maintain software based on incomplete, uncertain and/or noisy input. Effort estimates may be used as input to project plans, iteration plans, budgets, and investment analyses, pricing processes and bidding rounds.The use of a repeatable, clearly defined and well understood software development process has, in recent years, shown itself to be the most effective method of gaining useful historical data that can be used for statistical estimation. In particular, the act of sampling more frequently, coupled with the loosening of constraints between parts of a project, has allowed more accurate estimation and more rapid development times. Estimating is defined as [35]

The process of forecasting or approximating the time and cost of completing project deliverables. Or The task of balancing the expectations of stakeholders and the need for control while the project is implemented

COCOMO (Constructive Cost Model) is a model that allows software project managers to estimate project cost and duration. It was developed initially (COCOMO 81) by Berry Boehm in early eighties. The COCOMO II model is a COCOMO81 update for software development during 1990s and 2000s. The COCOMO II Post Architectural Model [7, 8, and 11] predicts software development effort, Person Month (PM) as shown in equation 1.

PM = A. (Size) i. I .. (1)

It has a set of 17 multiplicative cost drivers (EM)[31, 32] and a set of 5 scaling cost drivers to determine the projects scaling exponent (SF). These scaling cost drivers replace the development modes (Organic, semidetached, or Embedded) in the original COCOMO 81 model, and refine the four exponent- scaling factors in Ada COCOMO. All of the cost drivers are described below. There are multiple factors that affect project cost. COCOMO II model defines 17 parameters called cost drivers that have a major influence on project cost.

  1. Personnel

    1. ACAP (Analyst Capability)

    2. APEX(Application Experience)

    3. PCAP(ProgrammerCapability)

    4. PLEX(Platform Experience)

    5. LTEX (Language and Tool Experience)

    6. PCON(PersonnelContinuity)

  2. Platform

    1. TIME(Time Constraint)

    2. STOR(Storage Constraint)

    3. PVOL(Platform Volatility)

  3. Product

    1. RELY(Required Software)

    2. DATA(Database Size)

    3. CPLX(ProductComplexity)

    4. RUSE(Required Reusability)

    5. DOCU(Documentation match to life cycle needs)

  4. Project

    1. TOOL ((Use of Software Tools)

    2. SCED (Required Development Schedule)

    3. SITE(Multisite Development Schedule)

Scale factors are new in COCOMO II. They modify second coefficient in formula 1 (coefficient b). The effect of scale factor is in 1.01 1.26 range.

  1. PREC (Precedence)

  2. PMAT(Process Maturity)

  3. TEAM(Team Cohesion)

  4. FLEX (Development Flexibility)

  5. RESL (Architectural and Risk Resolution)

Each driver can accept one of the six possible ratings

: Very Low(VL) , low(L) , Nominal (N), High(H) , Very High(VH) , and extra high (XH). Table 1 [11] shows the apriority values assigned to each rating before calibrating.

Driver

Sym

VL

L

N

H

VH

XH

PREC

SF1

0.05

0.04

0.03

0.02

0.01

0.0

FLEX

SF2

0.05

0.04

0.03

0.02

0.01

0.0

RESL

SF3

0.05

0.04

0.03

0.02

0.01

0.0

TEAM

SF4

0.05

0.04

0.03

0.02

0.01

0.0

PMAT

SF5

0.05

0.04

0.03

0.02

0.01

0.0

RELY

EM1

0.75

0.88

1.00

1.15

1.40

DATA

EM2

0.94

1.00

1.08

1.16

CPLX

EM3

0.75

0.88

1.00

1.15

1.30

1.65

RUSE

EM4

0.89

1.00

1.16

1.34

1.56

DOCU

EM5

0.85

0.93

1.00

1.08

1.17

TOME

EM6

1.00

1.11

1.30

1.66

STOR

EM7

1.00

1.06

1.21

1.56

PVOL

EM8

0.87

1.00

1.15

1.30

ACAP

EM9

1.5

1.22

1.00

0.83

0.67

PCAP

EM10

1.37

1.16

1.00

0.87

0.74

PCON

EM11

1.26

1.11

1.00

0.91

0.83

AEXP

EM12

1.23

1.10

1.00

0.88

0.80

PEXP

EM13

1.26

1.12

1.00

0.88

0.80

LTEX

EM14

1.24

1.11

1.00

0.9

0.82

TOOL

EM15

1.20

1.10

1.00

0.88

0.75

SITE

EM16

1.24

1.10

1.00

0.92

0.85

0.79

SCED

EM17

1.23

1.08

1.00

1.04

1.10

Table 1. Apriori Model Values

3. Neural Network

A Neural Network (NN) is an artificial, computational model that simulates biological neural networks.

Basically, a Neural Network consists of linked, artificial neurons which are typically grouped to input, hidden, and output layers. Depending on the network structure, different network types can be identified. In contrast to recurrent networks, Feed- Forward Networks represent a directed acyclic graph. Information is forwarded in one direction only, consecutively processed by the input, hidden, and output neurons. [15]

Neural networks consist of layers of interconnected nodes, where each node produces a non-linear function of its input. The nodes in the network are divided into the ones from the input layer going through the network to the ones at the output layer through some nodes in a hidden layer. The NN

process starts by developing the structure of the network and establishing the technique used to train the network with using an existing data set.

Therefore, there are three main entities:

  1. the neurons (nodes),

  2. the interconnection structure,

  3. the learning algorithm

Artificial neural networks are the interconnection of the artificial neurons. They are used to solve the artificial intelligence problems without the need for creating a real biological model. The neural network used in our approach is perceptron neural network [34].The perceptron is a network that learns concepts,

i.e. it can learn to respond with true (1) or False (0) for inputs presented to it, by repeatedly studying examples provided to it. This network weights and biases could be trained to produce a correct target vector when presented with the corresponding input vector. The training technique used is called the perceptron learning rule. Perceptron Neural network is selected due to its ability to generalize from its training vectors and work with randomly distributed connections. Vectors from a training set are presented to the network one after another. If the networks output is correct, no change is made. Otherwise, the weights and biases are updated using the perceptron learning rule. An entire pass through all of the input training vectors is called an epoch. When such an entire pass of training set has occurred without an error, training is complete. At this time any input training vector may be presented to the network, the network will tend to exhibit generalization by responding with an output similar to the target vectors close to the previously unseen input vectors. The activation function is one of the key components of the perceptron as in the most common neural network architectures. It determines based on the inputs, whether the perceptron activates or not. The perceptron takes all of the weighted input values and adds them together. If the sum is above or equal to some value (called the threshold) then the perceptron fires. Otherwise, the perceptron does not [19].

Figure 1.Neural Network Model 4.Related Work

Many researchers used their different non algorithmic models and different data sets to predict the software effort more correctly [28,29,and 32]. Most of the work in the application of neural network to estimate effort use backpropogation algorithm and cascade correlation network. [24]. ANN is a network of nonlinear computing elements called neurons which model the functionality of human brain. Anjana Bawa [24] proposed a general ANN architecture composed of 8 basic components. (i) Neurons, (ii) Activation function, (iii) Signal function, (iv) Pattern of connectivity, (v) Activity aggregation rule, (vi) Activation rule, (vii) Environment. The model implemented by Anupama Kaushik, et al. [19], is trained using perceptron learning algorithm. The test results from the trained neural network are compared with COCOMO model. Nasser Tadayon [17] explained the use of expert judgment and machine learning technique using neural network as well as referencing COCOMO II approach to predict the cost of software. Ch.Satyananda Reddy [20] adopted feed forward multilayer perceptron with linear activation function to avoid slow convergence problem that is a drawback of sigmoid activation function.

  1. Proposed Neural Network

    The main objective of the software cost and effort estimation using perceptron learning rule is to enhance the cost and effort estimation accuracy by introducing the concept of perceptron learning rule [33, 34] on COCOMO II model.

    The proposed structure of the neural network with perceptron learning is shown in figure 2.

    Neural networks consist of layers of interconnected nodes, where each node produces a non-linear function of its input. The neural network structure,

    as shown in figure 4, used in our work consists of three layes namely:

    1. Input layer: The use of the neural network to estimate PM (person-month) requires twenty-four input nodes in the input layer in the proposed neural network that corresponds to all EM and SF as well as two bias values.

    2. Hidden layer: In order to structure the network to accomplish the COCOMO II post-architecture model, a specific hidden layer and a sigmoid activation function with some pre-processing of data for input layer is considered

    3. Output layer: there is only one neuron at the output layer that will output the effort calculated from the network in terms of PM (Person/month).

The proposed structure of neural network is customized to accommodate the COCOMO II post architectural model. There are 5 scale factors denoted by SF and 17 effort multipliers denoted by EM. These inputs enter the network as weighted inputs. The effort is calculated using equation (1). The weights are initialized as wi=1 for i=1 to 17 and vj=0 for j=1 to 5. The values of bias1 is log (a) and bias2=1.01. All the inputs of Scale factors and effort multipliers are provided through the neurons of input layer as shown in figure 4 with bias.

As the propogation network uses summation of the inputs but the COCOMO II model uses its multiplication, a log function is used to neutralize them. So, the equation obtained by Berry Boehm model of effort estimation is modified as:

Log (Effort) = log (a*[size]b * i=1 15EMi)

The output obtained by the above equation [20], is compared using the activation function and the output signal is sent forward. According to the output of the activation function, the weights applied on the inputs are modified. When the output of activation function is 1, the difference between the actual effort and the effort calculated is found to check if it is the permissible limit or not. If it is in the permissible limit, the output is accepted else weights are adjusted. This completes one epoch of the project.

This work proposes an estimation model that incorporates Constructive Cost Model (COCOMO

II) with perceptron learning rule to provide more accurate software estimates at the early phase of software development. There are several on-going researchers working on implementing COCOMO using neural networks [ 16 , 17 , 18], but in this research a neural network model is trained using Perceptron learning approach to implement COCOMO II post architectural model.

This model uses the advantages of artificial neural networks such as learning ability and good interpretability, while maintaining the merits of the COCOMO II model. The aim of this study is to enhance the estimation accuracy of COCOMO model, so that the estimated effort is more close to actual effort. The proposed structure of neural network is customized to accommodate the COCOMO II post architectural model. There are 5 scale factors denoted by SF and 17 effort multipliers denoted by EM. The use of neural All the inputs of Scale factors and effort multipliers are provided through the neurons of input layer as shown in figure 4 with bias. The net input of scale factors and effort multipliers is calculated at each node of hidden layer.

Figure 2: architecture of neural network.

Initialization: The weights associated with effort multipliers are initialized as wi = 1 for I = 1 to 17, learning rate = 0.001 and bias1 =log (A). The inputs are received and multiply to the weights and provided to the network. The weights associated with scale factors vj = 0for j = 1 to 5 and bias 2 is 1.01.

Abbreviations used:

PM : Person per month A :

SIZE: Line of Code in KLOC SF : Scale factors

EM : Effort Multipliers

Q0 : Initial weight associated with scale

factors

P0 : Initial weight associated with scale

factors

Step 1: Calculate PM according to COCOMO II model of Berry Boehm

PMd = A. (Size) i . i

Step 2: Calculate output of hidden layer neuron as:

Net input to hidden layer node 1 (for scale factors ( wi is the weights)) = N1

((q0 + log (size)) Bias1 +

= P

F (net) i.e. output of hidden layer node 1 (for scale factors) = F (N1)

F (N1) = 1/ 1 + exp (-N1) = S

Net input to hidden layer node 2 (for effort multiplier ( vj are the weights)) = N2

(P0 Bias +

F (net) i.e. output of hidden layer node 2 (for effort multiplier) = F (N2)

F (N2) = 1/ 1 + exp (-N2) = T

Step 3: Calculate Net input to output layer node as: PMa = SP + TQ

Where P and Q are weights from hidden layer nodes

to output layer node. P =1 And, Q=1

Step 4: Check if (PMa>=PMd) then output =1 and

exit

Else output =0 and go to step 5

Step 5: weights are updated as.

Wt (new) = wt (old) + (desired o/p actual o/p) * input.

Go to step 2

For flowchart see Annexure 1.

  1. Estimation Criteria and Results

    The experiments are done with the proposed neural network and are implemented in Visual Studio 2010. In this thesis, a cost estimation model based on artificial neural networks is constructed.

    The evaluations consist of comparing the accuracy of the estimated effort with the actual effort. There are many evaluation criteria for software effort estimation among them here MRE (Magnitude Of relative Error) [36, 37] is used which is defined as:

    MRE = *100

    The MRE was calculated for each software project based on the above equation. Table 5 [Annexure 2] shows some of the experimental values which weretested. These values are then compared with the actual effort of the model. The comparison tells us about the efficiency of our network. Each row of the table corresponds to a project data which specifies the size of the project, actual effort of the project, the cost driver values and finally the effort calculated by our project. The input values are entered in the project through a GUI (Graphical User Interface). The model is implemented in Visual Studio.

    Table 6 [Annexure 3] shows the actual effort, the estimated effort and the MRE value for the experimented projects. Figure 4 is the graphical representation of the actual and calculated effort of the 15 projects. Through this graph it can be observed that the difference between the actual and the calculated effort is quite less which shows that the proposed algorithm is an accurate and precise algorithm.

    Figure 4: Actual and Calculated Effort

  2. Conclusion

    Neural network architecture for multilayer perceptron is used to implement COCOMO II model for software effort estimation and the learning rule used is Perceptron learning rule.

    The architecture of the network is multilayer and network is trained using Perceptron learning rule.

    Proposed algorithm takes inputs viz. Scale factors, Effort Multipliers and Size to calculate intermediate values of hidden layers and sigmoid activation function is applied to get the output of hidden neurons, and the output node produces 0 or 1 i.e. true or false based on the net input received at the output node. Final results are shown using Visual Studio 2010 and mean error is calculated.

    Thus, it is concluded that the use of artificial neural network algorithm to model the COCOMO II estimation algorithm is an efficient way to find the values of project estimates.

  3. Future Scope

Here the most popular neural network approach viz. Perceptron learning rule is suggested to predict the software cost estimation. To get accurate results the proposed neural network depends on adjustment of weights from input to hidden layer of the perceptron model. The proposed network is validated using 10 sample of different projects which is used to train and test the designed neural network and found that the Neural Network designed with perceptron learning rule performs better in terms of efficiency and estimation accuracy. This work can be extended by integrating with various supervised learning algorithms.

References

    Boehm, B.W., Software Engineering Economics, IEEE Transactions on software Engineering, SE-10, 1, pp. 4-21, January 1984.

  1. REVIC, Software Cost Estimating Model User's Manual, ver. 9, 1991

  2. Jones, Capers, "Software Cost Estimation in 2002", Crosstalk, The Journal of Defence Software Engineering, Vol. 15 No.6, June 2002

  3. Stamelos,etal.Estimating the development cost of custom software, information and management, V.40 n.8, pp729-741.

  4. R.W.Jensom, Extreme Software Cost Estimating, Crosstalk, The Journal of Defence Software Engineering, Vol. 15 No.6, June 2004

  5. A.Albreeht, Measuring Application Development Productivity, in IBM Application Development Symp.1979, pp83-92.

  6. Pressman, Roger, Software Engineering A Practitioner's Approach, McGraw Hill, Boston, MA, 2001

  7. Boehm, Barry, and others Software Cost Estimation With COCOMO II, Prentice Hall, Upper Saddle River, NJ, 2000

  8. Warburton, R. D. H. (1983). "Managing and predicting the costs of real-time software."IEEE Transactions on Software Engineering 9(5): 562-569.

  9. Symons (1991), Software Sizing and Estimating Mark II FPA, Wiley, UK.A.R.Venkatachalam, Software Cost Estimation Using Artificial Neural Networks. Proceedings of 1993 International Joint Conference on Neural Networks.

  10. SunitaDevnani-Chulani, Bradford Clark, Barry Boehm, Calibrating the COCOMO II Post Architectural Model.

  11. B. Boehm., Cost Models for Future Life Cycle Process: COCOMO2. Annals of Software Engineering. 1995 [25] Pankaj jalote, An Integrated Approach for Software Engineering. , Third Edition. ISBN: 978-81-7319-702-4.

  12. J.P. Lewis, Large Limits to software estimation, Software Engineering Notes, Vol. 26, No. 4, July 2001Stamelos, et al. Estimating The Development cost of custom software, Information and Management, v.40 n.8, pp.729-741, 2003

  13. Anthony Senyard et al., Software Engineering Methods for neural Networks. IEEE Proceedings of the tenth Asia Pacific Software Engineering Conference, (APSEC03), PAGES468-477, 2003.

  14. Karunanithi, N., etal. Using neural networks in reliability prediction, IEEESoftware, pp.53-59, 1992.

  15. Ali Idri , Samir Mbarki , Alain Abran ,Validating and Understanding Software Cost Estimation Models based on Neural Networks

  16. Nasser Tadayon, Neural Network Approach of Software Cost Estimation. Proceedings of the International Conference on Information Technology: Coding and Computing (ITCC05) 0-7695- -2315- 3/05

  17. Iman Attarzadeh , Amin Mehranzadeh , Ali Barati , Proposing an Enhanced Artificial Neural Network Prediction Model to Improve Accuracy in Software Effort Estimation , 2012 Fourth International Conference on Computational Intelligence, Communication Systems and Networks

  18. Anupama Kaushik , Ashish Chauhan , Deepak Mittal, Sachin Gupta , COCOMO Estimates using Neural Networks , I.J. Intelligent Systems and Applications, 2012, 9, 22-28 Published Online August 2012 in MECS

  19. Ch. Satyananda Reddy, KVSVN Raju,a Concise Neural Network Model for Estimating Software Effort,International Journal of Recent Trends in Engineering, Issue. 1, Vol. 1, May 2009

  20. Xishi Huang, Luiz F. Capretz, Jing Ren, Danny Ho, Neuro Fuzzy Model for Software Cost Estimation Proceedings of the Third International Conference On Quality Software (QSIC03)

  21. Ali Idri , Alain Abran , Samir Mbarki ,An Experiment on the Design of Radial Basis Function Neural Networks For Software Cost Estimation

  22. Harish Mittal , Pradeep Bhatia ,Optimization Criteria for Effort Estimation using Fuzzy Technique , CLEI ELECTRONIC JOURNAL, VOLUME 10, NUMBER 1, PAPER 2, JUNE 2007.

  23. Anjana Bawa , Mrs.Rama Chawala, Experimental Analysis of Effort Estimation Using Artificial Neural Network

  24. Ali Bou Nassif , Luiz Fernando Capretz, Danny Ho

    ,Software Effort Estimation In Early Stages of the Software life Cycle Using a Cascade Correlation Neural Network Model , 2012 13th ACIS International Conference on Software Engineering, Artificial Intelligence, Networking and Parallel/Distributed Computing

  25. L.A. Zadeh, 2002, From Computing with numbers to computing with words-from manipulation of measurements to manipulation of perceptions, Int. J. Appl. Math.Comut.Sci., 2002, Vol.12, No.3, 307- 324.

  26. Vahid Khatibi, Dayang N. A. Jawawi , Software Cost Estimation Methods: A Review , Journal of Emerging Trends in Computing and Information Sciences , Volume 2 No. 1, ISSN 2079-8407

  27. Prasad Reddy P.V.G.D , Sudha K.R., Rama Shree P & Ramesh S.N.S.V.S.C, Software Effort Estimation using radial Basis and Generalized Regression Neural Networks, Journal of Computing, Vol2, Issue5, May2010.

  28. ZhiweiXu,TaghiM.Khoshgoftaar, Identification of fuzzy models of software cost estimation, Fuzzy sets and systems 145(2005) 141-163.

  29. Mrinal Kanti Ghose, Roheet Bhatnagar and VandanaBhattacharjee, comparing Some Neural Network Models for Software Development Effort Prediction, IEEE, 2011.

  30. Ali Idri and Alan Abran, COCOMO cost model using fuzzy logic Proceedings of 7th International Confrence on Fuzzy Theory and Technology, Atlantic City, New Jersey, Feb27-Mar03,2000.

  31. Boehm, B.W.,et al., Cost models for future life cycle processes: COCOMO 2.0 Annals of Software Engineering on Software Process and Product Measurement, Amsterdam, 1995.

  32. Stephen Marsland,Jonathan Shapiro and Ulrich Nehmzow. Aself-organizing network that grows when required, Journal Neural Networks Vol15 Issue (8-9):1041-1058, 2002.

  33. S.N.Sivanandam,S.N.Deepa, Principles of Soft Computing,Wiley, India (2007).

  34. YogeshSingh,K.K.Aggarwal, Software Engineering and Estimation.

  35. B.A.Kitchenham, L.M.Pickard, S.G.MacDonell and M.J Shepperd, What Accuracy Statistics Really Measure. IEEE Proc. Software, vol.148, no.3, pp. 81-85, June, 2001.

  36. Braind L.C., Emam K.E. Surmann D. and Wieczorek I., An assessment and comparison of common software cost estimation modelling techniques, ISERN 1998-27.

Annexure 1.

Start

Initialization

InitializeWeig hts of SF as 0

Initialize EM Weights for all 17 neuron as 1

Input the value of 5 Scale Factors

Input the value of 17 Effort Multipliers

Calculate net input for hidden layer neuron 1

Calculate net input for hidden layer neuron 1

Calculate net input for hidden layer neuron 2

Calculate the output of hidden layer neuron 1 I.e. F(net1)

Calculate the output of hidden layer neuron 2 i.eF(net2)

Calculate the output of hidden layer neuron 1 I.e. F(net1)

Calculate the output of hidden layer neuron 2 i.eF(net2)

P Q

Output layerneuron

Initialize Weights from hidden to output layer neurons(S, T) as 1

Effort(PM) PS +QT

Effort(PM) PS +QT

If Effort(NN)>= Effort (COCOMO II)

NO

yes

All weights are updated

Annexure 2.

Final effort is displayed

End

PROJE CT NO.

SIZE (LCOC)

ACTUA L EFFORT (PM)

SCALE FACTORS

EFFORT MULTIPLIERS

CALCU LATED EFFOR T (PM)

VERY LOW SF

LOW SF

NOMIN AL SF

HIGH SF

VERY HIGH SF

EXTRA HIGH SF

VERY LOW

LOW EM

NOMIN AL EM

HIGH EM

VERY HIGH EM

P1

3

9

TEAM

PMAT

RESL

FLEX

PREC

DATA PVOL SITE TOOL

RELY RUSETIME

SCED, CPLX, STOR, PCAP

LTEX , AEXP , PEXP ,

ACAP , PCOM

, DOCU

11.76

5

P2

6

10.03

PREC

FLEX

PMAT

RESL

TEAM

RELY RUSE TIME

DATA PVOL

,SITE, TOOL

ACAP , PCOM , DOCU

SCED, CPLX, STOR, PCAP

LTEX , AEXP , PEXP ,

11.38

P3

12

12.97

PMAT

REASL

TEAM

PREC

FLEX

SCED, CPLX, STOR

, PCAP

LTEX , AEXP , PEXP ,

DATA , PVOL , SITE , TOOL

ACAP , PCOM

,DOCU

RELY , RUSE, TIME ,

12.97

P4

7

10.908

RESL

FLEX

TEAM

PMAT

PREC

LTEX AEXP PEXP

SCED, CPLX, STOR, PCAP

ACAP , PCOM , DOCU

RELY , RUSE, TIME ,

DATA , PVOL , SITE, TOOL

19.40

6

P5

10

12.554

FLEX

PREC

PMAT

RESL

TEAM

ACAP PCO M DOC U

LTEX , AEXP , PEXP ,

SCED, CPLX, STOR, PCAP

DATA , PVOL , SITE, TOOL

RELY , RUSE, TIME ,

22.98

P6

9

11.89

TEAM

REASL

PREC

FLEX

PMAT

TOOL DATA STOR

, SITE

SCED TIME RELY PCON

RUSE , DOCU , PVOL , PCAP , LTEX

ACAP , AEXP ,

CPLX , PEXP

12.79

P7

8

11.44

PREC

PMAT

RESL

RESL

TEAM

CPLX TIME TOOL

,RELY

SITE , PVOL , SCED , DOCU

STOR , DATA , ACAP , PCOM

LTEX , AEXP , PEXP ,

RUSE , PCAP

12.66

P8

14

11.82

PMAT

TEAM

PREC

FLEX

RESL

STOR

,DAT A,AC AP , PLEX

DOCU

,RUSE, PCOM

,APEX

SCED , PVOL , PCAP , TOOL

RELY , CPLX

TIME , SITE , LTEX ,

13.28

P9

12

12.61

FLEX

RESL

PMAT

PREC

TEAM

TOOL DATA STOR

, SITE

ACAP

,AEXP

CPLX , PEXP

SCED TIME RELY PCON

RUSE

,DOCU

, PVOL

, PCAP

, LTEX

16.33

P10

10

11.01

FLEX

PMAT

TEAM

PREC

RESL

STOR DATA ACAP PCO M

RUSE

,PCAP

LTEX , AEXP , PEXP ,

CPLX , TIME , TOOL , RELY

SITE , PVOL , SCED , DOCU

12.27

Table 1. Experimental Evaluation

Annexure 3.

PROJECT NO.

ACTUAL EFFORT (PM)

CALCULATED EFFORT (PM)

MRE

P1

9.00

11.76

30.66

P2

10.03

11.38

13.45

P3

12.97

12.927

0

P4

10.90

19.406

78.03

P5

12.55

22.98

83.10

P6

11.89

12.79

7.56

P7

11.44

12.66

10.66

P8

11.82

13.28

12.35

P9

12.61

16.33

29.50

P10

11.01

12.27

11.44

Table 2. Evaluation Criteria

Leave a Reply