Factors Affecting the Stakeholder Management Process in Construction Project

DOI : 10.17577/IJERTV7IS040216

Download Full-Text PDF Cite this Publication

Text Only Version

Factors Affecting the Stakeholder Management Process in Construction Project

Asma P

Department of Civil Engineering

Cochin College of Engineering and Technology, Valanchery Malappuram, Kerala, India

AbstractThe construction industries involved a diverse range of stakeholders. The stakeholders are a major source of uncertainty in construction project. The successful construction project management can be carried out only when the responsible managers take into account the potential influence of the project's stakeholders. This study used to identify and evaluate Critical Success Factors affecting stakeholder management in construction projects, using a questionnaire survey among construction professionals for validate 30 Critical Success Factors identified from the literature reviewed and Relative Importance Index and SPSS for analysis. Six groups were also confirmed. Decision making, Information input, Management support was highly ranked groups. Managing of all the factors will helps successful delivery of project.

Keywords Critical Success Factors, Stakeholder, Stakeholder management, Relative Importance Index, SPSS

  1. INTRODUCTION

    Today almost every project takes place in a context where stakeholders play a major role in the accomplishment of the tasks. Different stakeholders have different levels and types of investments and interests in projects in which they are involved. Often the project is sensitive to actions and decisions taken by the stakeholder. To ensure a successful project, the project team must identify the stakeholders, determine their requirements and expectations, manage their influence in relation to the requirements and identify the various factors affecting the stakeholder management.

    This study aims at identifying and evaluating CSFs for effective stakeholder management, 30 factors affecting stakeholder management are identified and they can be categorized in to six groups. The main factors affecting the stakeholder management process are, setting common goal and objective of the project, transparent evaluation of the alternative solution, Stakeholder involvement in decision- making, Formulate appreciate strategy to deal with stakeholder and Communication with the engaging stakeholder properly and frequently. The client and donor are the main key stakeholders, who have the most influence in the construction project. These factors that influences the outcome of successful stakeholder management process.

    Rosemary Sunny

    Assistant Professor, Department of Civil Engineering

    Cochin College of Engineering and Technology, Valanchery Malappuram, Kerala, India

    No

    Categories

    Critical Success Factors (CSFs)

    1

    Management Support

    Managing stakeholder with corporate social responsibilities

    Flexible project organization

    Project manager competences

    2

    Information Input

    Setting common goal and objective of the project

    Identifying stakeholders

    Exploring the stakeholder need and expectation

    3

    Stakeholder Assessment

    Assessing stakeholders attitude

    Understanding area of stakeholders interests

    Predicting the inuence of stakeholders

    Analyzing conicts and coalitions among stakeholders

    Evaluate the stakeholder power

    Evaluating the stakeholder legitimacy

    Understand the stakeholder urgency.

    Determine the stakeholder proximity

    Determine the stakeholder Knowledge.

    4

    Decision Making

    Transparent evaluation of the alternative solution based on stakeholder concern.

    Ensuring effective communication between

    the project and its stakeholder

    Formulate appreciate strategy to deal with stakeholder

    5

    Action And Evaluation

    Implementing the strategy based on schedule plans

    Flexibility in the implementing strategy to

    deal with stakeholder' reaction

    Evaluation the stakeholder satisfaction in

    terms of achievement of the stakeholder pre – project expectation

    6

    Continuous Support

    Communication with the engaging stakeholder properly and frequently

    Stakeholder involvement in decision-making

    Keeping and promoting an on-going relationship with stakeholder

    Analyzing the change of multiple stakeholder engagement and the relation

    Obtain support assistant from higher authorities

    Mutual trust and respect amongst the stakeholder

    Reduce the uncertainty

    Maintain alignment between or among the stakeholder

    Access to resource and knowledge

    TABLE 1.1 CSFs

    1. Objectives Of The Study

      To identify and rank the most common factors that affecting the stakeholder management process in construction project.

    2. Benefit Of The Study

      • By doing this study it is hoped that the delivery of the projects will be improved.

      • To know how to manage stakeholder properly and identified their problem in various stages in order to fulfill their needs and expectations.

  2. METHODOLOGY

    The adopted methodology that is used to accomplish this study is the following techniques: review of literatures related to stakeholder management, questionnaire for gathering data, and interview with professionals from the construction industry and data analysis by Relative Importance Index and SPSS.

    1. Relative Importance Index (RII)

      Likert scaling was used for ranking questions that have an agreed level. The respondents were required to rate the importance of each factor on a 5-point Likert scale using 1 for strongly disagree, 2 for disagree, 3 for neutral, 4 for agree and 5 for strongly agree. Then, the Relative Importance Index was computed using the following equation:

      Relative Importance Index = w/ AN

      Where W is the weighting given to each factor by the respondent, ranging from 1 to 5, "A" is the highest weight and N is the total number of samples. The relative importance index ranges from 0 to 1

    2. Cronbach's Alpha

    This method is used to measure the reliability of the questionnaire between each field and the mean of the whole fields of the questionnaire. The normal range of Cronbach's coefficient alpha () value between 0.0 and + 1.0, and the higher values reflects a higher degree of internal consistency.

    = Kr /1+ (K1)r

    The closer the Alpha () is to 1, the greater the internal consistency of items in the instrument being assumed. The formula that determines alpha is fairly simple and makes use of the items (variables), k, in the scale and the average of the inter-item correlations, r.

  3. RESULTS AND DISCUSSION

This part consists of results and discussion of factos that influence the stakeholder management process. These factors were grouped into six. The groups are management support, information input, stakeholder assessment, decision making, action and evolution and continuous support.

  1. Relative Importance Index (RII)

    Table 1.2: RII's for CSFs groups affecting the stakeholder management

    process

    NO

    CSFs

    RII

    RANK

    1

    Decision Making

    0.816

    1

    2

    Information Input

    0.802

    2

    3

    Management Support

    0.759

    3

    4

    Continuous Support

    0.66

    4

    5

    Action And Evaluation

    0.658

    5

    6

    Stakeholder Assessment

    0.594

    6

    From Table 1.2, it is shown that the Decision making was ranked in the first position by the respondents with Relative Importance Index equals (0.816), Information input was ranked in second position and Management Support, Continuous Support, Action And Evaluation, Stakeholder Assessment was ranked in next position by the respondent.

    Table 1.3: RII's for management support

    NO

    Management Support

    RII

    RANK

    1

    Managing stakeholder with corporate social responsibilities

    0.796

    1

    2

    Flexible project organization

    0.777

    2

    3

    Project manager competences

    0.704

    3

    From Table 1.3, it is shown that the Managing stakeholder with corporate social responsibilities was ranked in the first position by the respondents under this group as a critical factor influencing the management support in the stakeholder management process with Relative Importance Index equals (0.796), Flexible project organization was ranked in second position and Project manager competences was ranked in third position by the respondent.

    NO

    Information Input

    RII

    RANK

    1

    Setting common goal and objective of the project

    0.877

    1

    2

    Exploring the stakeholder need and expectation

    0.788

    2

    3

    Identifying stakeholders

    0.742

    3

    Table 1.4: RII's for Information Input

    From Table 1.4, it is shown that the Setting common goal and objective of the project was ranked in the first position by the respondents under this group as a critical factor influencing the Information Input in the stakeholder management process with Relative Importance Index equals (0.877), Exploring the stakeholder need and expectation was ranked in second position and Identifying stakeholders was ranked in third position by the respondent.

    Table 1.5: RII's for Stakeholder Assessment

    NO

    Stakeholder Assessment

    RII

    RANK

    1

    Understanding area of stakeholders

    interests

    0.680

    1

    2

    Assessing stakeholders attitude

    0.626

    2

    3

    Evaluate the stakeholder power

    0.623

    3

    4

    Evaluating the stakeholder legitimacy

    0.592

    4

    5

    Predicting the inuence of stakeholders

    0.588

    5

    6

    Determine the stakeholder Knowledge.

    0.576

    6

    7

    Analysing conicts and coalitions

    among stakeholders

    0.573

    7

    8

    Understand the stakeholder urgency.

    0.55

    8

    9

    Determine the stakeholder proximity.

    0.546

    9

    From Table 1.5, it is shown that the Understanding area of stakeholders interests was ranked in the first position by the respondents under this group as a critical factor influencing the Stakeholder Assessment in the stakeholder management process with Relative Importance Index equals (0.680), Assessing stakeholders attitude, Evaluate the stakeholder power, Evaluating the stakeholder legitimacy, Predicting the inuence of stakeholders, Determine the stakeholder Knowledge, Analysing conicts and coalitions among stakeholders, Understand the stakeholder urgency, Determine the stakeholder proximity was ranked in next position by the respondent.

    Table 1.7: RII's for Action and Evaluation

    NO

    Action And Evaluation

    RII

    RANK

    1

    Implementing the strategy based on schedule plans.

    0.746

    1

    2

    Evaluation the stakeholder satisfaction in terms of achievement of the stakeholder pre

    – project expectation.

    0.638

    2

    3

    Flexibility in the implementing strategy to deal with stakeholder'

    reaction.

    0.592

    3

    From Table 1.7, it is shown that the Implementing the strategy based on schedule plans. was ranked in the first position by the respondents under this group as a critical factor influencing the Action And Evaluation in the stakeholder management process with Relative Importance Index equals (0.746), Evaluation the stakeholder satisfaction in terms of achievement of the stakeholder pre – project expectation was ranked in second position and Flexibility in the implementing strategy to deal with stakeholder' reaction was ranked in third position by the respondent.

    NO

    Continuous Support

    RII

    RANK

    1

    Stakeholder involvement in decision- making.

    0.826

    1

    2

    Communication with the engaging stakeholder properly and frequently.

    0.812

    2

    3

    Obtain support assistant from higher authorities.

    0.65

    3

    4

    Keeping and promoting an on-going relationship with stakeholder.

    0.630

    4

    5

    Access to resource and knowledge

    0.630

    5

    6

    Reduce the uncertainty

    0.623

    6

    7

    Analysing the change of multiple

    stakeholder engagement and the relation.

    0.60

    7

    8

    Mutual trust and respect amongst the stakeholder

    0.60

    8

    9

    Maintain alignment between or among the stakeholder

    0.592

    9

    Table 1.8: RII's for Continuous Support

    Table 1.6: RII's for Decision Making

    NO

    Decision Making

    RII

    RANK

    1

    Transparentevaluation of the alternative solution based on stakeholder concern.

    0.842

    1

    2

    Formulate appreciate strategy to deal with stakeholder.

    0.815

    2

    3

    Ensuring effective communication between the project and its stakeholder.

    0.792

    3

    From Table 1.6, it is shown that the Transparent evaluation of the alternative solution based on stakeholder concern. was ranked in the first position by the respondents under this group as a critical factor influencing the Decision Making in the stakeholder management process with Relative Importance Index equals (0.842), Formulate appreciate strategy to deal with stakeholder was ranked in second position and Ensuring effective communication between the project and its stakeholder was ranked in third position by the respondent.

    From Table 1.8, it is shown that the Stakeholder involvement in decision-making was ranked in the first position by the respondents under this group as a critical factor influencing the Continuous Support in the stakeholder management process with Relative Importance Index equals (0.826), Communication with the engaging stakeholder properly and frequently, Obtain support assistant from higher authorities, Keeping and promoting an on-going relationship with stakeholder, Access to resource and knowledge, Reduce the uncertainty, Analyzing the change of multiple stakeholder engagement and the relation, Mutual trust and respect amongst the stakeholder and Maintain alignment between or among the stakeholder by the respondent.

  2. Cronbachs Coefficient Alpha

The values of Cronbach's Alpha for CSFs equal 0.834 which indicates an excellent reliability of the entire CSFs.

Table 1.9 Cronbach's Alpha for CSFs Groups

No

CSFs

Cronbach's Alpha

1

Management Support

0.257

2

Information Input

0.244

3

Stakeholder Assessment

0.745

4

Decision Making

0.437

5

Action And Evaluation

0.561

6

Continuous Support

0.738

From Table 1.9, it is shown that Cronbach's Alpha for each groups of CSFs.Continuous support group have higher reliability.

CONCLUSIONS

Stakeholders management has developed into an essential task of the project management process over the recent decades. Critical success factors for stakeholder management in construction projects will helps in achieving the desired results and their by project success can be attained. This paper presented a part results of a questionnaire survey, and aims to identify CSFs associated with stakeholder management. A total of 30 factors affecting the stakeholder management process were identified and setting common goal and objective of the project is the first ranked by the respondent, it consider has an most important critical success factors. Cronbach's

Alpha for CSFs equal 0.834 which indicates an excellent reliability of the entire CSFs.

REFERENCES

  1. Aki Aapaoja and Harri Haapasalo, A Framework for Stakeholder Identification and Classification in Construction Projects Open Journal of Business and Management, 2014, 2,pp. 43-55

  2. Eyiah-Botwe, E. Aigbavboa, C.O and Thwala, W.D, Critical Success Factors For Enhanced Stakeholder Management In Ghana The Scientific Journal for Theory and Practice of Socio-economic Development 2016, 5(10), pp. 153-170

  3. Eyiah-Botwe, E , Aigbavboa, C and Thwala, WD Mega Construction Projects: using stakeholder management for enhanced sustainable construction American Journal of Engineering Research e-ISSN: 2320- 0847 p-ISSN : 2320-0936 Volume-5, Issue-5, pp-80-86

  4. Jing Yang, Geoffrey Qiping Shen, Manfong Ho, Derek S. Drew and Albert P. C. Chan, Exploring Critical Success Factors For Stakeholder Management In Construction Projects Journal Of Civil Engineering And Management 2009 15(4), pp.337348

  5. Prof. Dr. Omar El-Naway, DR. Ibrahim Mahdi, Dr. Mohamed Badwy and Ahmed Gamal Al-Deen, Developing Methodology for Stakeholder Management to Achieve Project Success International Journal of Innovative Research in Science, Engineering and Technology Vol. 4,

    Issue 11, November 2015, pp.10652-10660

  6. Yogita M. Waghmare, Nikhil Bhalerao and S.V.Wagh Analysis of the Factors Affecting the Stakeholder Management Process in Building Construction Project International Journal of Innovative Studies in Sciences and Engineering Technology ISSN 2455-4863 Volume: 2 Issue: 7,July 2016, pp.48-56