Constrained Lot Sizing Problem for Continuous Demand Supply Chain

DOI : 10.17577/IJERTV4IS051206

Download Full-Text PDF Cite this Publication

Text Only Version

Constrained Lot Sizing Problem for Continuous Demand Supply Chain

Ghada E. Shedid, Amin K. El-Kharbotly, Mohamed M. Elbeheiry

Design and Production Engineering Department Ain Shams University

Cairo, Egypt

Abstract Lot sizing is of a prime importance in determining the performance of a supply chain especially in constraint environment due to internal and external factors. In the present work, a mathematical model is proposed to determine the optimum constrained lot sizing for a supply chain that includes a supplier, manufacturer, and retailer. Integer Nonlinear Programming (INLP) was used to solve centralized control supply chain for optimum profit. The results show that, for coordinated supply chain, the constraints have major role in determining the lot or batch size at each echelon. For different supply chain parameters, the manufacturers echelon dominates the lot sizing decisions while other downstream supply chain members have least effect on the decisions. The research extends to the study of the effect of different parameters on lot sizing decisions. Parameters studied are holding costs, order/set-up costs, demand, production rate, and material percent defective. For centralized case of a supply chain, it was proved that the cost elements along with the throughput production quality, considerably affect the lot size at each echelon.

Keywords Lot sizing; supply chain; integer non-linear programming; finite production; integer replenishment policy.

  1. INTRODUCTION

    Coordinating decisions across the supply chain network represents an important issue in supply chain operation. It was proved that lot sizing decisions among coordinated supply chain members to be a win-win situation for all concerned parties. The lack of orders coordination across the supply chain results in high costs [1-4]. It is recommended to avoid the inefficient decentralized supply chain, where decisions are made individually, towards more efficient centralized supply chains, such that decisions are made centrally by the key player of the network [5-7]. System wide optimization is applicable in case the supply chain is vertically integrated and partially or jointly owned [1].

    Considerable number of research work emphasizes on integrating a finite production or replenishment rate in their models. Wang et al. [7] investigated the penalty for treating the manufacturer as a buyer. They showed that the finite production rate should be included; especially, when the set- up cost largely exceeds the order cost. The production rate was considered in the supply chain inventory models as an input parameter [2, 7-10]. Eiamkanchanalai and Banerjee [11], and Sana [5,12] considered the production rate as a decision variable and the production cost as a function of the production rate. Khouja and Mehrez [13] considered the case of variable production rate and they assumed that both production cost and process quality are dependent on the production rate.

    The assumption of perfect quality for lot sizing models has been modified by many researchers ever since Rosenblatt and Lee [14], who proposed a model for economic production cycles with imperfect production processes. Eroglu and Ozdemir [15] proposed an economic order quantity model with imperfect quality items. Their model extended Salameh and Jabers model [16] by allowing shortages and maximum backorder level. Also, the effect of different percent defective on the optimal solution was examined. Chang and Ho [17], similar to Eroglu and Ozdemir [15], used the renewal reward theorem to derive the expected profit in order to obtain optimal lot size and backordering quantity.

    Shortage may or may not be allowed for cases of finite production rate and imperfect quality. In case that shortage is not permitted, the basic assumption was that the number of acceptable quality items exceeds the demand [8,9]. In case of shortage, several models considered backorder [10,15,17,18].

    The demand was considered and modeled in different ways. Pal et al. [19] and Taleizadeh et al. [20] considered price sensitive demand. Pal et al. [19] studied a joint price and lot-size determination problem over two cycle periods, and the retailer offers a discount to sell end of the season products. Taleizadeh et al. [20] expanded the problem to optimize the vendors production rate when the supply chain comprises of multiple-retailers and deals with deteriorating items. Chung

    [21] considered stock-and-warranty dependent demand, where the selling rate depends on both the stock level at the buyer and the offered warranty period.

    Kreng and Tan [9] developed a model for determining optimal replenishment decisions. They extended the models of Chung and Huang [22] and Huang [23] to allow for two-level trade credit, offered by suppliers to wholesalers and wholesalers to customers, while including finite replenishment rate. Su [10] relaxed the assumption of not permitting shortages and considered any shortages to be fully backlogged.

    Sana [5, 12] compared between the Stakelberg approach (backward induction method) and the collaborating system approach for lot size determination. Optimal solutions obtained by collaborating system approach proved to provide better results than that obtained by Stakelberg. The same conclusion was confirmed by Sana et al. [24] and it was further implemented on a more complex network structure. Wang et al. [7] also compared decentralized lot-sizing decisions with centralized (coordinated/integrated) decisions. They studied a supply chain with price-sensitive demand and investigated the effect of suppliers finite production rate on

    the pricing and lot-sizing decisions. Results showed that in a centralized problem optimal quantities are sensitive to the production rate, while its effect on the optimal retail price is very small.

    Lot splitting along the supply chain (e.g., integer number of batches or partial production lots are transported between supply chain members) reduces average inventory in the system [25]. It helps in implementing the time-based strategy when integrated with lot streaming techniques [26]. Different optimization techniques were used when lots are taken as integer multiplier of the number of batches (i.e., integer replenishment policy). Differential calculus is the most sought after solution technique for obtaining analytical solutions. It is used for the determination of the optimum lot/batch size for the downstream member. This value is constrained by the system other variables and parameters, so other algorithms are needed to obtain the optimum values for the correlated variables [5,7, 10]. When it comes to stipulating integer number of batches, rounding up or down the differentiation results is a matter for the optimization to decide. Integrating integer constraints turns the objective function to a discontinuous function; but when the objective cost function is proved to be convex with respect to the integer decision variables (i.e., continuous real domain is assumed), the two rounding values can be checked for optimization [4].

    Despite the popularity of the lot sizing problems, when infinite planning horizon is assumed the majority of the research articles addressed the problem as an inventory system management. The operational limitations and constrains controlling the production facility in supply chain was given little attention in the research work. Researchers who combined finite production rate with integer replenishment policy in their models have given almost no attention to the constraints that simultaneously affect both the number and size of batches. One of the frequenly discussed reasons for

    CR : unit raw material cost

    Cm : hourly production cost

    CL : unit shortage cost in case that (1- m)P<d

    Ch : unit holding cost of perfect quality raw material per period

    CH : unit holding cost of perfect quality end product at the manufacturer per period

    CHr : unit holding cost of end product per period at the retailers warehouse

    Cd : unit transportation cost between the supplier and the manufacturer

    CD : Unit transportation cost between the manufacturer and the retailer

    CO : order cost per batch

    CS : set-up cost per run

    Csh : shipment cost per replenished batch s : order defective percentage (0< s<1)

    m : end product defective percentage (0< m<1)

    Bs : maximum suppliers batch size (units/shipment)

    Bm : maximum manufacturers lot size (units/production run)

    Br : maximum retailers batch size (units/shipment)

    Ui : raw material inventory capacity UI : retailers inventory capacity Decision Variables

    Qmr : number of products per replenishment shipment transported between the manufacturer and the retailer

    x : number of order batches per production run (positive integer)

    z : number of replenishment shipments received by the retailer per production run (positive integer)

    Dependent Variables

    Qs : number of units per order shipment (i.e., economic order quantity)

    stock shortage is the withdrawal of imperfect items from inventory; since the occurrence of imperfection is assumed

    Q zQmr

    s x 1 1

    Qm

    x 1

    random. The present work proposes a mathematical model for a lot sizing problem that is implemented on a three-echelon supply chain that consists of a supplier, manufacturer, and

    s m s

    Qm : number of units per production run (i.e., economic production quantity)

    retailer. Coordinated delivery -production- replenishment decisions are made, so as the total profit of the chain is

    Qm

    zQmr

    1 m

    x 1

    s Qs

    maximized and demands are met. Both unconstrained and

    constrained strategies are addressed. Shortage due to

    T : production cycle time; it includes the time for pure consumption

    production limitations is allowed. A constrained Integer Non-

    Linear Program (INLP) was used to optimize the problem and

    T = zQmr

    1 m Qm

    to obtain optimal solutions. The behavior of the optimal solution was explored against system parameter changes.

  2. NOTATION AND ASSUMPTIONS

    1 m P ,d

    x 1 s 1 m Qs

    m

    1 P ,d

    1 m P ,d

    1. Notation

      Parameters

      y : number of production runs per period

      D : customer demand per period

      y U m

      U m 1 m P ,d

      SP : unit selling price

      Um : production capacity, in hours, per period

      U

      d : demand rate, d D

      m

      tm : production time

      P : production rate, P 1

      t m

      T zQmr

      X : total number of order shipments per period

      X = xy

      Z : total number of replenishment shipments per period

      Z= zy

    2. Model Assumptions

      • The supply chain consists of a single-supplier, single- manufacturer, and single-retailer for single-item production.

      • The planning horizon is infinite.

        0.5z Q t 1 P ,d

        2

        h

        mr m m

        C

        x 1 m

        m H

        Q mr z 1 z 2t m 1 P ,d C

      • The supplier has unlimited capacity, infinite 2

        1 m

        d m

        production rate, and order replenishments are instantaneous.

      • The screening of the raw material is done in the

        0.5 Qmr 1

        P ,d C

        O

        Hr

        marshaling area with no additional cost, only the good quality material is stored at the manufacturers raw material inventory. The defective parts are scraped

        x U m 1 m P ,d C zQmr

        U m 1 m P ,d C

        S

        zQmr

        without additional cost (s Qs).

        U 1 P ,d U 1 P ,d

        m m C m m C

        d

      • Production rate of the manufacturer equal to the consumption rate of the raw material.

      • The manufacturer has a finite production rate with a percent defective (m).

      • Defective finished products are detected

        Qmr

        U m 1 m

        sh 1

        D

        P ,d C

        m 1 m

        instantaneously during production and discarded.

      • Coordination mechanism of an equal cycle time is assumed between the supply chain members.

      • At each production run, the manufacturer produces a

        D U m 1 m P ,d C L

        subject to

        lot (Qm) that is ordered and delivered on integer number of equal-sized shipments. Number of order/replenished shipments per production run are

        zQmr

        1 m

        Bm

        decision variables.

        Bs

      • The first batch is shipped immediately after being produced. That is, the first shipment to the retailer is allowed to be made before the whole production lot is

    zQmr

    x 1 m 1 s

    produced. The succeeding batches are continuously produced and every batch is shipped right after the retailer depletes his inventory (the consumption of the preceding batch), see Fig. 1.

    zQmr

    x (1 m )

    U i

    • The production run starts after the manufacturer has depleted its excess inventory from the preceding cycle.

    • The inventory cost for the defective raw material and finished products are negligible.

    • The product consumption rate at the retailer equal to the retailers demand rate.

    • Cost of idle times at the manufacturer is not considered.

    • Lead time is negligible at different echelons.

  3. PROBLEM FORMULATION

    The following mathematical model provides the order/replenishment batch sizes, the production lot size, and their period frequencies that maximize the total profit of the supply chain.

    Q B ,U

    mr r I

    Qmr , x , z 1 and integer

    Objective function (1) includes the total income from which the total cost is deducted. The income is the product of the selling price per unit and the total amount delivered to the customer, which is the minimum amount of both the required and available. The total cost includes the following cost elements, respectively.

    Raw material cost: this is the cost of ordered raw material per period. It is the product of the number of order batches per period, order batch size, and the unit price ( xyQsC R ).

    Production cost: this is the cost of production of the delivered and scraped amount per period. It is the product of

    Max . f (Qmr , x , z ) U

    P

    m 1 m P ,d S

    the number production runs per period, the production lot size, the products standard production time, and the hourly

    U 1 P ,d U 1 P ,d t

    production cost ( yQmtmCm ).

    m m C m m m C

    R

    m

    1

    m 1 s

    1 m

    Transportation cost: It is the cost of transportation of material from the supplier to manufacturer and the transportation of products from the manufacture to the retailer ( xyQsCd zyQmrCD ). Transportation cost is charged on the incoming material and the outgoing products regardless of their quality.

    Shortage cost: In case the demand exceeds the production, unmet demand incurs a shortage cost. The unmet demand is assumed to be lost. This cost is the product of the difference between the customer demand per period and the total amount delivered to the retailer and the shortage cost pe unit (lost sales cost D zyQmr C L ).

    Constraint (2) restricts the amount of manufactured products per production run (Qm). Constraint (3) limits the order shipment size (Qs). Constraint (4) limits the raw

    material inventory level ( 1 s Qs ) to storage capacity.

    Fig. 1. Representation of inventory levels for the proposed model

    Raw material inventory holding cost: this is the cost of holding the ordered material that confirms to specifications in inventories at the manufacturer. It is the product of holding cost per unit per period and the average quantity per period. From Fig. 1, the average quantity stored per period can be detailed as follows:

    Q t

    1 m P ,d

    Constraint (5) limits the replenishment shipment size. Constraint (6) prevents division by zero and ensures integer number of shipments and integer shipment size.

  4. RESULTS AND ANALYSIS

    Decision variables in a centralized supply chain include economic order/production quantities and number of shipments delivered to the downstream members. These decision variables are correlated differently with each other depending on problem configuration and the parameters considered. The present work is concerned with investigating the effect of supply chain parameters and constraints on the lot sizing at optimal solutions.

    The results are obtained using FICO-Xpress software v7.8. Different software modules were used to verify the obtained results and to ensure the solution convergence. Brute-force search, as a problem-solving technique, was used after narrowing down the set of candidate solutions using an INLP

    Average quantity x0.5 1

    2 2

    1. s m zQ

      optimization module. Values of considered parameters are

      mr

      End product inventory holding cost at the manufacturer: this is the cost of holding the manufactured products that confirm to specifications in inventories at the manufacturer. It is the product of holding cost per unit per period and the average quantity per period. For detailed proof, please see Appendix A.

      End product inventory holding cost at the retailer: this is the cost of holding the products in inventories at the retailer. It is the product of holding cost per unit per period and the

      0.5zQmr 2

      given in Table (1).

      An initial analysis of the present mathematical model may lead to the following observations:

      • Fewer orders per period are placed with increased order quantity at higher ordering cost.

      • Lot size decreases with the increase in the holding cost.

      • Lot size may increase with production time.

      • Larger production lot sizes yield optimal solutions with increased demand.

        1. Sensitivity analysis

          average quantity per period (

          d T

          C Hr ).

          A series of experiments are conducted to study the effect of changing the model parameters on the joint total profit

          Ordering cost : this is the cost incurred by ordering

          batches from the supplier. It is the product of the total number of orders per period and the order cost ( xyCO ).

          Set-up cost: this is the cost incurred by setting-up batches during production. It is the product of total number of production runs per period and the set-up cost per run ( yCS ). Replenishment cost: this is the cost incurred by delivering batches to the retailer. It is the product of the total number of

          replenishment shipments per period and the replenishment

          (JTP) and the optimal decision variables. The analysis is made by changing one of the parameters (D, tm, Ch, CH, CHr, CO, CS, Csh, m, s, SP, Cm, CR, CD, Cd) by ±%50, ±30%, and

          ±10%from its assumed nominal value, while the rest of the

          parameters remain unchanged. The results are given in Tables (2,3) and profit percentage change is represented by radar charts in Figs. (2,3). The profit percentage change (PPC) is the percentage increase or decrease of the total profit (JTP) compared to the optimal profit at the nominal values of

          shipment cost ( zyC ).

          (JTP*), where

          JTP – JTP .

          sh PPC

          JTP

          x 100

          TABLE I. ASSUMED VALUES OF PROBLEM PARAMETERS

          Parameter Value Dimension Customer Demand (D) 1920 units/period Manufacturers production capacity (Um) 1920 hrs/period Production Time ™ 0.8 hrs/unit

          Holding cost of raw material (Ch) 3 $/unit per period

          It is evident from the model and experimental results that the profit has an inverse relation with CR, Cm, CD, Cd, Ch, CH, CHr, CO, CS, Csh, m, s, tm. It has direct relation with the SP, and D except in the case when the demand exceeds the

          available production capacity and consequently the shortage cost increases. Therefore, it is evident that the profit does not

          Holding cost of finished product at the

          5 $/unit per

          change with changing the CL provided that the demand does not exceed the available production capacity. The relation governing the available production with problem parameters is

          1 m

          manufacturer (CH)

          Holding cost of finished product at the retailer

          4

          period

          $/unit per

          (CHr)

          Ordering cost (CO)

          80

          period

          $/shipment

          Set-up cost (CS)

          140

          $/run

          Replenishment cost (Csh)

          90

          $/shipment

          Defective percentage at the manufacturer (m)

          0-2

          %

          Defective percentage from the supplier (s)

          0-2

          %

          Selling price (SP)

          100

          $/unit

          Material cost (CR)

          20

          $/unit

          Production cost (Cm)

          35

          $/hr

          Shortage Cost (CL)

          10

          $/unit

          Transportation cost (Cd, CD)

          1

          $/unit

          Max. allowed production run size (Bm)

          1500

          units/run

          Max. suppliers shipment size (Bs)

          500

          units/shipment

          Max. retailers shipment size (Br)

          400

          units/shipment

          Raw material inventory capacity (Ui)

          1000

          units

          as follows: Max. production per period

          t m

          U m .

          Retailers inventory capacity (UI) 1000 units

          It is worth knowing that the selling price, material cost, production cost, and transportation cost affect the optimum profit but do not affect the optimal solution as shown in Table (3). The Shortage Cost does not affect both the profit and the decision variables, since the nominal values represent the case where the production volume exceeds the demand.

          Table (2) shows that the cost elements and the throughput production quality considerably affect the lot size at each echelon.

          1. b)

          Fig. 2. Profit% change against different parameters. a) reduced parameter

          values, b) increased values

          a) b)

          Fig. 3. Profit% change with different parameters after hiding the dominating parameters. a) reduced values, b) increased values

          The degree of profit sensitivity is affected by the values of different parameters under consideration. It depends on the model assumptions, the way costs are incurred, and the parameter relative values. For instance, the profit has an absolute importance relation with SP, D, tm, and CR as shown in Figs. 2(a,b). Figs. 3(a,b) show that the profit is affected largely by m, and moderately by Csh, s, CH. and weakly by CO, Ch, CHr, and CS.

          Effect of percent defective at the manufacturer:

          Manufacturing percent defective highly affecs the lot size at the manufacturer (Fig. 4). It has lower effect on the suppliers batch size and minor effects on the retailers batch size (Fig. 5). Optimizing supplier batch size follow certain pattern; it generally increases up to a certain value then decreases and resumes its increase as the percent defective increases. This is because, as shown in Fig. 6, the integer number of shipments per production run increases as the percent defective increases.

          Fig. 4. The effect of percent defective on the economic production quantity

          Fig. 5. The effect of percent defective on economic shipment sizes

          Fig. 6. The effect of percent defective on number of shipments

        2. Effect of Integrating Different Constraints with the proposed Lot Sizing Problem

        Studying the effect of integrating functional constraints with the lot sizing problem is important for obtaining practical optimal solutions. The proposed mathematical model is optimized for profit while considering different constraints.

        Effect of Batch/Lot Size Constraints: Fulfilling different constraints causes extra costs, see Fig. 7. Comparing Figs. 8-

        10 shows that the lot size constraint at the manufacturer dominates the change in both the supplier and retailers batch sizes. The suppliers batch size is highly affected by manufacturing lot size constraint when compared with that of the retailer, since the optimal supplier batch size is controlled by the optimal values of both integer number of shipments x and z.

        Fig. 7. The effect of echelon constraints on the profit

        Fig. 8. The effect of manufacturers related constraint on the batch optimal decisions

        Fig. 9. The effect of suppliers related constraint on the manufactures economic production quantity and on the retailers optimal shipment size

        Fig. 10. The effect of retailers related constraint on the manufactures economic order and production quantities

        Effect of Production Capacity and Different Production Rates: Constrained capacity of the manufacturer drastically changes the production lot size. It has a consequent effect on suppliers batch size more than that on the retailers batch size. In other words, the retailer may be the least affected echelon with regard to lot sizing within the supply chain for constrained conditions (Fig. 11). Also, increasing the production rate (or decreasing the production time) considerably affects the lot size at the manufacturer. The higher the production rate, the lower the lot size (Fig. 12). The batch size at the supplier and the retailer slightly changes; however, the change at the supplier is higher than that at the retailer. The reason for this is that the higher the production rate, the higher the products inventory holding cost at the manufacturer and the lower the raw material inventory holding cost.

        Fig. 11. The effect of production capacity on the optimal lot/batch size

        Fig. 12. The effect of production time on the optimal lot/batch size

  5. CONCLUSION

The goal of the lot sizing problem is to establish a policy that would maximize profit or minimize relevant costs when implemented. The optimal policy depends on the assumptions made about the way costs are incurred, how demand is satisfied, and any limitations and constraints that face the supply chains operations. Calculus differentiation is suitable to obtain exact solutions for shipment sizes in non-constrained system. In real industrial problems, lot sizing decisions are made under certain constrains and limitations. There might be

constrains on the size and number of shipments, size and number of production lots, space and monetary limitations, etc. The present proposed model considers constrained situations seeking more feasible and practical decisions. It considers a multi-echelon supply chain where ordering and inventory management decisions have to be made in multiple locations. The demand occurs continuously at a constant and known rate. Integer non-linear programming was used to optimize the problem

The results show that, for constrained model, constraints at any echelon affect the lot sizing decisions at the other echelons. Increased demand rate; generally, increases the total number of shipments per period and consequently, the order and replenishment shipment quantities are determined. However, it does not always guaranty an increase in the number of production runs per period. Meanwhile, any increase in the number of shipments per production run results in a decrease of number of production runs per period. It was also found that the manufacturer is the key decision maker when maximizing the total profit of the system.

The present work can be extended for soft constraints, stochastic parameters, and more complex networks.

TABLE II. RESULTS OF SENSITIVITY ANALYSIS ON DIFFERENT PARAMETERS

Parame te r

-50%

-30%

-10%

PPC

T

Q s

Q m

Q mr

xy

zy

PPC

T

Q s

Q m

Q mr

xy

zy

PPC

T

Q s

Q m

Q mr

xy

zy

D

-50.56%

570

297

291

285

3.4

3.4

-30.42%

594.3

433

424

208

3.2

6.5

-10.17%

726.7

340

667

218

5.3

7.9

t m

30.68%

404

421

412

404

4.8

4.8

18.33%

494

514

504

247

3.9

7.8

6.09%

690

359

704

230

5.6

8.3

m

1.09%

696

359

703

232

5.5

8.3

0.66%

696

360

706

232

5.5

8.3

0.22%

696

362

709

232

5.5

8.3

C sh

0.51%

750

390

765

150

5.1

12.8

0.29%

732

381

747

183

5.2

10.5

0.09%

776

404

792

194

4.9

9.9

s

0.47%

696

359

710

232

5.5

8.3

0.28%

696

360

710

232

5.5

8.3

0.09%

696

362

710

232

5.5

8.3

C H

0.44%

1028

357

1049

257

5.6

7.5

0.25%

968

336

988

242

6.0

7.9

0.08%

708

369

722

236

5.4

8.1

C

0.28%

699

243

713

233

8.2

8.2

0.16%

848

294

865

212

6.8

9.1

0.05%

681

355

695

227

5.6

8.5

C h

0.28%

872

454

890

218

4.4

8.8

0.16%

844

439

861

211

4.5

9.1

0.05%

702

365

716

234

5.5

8.2

C Hr

0.27%

753

392

768

251

5.1

7.6

0.16%

723

376

738

241

5.3

8.0

0.05%

702

365

716

234

5.5

8.2

C S

0.22%

651

339

664

217

5.9

8.8

0.13%

666

347

680

222

5.8

8.6

0.04%

687

358

701

229

5.6

8.4

Parame te r

+10%

+30%

+50%

PPC

T

Q s

Q m

Q mr

xy

zy

PPC

T

Q s

Q m

Q mr

xy

zy

PPC

T

Q s

Q m

Q mr

xy

zy

D

10.24%

977.3

373

1097

215

5.9

9.8

21.61%

1200

383

1500

210

6.4

11.2

17.41%

1200

383

1500

210

6.4

11.2

t m

-6.03%

1025

356

1046

205

5.6

9.4

-24.03%

1553.6

305

1494

183

6.2

9.9

-47.08%

1792.7

305

1494

183

5.4

8.6

m

-0.22%

693

362

709

231

5.5

8.3

-0.66%

690

361

708

230

5.6

8.3

-1.11%

690

363

711

230

5.6

8.3

C sh

-0.08%

711

370

726

237

5.4

8.1

-0.24%

741

386

756

247

5.2

7.8

-0.39%

768

400

784

256

5.0

7.5

s

-0.10%

696

363

710

232

5.5

8.3

-0.29%

696

365

710

232

5.5

8.3

-0.48%

696

366

710

232

5.5

8.3

C H

-0.08%

678

353

692

226

5.7

8.5

-0.22%

651

339

664

217

5.9

8.8

-0.36%

627

326

640

209

6.1

9.2

C O

-0.05%

702

365

716

234

5.5

8.2

-0.14%

828

431

845

207

4.6

9.3

-0.22%

844

439

861

211

4.5

9.1

C h

-0.05%

681

355

695

227

5.6

8.5

-0.14%

864

300

882

216

6.7

8.9

-0.22%

844

293

861

211

6.8

9.1

C Hr

-0.05%

681

355

695

227

5.6

8.5

-0.14%

772

402

788

193

5.0

9.9

-0.23%

752

392

767

188

5.1

10.2

C S

-0.04%

702

365

716

234

5.5

8.2

-0.12%

920

319

939

230

6.3

8.3

-0.18%

1040

361

1061

208

5.5

9.2

Case of (1-m)/tm<d

TABLE III. RESULTS OF SENSITIVITY ANALYSIS ON DIFFERENT PARAMETERS

Parame te r

Profit Pe rce ntage C hange

De cision variable s

-50%

-30%

-10%

+10%

+30%

+50%

S P

-106.57%

-63.94%

-21.31%

21.31%

63.94%

106.57%

T

696

C m

30.45%

18.27%

6.09%

-6.09%

-18.27%

-30.45%

Q s

362

C R

22.19%

13.32%

4.44%

-4.44%

-13.32%

-22.19%

Q m

710

C d

1.11%

0.67%

0.22%

-0.22%

-0.67%

-1.11%

Q mr

232

C D

1.07%

0.64%

0.21%/p>

-0.21%

-0.64%

-1.07%

xy

5.5

C L

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

zy

8.3

Income < Total Cost, minimum selling price is 53% of the nominal value.

Appendix A. Average end product inventory per period at the manufacturer is given by the following equation

2 2 z 1

2 1 P

Q z 2t

zQmr m

1 m P ,d

: mr z 1 m 1 m P ,d

2 z

z 1

2 1 m

1 m P

1

P ,d

The following is the general form for the total end product inventory at the manufacturer per dominant cycle (i.e., the cycle that is determined by the minimum rate), see Fig. 1A.

m

r

zQm 2 z 1 z 2

1 z 1

z 2Q 2

2 1

P ,d

1 m P

zQ

2

mr

m

m

mr 1 P

1 m P ,d

21 m P

Manufacturers average inventory per period

2

Qmr

1 2 … z 1

zQ 2

z 1

z 2t

1

mr m

1 m P ,d

2 1

m

,d

1 m

T

Since the summation of an arithmetic series is as follows:

t m

n 1 n

a kd 2 2a n 1d

zQmr 2 z 1 z 2t m 1 m P ,d

k 0

z 1 z

2 1 m P ,d

1 m

zQmr

2

k 1 2 … z 1 z 1

z 2 t

k 0

Qmr z 1 m 1 P ,d #

m

Then,

2 2

2 1 m

zQ

2 1 z 1

z Qmr

In case the production exceeds the demand (Fig. 1A,a); the

m

mr 1 P

2

1 m P ,d

21 m P

manufacturers average inventory holding cost per period is

as follows: Qmr z 1 z 2t m d C

z z 1

Qmr

2 1 H

m

2 1 P ,d

m

In case the demand exceeds the production (Fig. 1A,b); the manufacturers average inventory holding cost per period is

as follows:

zQmr 2

m T H

21 m

  1. 1 C

Qmr

2

C H .

a) b)

Fig. 1A. Accumulated inventory at the manufacturer, a) Case (1- m)P>d b) Case (1- m)P<d

REFERENCES

  1. M. Khouja, Optimizing inventory decisions in a multi-stage multi- customer supply chain, Transportation Research Part E 39, pp. 193 208, 2003.

  2. M.E. Seliaman and Ab.R. Ahmad, Optimizing inventory decisions in a multi-stage supply chain under stochastic demands, Applied Mathematics and Computation, vol. 206, pp. 538542, 2008.

  3. J.A. Muckstadt and A. Spara, Principles of inventory management: When You Are Down to Four, Order More, Springer Series in Operations Research and Financial Engineering, 2010.

  4. S.D. Lee and Y.C. Fu, Joint production and delivery lot sizing for a make-to-order producerbuyer supply chain with transportation cost, Transportation Research Part E, vol. 66, pp. 2335, 2014.

  5. S.S. Sana, A collaborating inventory model in a supply chain, Economic Modelling, vol. 29, pp. 2016-2023, 2012.

  6. Q. Duan and W. Liao, Optimization of replenishment policies for decentralized and centralized capacitated supply chains under various demands, Int. J. of Production Economics, vol. 142, pp. 194204, 2013.

  7. C.X. Wang, R.B. Huang, and Q.L. Wei, Integrated pricing and lot- sizing decision in a two-echelon supply chain with a finite production rate, Int. J. of Production Economics, vol. 161, pp. 44-53, 2015.

  8. Y.S.P. Chiu, K.K. Chen, F.T Cheng, and M.F. Wu, Optimization of the finite production rate model with scrap, rework and stochastic machine breakdown, Computers and Mathematics with Applications, vol. 59, pp. 919-932, 2010.

  9. V.B. Kreng and S.J. Tan, Optimal replenishment decision in an EPQ model with defective items under supply chain trade credit policy, Expert Systems with Applications, vol. 38, pp. 98889899, 2011.

  10. C.H. Su, Optimal replenishment policy for an integrated inventory system with defective items and allowable shortage under trade credit, Int. J. of Production Economics, vol. 139, pp. 247256, 2012.

  11. S. Eiamkanchanalai and A. Banerjee, Production lot sizing with variable production rate and explicit idle capacity cost, Int. J. of Production Economics , vol.59, pp. 251-259, 1999.

  12. S.S. Sana, A production-inventory model of imperfect quality products in a three-layer supply chain, Decision Support Systems, vol. 50, pp. 539547, 2011.

  13. M. Khouja and A. Mehrez, Economic production lot size model with variable production rate and imperfect quality, J. of the Operational Research Society, vol. 45, no. 12, pp. 1405-1417, 1994.

  14. M.J. Rosenblatt and H.L. Lee, Economic production cycles with imperfect production processes, IEE Transactions, vol. 18, pp. 4855, 1986.

  15. A. Eroglu and G. Ozdemir, An economic order quantity model with defective items and shortages, Int. J. of Production Economics, vol. 106, pp. 544549, 2007.

  16. M.K. Salameh and M.Y. Jaber, Economic production quantity model for items with imperfect quality, Int. J. of Production Economics, vol. 64, pp. 5964, 2000.

  17. H.C. Chang and C.H. Ho, Exact closed-form solutions for optimal inventory model for items with imperfect quality and shortage backordering, Omega, vol. 38, pp. 233237, 2010.

  18. H.M. Wee, J. Yub, and M.C. Chena, Optimal inventory model for items with imperfect quality and shortage backordering, Omega, vol. 35, pp. 711, 2007.

  19. B. Pal, S.S. Sana, and K. Chaudhuri, Joint pricing and ordering policy for two echelon imperfect production Inventory model with two cycles, Int. J. of Production Economics, vol. 155, pp. 229238, 2014.

  20. A.A. Taleizadeh, M. Noori-daryan, and L.E. Cárdenas-Barrón, Joint optimization of price, replenishment frequency, replenishment cycle and production rate in vendor managed inventory system with deteriorating items, Int. J. of Production Economics, vol. 159, pp. 285295, 2015.

  21. C.J. Chung, Investigating imperfect process and demand effects on inspection scheduling and supply chain replenishment policy, Computers & Industrial Engineering, vol. 64, pp. 3144, 2013.

  22. K.J. Chung and Y.F. Huang, The optimal cycle time for EPQ inventory model under permissible delay in payments, Int. J. of Production Economics, vol. 84, pp. 307318, 2003.

  23. Y.F. Huang, Optimal retailers ordering policies in the EOQ model under trade credit financing, J. of the Operational Research Society, vol. 54, pp. 10111015, 2003.

  24. S.S. Sana, J.A. Chedid, and K.S. Navarro, A three layer supply chain model with multiple suppliers, manufacturers and retailers for multiple items, Applied Mathematics and Computation, vol. 229, pp. 139150, 2014.

  25. C.H. Glock, E.H. Grosse, and J.M. Ries, The lot sizing problem: A tertiary study, Int. J. of Production Economics, vol. 155, pp. 3951, 2014.

  26. J.H. Changy and H.N. Chiuz, A comprehensive review of lot streaming, Int. J. of Production Research, vol. 43, pp 15151536, 2005.

Leave a Reply