- Open Access
- Total Downloads : 232
- Authors : P. U. Okorie, D. M. Ezekiel
- Paper ID : IJERTV3IS20570
- Volume & Issue : Volume 03, Issue 02 (February 2014)
- Published (First Online): 15-02-2014
- ISSN (Online) : 2278-0181
- Publisher Name : IJERT
- License: This work is licensed under a Creative Commons Attribution 4.0 International License
Assessment of Reliability Indices of Abuja Distribution Network
P. U. Okorie , D. M. Ezekiel
Department of Electrical Engineering, Ahmadu Bello University, Zaria.
Abstract Assessment of customer power supply reliability is an important part of distribution system operation and planning. Analysis of outage data from a practical distribution system is performed in order to assess the reliability indices. The aim of this paper is to assess the reliability and analysis customer power supply of Abuja metropolis, evaluating with SAIDI, SAIFI and CAIDI. The report consists of measuring past performance, including reliability indices; sources of data; and existing methods for reliability analysis. The main conclusion of the report is that, Abuja municipal city reliability network measured failed below the average industrial city: SAIDI, 392.88 hrs of duration in 2007, CAIDI, 1.82 hrs while SAIFI records 215.47.
Keywords Reliability, Distribution system reliability, Availability, Failure and Reliability indices.
-
INTRODUCTION (Heading 1)
Reliability concerns are often split into three categories: Adequacy, Security and Quality. Adequacy is the capacity and energy to meet demand; Security is the ability to withstand disturbances; and Quality is the acceptable frequency, voltage and harmonic characteristics. There are more than forty reliability indices, the most common one include SAIDI, SAIFI, CAIDI, MAIFI, ASAI etc, other common indices that measure unavailability include ASUI which is complement of ASAI, EENS, and AENS. The indices used in this report are SAIDI, SAIFI and CAIDI [1]. These indices are generallyyearly average of interruption of frequency and duration. They attempt to capture the magnitude of disturbances by load lost during each interruption. We used these indices; CAIDI, SAIFI and SAIDI method because there were best suited to the subject discussed. These reliability indices are among the following.
-
Customer Average Interruption Duration Index (CAIDI) is an indicator of average interruption duration, or the time to restore service to interrupted customers.
-
System Average Interruption Frequency Index (SAIFI) is an indicator of average service interruption frequency experienced by customers on a system.
-
System Average Interruption Duration Index (SAIDI) is a composite indicator of outage frequency and duration and is calculated by dividing the customer minutes of interruptions by the number of customers served on a system. Mathematically, SAIDI is the product of SAIFI and CAIDI. Thus, a SAIDI of 100 may be achieved by a SAIFI of 1 and a CAIDI of 100, or by a SAIFI of 1.25 and a CAIDI of 80
-
-
RELIABILITY STUDIES OF ABUJA DISTRIBUTION NETWORK
The power system is vulnerable [2] to system abnormalities such as control failures, protection or communication system failures, and disturbances, such as lightning, and human operational errors. Therefore, maintaining a reliable power supply is a very important issue for power systems design, operation and planning [3]. The results of reliability assessment of distribution systems supplying electricity of various consumers in Abuja Federal Capital Territory are presented and discussed. The various reliability indices computed for the distribution systems in all the districts of Abuja Federal Capital Territory are based on the methodology described. The major causes of power supply problems in Abuja have been identified and also summarized in Tables 1 to 4. There are a number of problems associated with transmission, distribution and consumption of electricity in a rural area. A study into the problems of power supply shows that disturbance on the commercial mains power supply can be categorized into the following: (i) Weather problem, (ii) Human problem and (iii) Planned problem. The computed annual outages and their durations between 2002 and 2007 according to fault type are given in Table 1.
Table1: outage and duration of faults types for the Abuja distribution network, 2002 2007 (Okorie, 2009)
S/N
Nature & causes of fault due to bad joint
2002
2003
2004
2005
2006
2007
Avg. outage & duration /year
Freq.
Duration
Freq.
Duration
Freq.
Duration
Freq.
Duration
Freq.
Duration
Freq.
Duration
Freq.
Duration
1
UG cable
120
158.74
87
224.38
142
280.46
56
305.79
176
545
98
381.16
113.2
315.92
2
Cable sparked by diggers
5
45.61
5
38.12
5
38.34
4
55.45
6
51.37
2
14.35
4.5
40.54
3
Pole and equipment damaged by vehicles
28
176.82
35
130.23
31
234.34
27
237.6
79
379.3
17
241.23
36.2
233.25
4
Failure of line due to jumper or cross arm
1079
558.1
286
476.6
472
331.04
349
454.81
551
720.3
422
804.82
526.5
557.6
5
Tree falling on line
171
218.91
21
105.28
56
262.13
78
218.5
52
295.5
55
338.99
72.2
239.88
6
Faulty transformer
32
374.6
11
253.37
26
435.32
33
261.13
30
426.6
9
590.36
23.5
390.23
7
Faulty switchgear/panel
10
69.54
19
54.02
20
86.12
29
116.41
37
98.74
16
105.97
21.8
88.47
8
Faulty tripping unit
151
138.06
54
124.79
165
110.43
30
53.72
95
269.6
6
15.73
83.5
118.72
9
Earth fault
938
231.53
441
209.08
<>1689 756.4
2235
822.86
805
1467
1178
1478.3
1241.
3
827.57
10
Over current
846
226.36
342
254.04
1328
498.93
1750
702.7
785
573.8
1197
1070.9
1041.
3
554.48
11
Other causes
219
274.02
40
168.96
80
382.53
156
364.13
119
336.6
232
851.38
141
396.26
12
Yearly total
3599
2472.3
1341
2038.87
4014
3416
4747
3593.1
2735
5164
3232
5893.2
3278
3762.91
-
RELIABILITY INDICATORS FOR MEASURING SERVICE QUALITY PERFORMANCE MODELING
These are the five key reliability indicators recently introduced for the purpose of assessing distribution reliability performance. These are the reliability indices used by the Floridas Investor owned electric utilities (IOU) for assessing and auditing their performance in electricity distribution system [5]. Such reliability indicators are listed below:
-
Customer Average Interruption Duration Index (CAIDI);
-
System Average Interruption Frequency Index (SAIFI);
-
System Average Interruption Duration Index (SAIDI);
-
Momentary Average Interruption Event Frequency Index/Indicator (MAIFI);
-
Customers Experience More than Five Interruptions (CEMI5).
The mathematical computation is as follows:
CAIDIik =
SAIFI =
Sumof all customers min utes int errupted (CMIik ) 1
Total number of customersint erruptions (CIik )
Total number of customer' s int erruption (CIik ) 2
ik
SAIDIik MAIFIE
=
ik=
Total number of customers served (Cik )
Sumof all customers min utes int errupted (CMIik ) 3
Total number of customers served (Cik )
Sumof all customers momentaryint erruption events (CMEik ) 4
Total number of customers served (Cik )
CEMI5ik = 5
Customers exp erienced morethan 5int erruptions (CEM 5ik ) x Total number of customers served (Cik )
100%
i = 1, 2, 3 m
k = 1, 2, 3 n wherei denotes year and
k denotes kth district
These five performance indices express interruption statistics in terms of system customers. A customer here can be either feeder, or an individual, firm, or organization who purchases electric services at one location under one rate classification, contract or schedule. If service is supplied to a customer at more than one location, each location shall be counted as a separate customer.
Furthermore, the well known basic reliability indices are defined in equations ( 6 ) to ( 12 ).
1
Mean Time To Failure (MTTF) =
Mean Time To Repair (MTTR) =
6
Failure Rate
Fault Duration
7
No. of Outage
Mean Time Between Failure (MTBF)= MTTF + MTTR 8
1
Failure Rate () = Repair Rate () = Availability =
Unavailability =
9
MTTF
1
10
MTTR
11
12
The computations of the above basic reliability indices required acquisition of fields data on distribution component failure statistics over the desired time frame.
-
-
ANALYSIS OF DATA COLLECTED USING RELIABILITY INDICES
Tables 2 to 4, and Figure 2 summarize the results of several reliability analysis carried out in respect of electricity
supplied to the customers in Abuja municipal city and satellite towns from 2002 -2007. Herein, service reliability indices (Failure rate, MTTR, MTTF, MTBF, CAIDI, SAIDI and SAIFI) were computed for all the five districts and for each year of the study period using equations (1) to (12).
Table 2: Reliability indices of Abuja distribution network for the specified study period *[4]
S/No
Parameters
Wuse District
Garki
District
Kubwa
District
Karu District
G/Lada
District
Abuja
Metropolis
1
Total no. of
failure/outages
5558
3676
552
1151
1091
19681
2
Total outages
duration
4208.49
5003.99
1404.28
1890.71
2480.15
21496.88
3
Average duration of outage (hrs/yr)
(MTTR)
1062.35
1252.21
703.34
945.36
1240.08
3582.81
4
Failure rate
158.618 x 10-3
104.908 x 10-3
31.507 x 10-3
65.696 x 10-3
62.215 x 10-3
374.448 x 10-3
5
Mean Time To
Failure (MTTF)
6.322
9.532
31.739
15.222
16.073
2.671
6
Mean Time
Between Failure
1068.85
1261.74
735.08
960.58
1256.15
3585.481
7
Repair Time
9.412 x 10-4
7.986 x 10-4
1.422 x 10-4
1.058 x 10-4
8.064 x 10-4
2.791 x 10-4
*study period for Wuse and Garki : 2004-2007; Study period for Kubwa, Karu and G/Lada: 2006-2007; Study period for Abuja Territorial District: 2002-2007.
450
400
350
300
250
200
150
100
50
0
SAIDI CAIDI
SAIFI
2002
2003
2004
2005
2006
2007
Figure 2: Abuja Municipal Network.Table3: Service reliability indices data year 2007
Utility Name ADC [4]
District
Registered Customers Served (C)
Interruptions (N)
Total feeder hour of interruption (FHI)
Feeder Interrupted (FI)
SAIDI
CAIDI
SAIFI
Garki
28,858
1164
2908886
2239381
100.80
1.30
77.60
Wuse
26,344
617
1494583
1083617
56.73
1.38
41.13
Kubwa
35,013
200
1489220
466840
42.53
3.19
13.33
Karu
41,104
802
3510623
2197908
85.41
1.60
53.47
G/Lada
31,023
466
941031
963781
30.33
0.98
31.00
Table 4: Summary of service reliability for Abuja 2002 2007 [4]
Year
Registered Customers Served (c)
Interrupted (N)
Total feeder hour of interruption
(FHI)
Feeder Interrupted (FI)
SAIDI
CAIDI
SAIFI
2002
145,989
3599
24061907
35027627
164.82
0.69
239.9
2003
146,349
1341
19892439
13083601
135.92
1.52
89.4
2004
148,750
4014
33875333
39805500
227.73
0.85
267.6
2005
150,394
4747
36025379
47594688
239.54
0.76
316.47
2006
158,446
2735
54547676
28889987
344.27
1.89
182.33
2007
162,342
3232
63780925
34979290
392.88
1.82
215.47
450
400
350
SAIDI CAIDI
SAIFI
300
250
200
150
100
50
0
2001 2002 2003 2004 2005 2006 2007 2008
Figure 3: Abuja Municipal City Reliability Network Measured.
-
RESULTS AND DISCUSSION
From Table 1 through 4 and Figures 2and 3, it can be seen that outages per feeder per year for all districts variedbetween (1341 to 4747). The Wuse feeders recorded the highest outage rates per feeder per year while the least is Kubwa feeder. However, Garki had the highest duration of outage account for 5003.99 hours. This records a total of about 209 days continuous `blackout`. This is followed by Wuse, which had 4208.49 hours duration of outage. This means a total of about 176 days continuous blackout. The least is also Kubwa with 1404.28 hours, 59 days blackout. These values are far too high when compared to the typical 2% value for industrialized nations and accounts for much of the national operational problems in the supply of electric power. There is need to analyze problem in the supply of electrical power. There is further need to analyze the fault to identify reasons for the high level of unavailability of the feeders.
According to Table 1, several factors have been identified to be responsible for these outages. The major cause of outages is earth fault (earth leakage). The average
outage frequency per year recorded is 1214.3 and accounted for 37.04% of the total failure. The time duration was
adequately maintained, increases operational cost might be incurred even if there was no frequent system failure.
The year by year assessment showed that the performance of the station was best in 2003. However, this value fell below expectation. The outage frequency recorded in 2003 was 1341 failures with 2038.77 hours of no electricity. The worst year was 2005 which accounted for about 4,747 failures which resulted to 3594.10 hours.
-
CONCLUSION.
Reliability evaluations are an important and integral feature of the planning, designs and operation of all engineering systems. Engineers must not only appreciate the benefits obtained from reliability assessments, but also how much such assessments can be made. The study has presented a statistical method of determining the power system components` failure rates and the associated durations. The method adopted was found to be satisfactory and comparable with other standard methods. The reliability parameters obtained gave a true reliability picture of the network.
REFERENCES
[1] Reliability of Electric Utility Distribution Systems: EPRI White827.57 hours. The next major cause was over current due to surge which contributed about 31.77%. The duration of the outage association with this was 1041.3 hours. Other
[2]Paper ECOSYNC; EPRI 1000424. Dec, 6 (2006), pp 5.1-5.4.
C.C. Liu, G.T. Heydt, A.G. Phadkeetal, The Strategic Power Infrastructure Defense (SPID) System IEEE control system Magazine, vol.20, Issue 4, August 2000, pp 40-52.
significant outages were due to jumper or cross arm 16.06%; other causes 4.3%, under ground cable fault 3% etc. The basic under line factor responsible for the poor performance, however, was poor maintenance and attitude
to duty. The total number of forced and scheduled outages
-
Rao J.M. et al Assessment of Reliability indices in Electric Power
Distribution Systems, International Journal of Engineering Research &Indu. Appls. (IJERIA) ISSN O974-1518, vol.2, No.vii (2009) , pp 447-459.
-
P.U. Okorie, Reliability Evaluation of Electricity Distribution System, using Abuja Metropolis as a case study, January, 2009. M. Eng. Theses, School of Engineering, Electrical/Electronics Program
were recorded with other causes which accounted for only 4.3%. Maintenance which is the back bone of successful performance had not been properly carried out for the Abuja 33kV and 11kV distribution network. If the feeders were not
me. AbubakarTafawaBalewa University, Bauchi.
James D.B. (2006) , Review of Floridas Investor Owned Electric Utilities (IOU) Service. Reliability in (2005) Florida Public Service Commission.