🌏
Global Academic Platform
Serving Researchers Since 2012

Escalation Mechanism in Project Management – A Framework for Effective Resolution in Metro Infrastructure Projects

DOI : https://doi.org/10.5281/zenodo.18470286
Download Full-Text PDF Cite this Publication

Text Only Version

 

Escalation Mechanism in Project Management – A Framework for Effective Resolution in Metro Infrastructure Projects

Tirumala Sunayana

Student, Masters of Building Engineering & Management School of Planning & Architecture, Vijayawada, Andhra Pradesh

Dr. Kranti Kumar Myneni

Assistant Professor, Masters of Building Engineering & Management School of Planning & Architecture, Vijayawada, Andhra Pradesh

Abstract – Escalation Mechanisms are vital in project Management because they provide a formal, time bound pathway to elevate unresolved issues and risks to higher authority before they cause major cost and schedule overruns. In large infrastructure, operational teams often lack the mandate to resolve systemic obstacles, so escalation ensures timely intervention, resource reallocation and strategic decision making at senior levels.

Metro Rail projects are especially vulnerable to escalation due to their long durations, dense urban settings, complex approvals and high technical interfaces. They face recurring challenges in land acquisition, environmental and statutory clearances, utility shifting, contractor performances and multi package coordination, leading to frequent and significant overruns compared to many other project types.

The study develops a structured escalation framework specifically for metro projects across the phases of construction. Though Literature review, case studies of DMRC, BMRCL, MMRDA and a stakeholder questionnaire, it identifies key escalation drivers. The study of existing escalation frameworks, revealing gaps as delayed escalation, unclear roles and thresholds and weak documentation. The proposed framework responds with phase wise measures in different phases of construction, indicates the potential to shorten the duration by 10 months and reducing the escalation in each phase by more than half, strengthening governance and delivery reliability in metro projects.

Keywords – Escalation, Issue Resolution, Metro Projects, Cost Overrun, Schedule delay

  1. INTRODUCTION

    Effective decisionmaking and timely issue resolution are critical for successful construction project delivery. Escalation is a structured process to raise unresolved issues, risks, or delays to higher authorities when they cannot be addressed at operational levels. Throughout a projects lifecycle mobilization, procurement, execution, and handover unresolved challenges lead directly to schedule overruns, cost escalation, and client dissatisfaction. (planta, 2025)

    A defined escalation framework assigns responsibility, sets authority thresholds, and ensures that issues receive attention at the right managerial level, enhancing transparency, accountability, and responsiveness. Metro rail projects in

    rapidly urbanizing countries such as India are especially exposed, as they depend on complex approvals and interfaces yet are expected to deliver rapid, sustainable urban mobility and economic benefits. (Insights, 2025)

    1. Escalations

      Project escalation is widely recognized in project management literature as a formal mechanism for addressing unresolved issues, risks, or bottlenecks that cannot be effectively managed at the operational or team level. It serves as a critical control to ensure that problems threatening project success receive timely attention from higher authority levels, thus safeguarding project objectives such as cost, schedule, and quality. (Project Management .com , n.d.) (planta, 2025)

      The primary purpose of escalation is to accelerate problem resolution and prevent adverse outcomes such as cost overruns, schedule delays, and quality degradation. Escalation helps to address barriers that lower management cannot overcome due to limitations in authority, resources, or expertise. According to Indeed.com and IPMA, an effective escalation process enhances transparency, accountability, and communication among stakeholders, supporting more informed and timely decisions (Indeed) (IPMA, n.d.)

    2. Triggers & types of Escalations
      • Unresolved risks or issues affecting scope, schedule, cost, or quality.
      • Resource shortages, communication breakdowns, contractual disputes, or external shocks.
      • Missed milestones and supplier performance problems. (Project Management .com )

        Common Escalation Types:

      • Formal: Structured, documented escalation for serious issues that exceed operational authority.
      • Informal: Early attempts via discussion within the team or with immediate management.
      • Time based: Triggered by missed deadlines or slippage against the baseline schedule.
      • Quality based: Related to non conformance with agreed specifications and deliverables.
      • Person related: Linked to conflicts, performance problems, or team breakdowns that need higher level intervention.
    3. Existing Framworks
      Framework Description Key Features Applications
      PRINCE2

      Escalation Framework

      PRINCE2

      (Projects IN Controlled Environments) is a widely adopted structured project management methodology emphasizing clear governance and control.

      Establishes tolerances for time, cost, quality, scope, risk, and benefits at project initiation and at each stage boundary.

      When these tolerances are forecasted or breached, it triggers escalation to the next management level (e.g., Project Manager to Project Board).

      Defined roles and responsibilities create a transparent chain of command for rapid decision- making.

      The framework facilitates early warning and manages deviation through formalized escalation routes, enabling timely corrective measures.

      (Liz Gallacher, 2012)

      PMBOK

      (Project Management Body

      of Knowledge) Escalation Process

      Developed by PMI (Purchasing Managers Index), PMBOK

      integrates escalation within its risk and issue management knowledge area.

      Risk thresholds and triggers pre-defined in the risk management plan guide when escalation is necessary.

      Issues are categorized by severity, and escalation levels and handling procedures are documented in the projects communication and risk plans.

      Use of issue logs and registers to track escalation status, ensuring visibility and accountability.

      Enables structure and consistency in elevating issues, ensuring relevant stakeholders are informed to support effective resolution.

      (A guide to the Project management Body of Knowledge, 2023)

      Agile Frameworks (Scrum, Safe) for Escalation Agile methods prioritize flexibility and rapid response, influencing how escalation is handled in dynamic project environments. Scrum teams utilize daily stand-ups to surface issues early, escalating impediments that cannot be resolved within the team to Scrum Masters or Product Owners.

      The Scaled Agile Framework (Safe) introduces an Escalation Pathway from Agile Teams to Release Train Engineers and Portolio Management for cross-team or systemic issues.

      Emphasizes collaborative problem-solving and utilizes digital tracking tools for transparency.

      Particularly effective in software and IT projects where iteration speed demands swift escalation to maintain delivery momentum.

      (htt1) (Sutherland, 2017)

      Industry-Specific Frameworks in Infrastructure Projects Major infrastructure projects often deploy tailored escalation frameworks addressing domain-specific risks. Define escalation avenues for technical, contractual, economic, and environmental issues specific to construction and infrastructure sectors. Formal escalation matrices link levels of authority to types and severity of issues, incorporating stakeholder representation from government, contractors, and clients.

      Use of project management information systems (PMIS) to monitor thresholds and automate alerts for trigger events.

      Such frameworks have proven effective in large- scale projects like metro rail development, highway construction, and energy infrastructure, promoting interdisciplinary coordination and expedited decision-making. (planta, 2025)
      Enterprise Risk Management (ERM) Integrated Escalation ERM frameworks incorporate change and issue escalation as part of wider organizational risk governance. Integrate escalation processes with enterprise risk appetite, policies, and reporting channels.

      Utilize key risk indicators (KRIs) monitored continuously to pre-emptively identify issues requiring escalation.

      Promote risk culture, encouraging proactive escalation and minimizing organizational inertia.

      Ensures alignment between project-level escalations and corporate risk management approaches for cohesive strategy execution. (ISO 31000, 2018)

      Table 1 Existing Escalation Frameworks (source- Author)

    4. Gaps Found
      GAPS Description
      Delay in Escalation Initiation Many projects suffer from delayed escalation, where issues are either not recognized early or are managed at inappropriate levels for too long, leading to aggravated cost and schedule overruns. (Chandrashekar Iyer, 2016)
      Ambiguity in Roles and Responsibilities Lack of clarity in who should escalate, when, and to whom often results in inconsistent escalation practices, causing confusion and delayed resolutions.
      Inadequate Threshold Definition Some frameworks lack clearly defined quantitative trigger points (e.g., specific cost percentage overrun or days delayed), making it difficult to objectively decide when escalation is warranted.
      Insufficient Documentation and Follow- up Poor record-keeping of escalated issues and inadequate tracking of resolution actions undermine accountability and learning from past experiences. (planta, 2025)
      Limited Integration with Risk Management Escalation processes are sometimes not fully integrated into the overall risk management framework, leading to fragmented approaches in handling emerging threats.
      Lack of Real time Monitoring and Tools Many projects do not use Real time analytics, dashboards, or automated alerts to fast track risk identification and escalation (Consulting, n.d.)
      Cultural and Communication Barriers Organizational culture that discourages reporting problems, fear of blame, or poor communication channels limit effective escalation.
      Over-escalation and Escalation Fatigue Some projects experience excessive or unjustified escalations, leading to management fatigue and reduced responsiveness to genuine critical issues.
      Inadequate Tailoring for Project Complexity Generic escalation frameworks often lack customization based on project size, complexity, stakeholders, or sector-specific challenges, reducing applicability.

      (planta, 2025)

      Post-escalation Monitoring is Weak Follow-through mechanisms to ensure that escalated issues are resolved effectively and lessons learned are not systematically executed.

      Table 2 Gaps found from the Existing Frameworks (source- Author)

      Major reference frameworksPRINCE2, PMBOK, Agile/SAFe, industryspecific infrastructure models, and ERMbased escalationprovide structured escalation paths, defined tolerances, and clear roles. They use tools such as stage tolerances, risk thresholds, escalation matrices, issue logs, and integrated PMIS or KRI dashboards to trigger escalation and maintain visibility.

      However, literature and practice reveal recurring gaps: delays in escalation initiation, ambiguous roles, and poorly defined quantitative thresholds. Documentation and followup are often weak, integration with risk management and realtime monitoring is limited, and cultural barriers discourage timely escalation. Overescalation, insufficient tailoring to project complexity, and weak postescalation monitoring further reduce effectiveness.

    5. Synthesis of Previous Work

    Recent research on escalation in construction and infrastructure projects reveals that cost and schedule overruns are caused by a wide variety of interrelated factors. Studies compare escalation provisions across countries, highlight contract flexibility and risk sharing as essential for handling economic shocks, and show that poorly managed scope changes and inadequate early risk controls are common triggers.

    Delay-induced escalations are often linked to employer actions, planning failures, and late claims processing, underscoring the importance of clear contracts and timely interventions. Change orders resulting from design modifications or planning errors also feature as major

    escalation drivers, and their impact can be mitigated through structured procedures, technology adoption, and improved coordination.

    Analyses from Indian infrastructure case studies underscore the significance of upfront planning, detailed documentation, and the use of escalation logs in reducing budget and schedule overruns. Reviews and literature syntheses consistently identify scope creep, tendering delays, and client-driven changes as important contributors to escalation. Overall, the studies advocate for robust planning, active monitoring, and proactive contract management to curb overruns and improve project outcomes.

  2. CASE STUDIES
    1. Parameters for selection of case studies:
      • Scale & Project Maturity
      • Data Depth & Availability
      • Governance & delivery Model System
      • Performance Impact Magnitude
      • Chronological Breadth for Comparative Analysis
    2. Case studies Identified
      • Delhi Metro
      • Mumbai Metro
      • Bengaluru Metro Project
        Project Name Delhi Metro Namma Metro Mumbai Metro
        Owner DMRC, Joint venture of Govt. of India and GNCTD Bangalore Metro Rail Corporation

        Limite (BMRCL), Govt of India & Karnataka

        Mumbai Metropolitan

        Region Development Authority (MMRDA)

        Project Start Construction started in 1998 Construction began around 2006 Construction initiated in 2008; first line operational

        from 2014 with continuous expansions ongoing

        Phases Phase 1: 65.1 km network

        with 59 stations

        – Phase 4 ongoing (new corridors and extensions)

        Phase 1: 42.3km network with 40 stations

        Phase 2: 72km network with 62 stations expected to be completed by 2-26

        Phase 3:44l=km yet to start

        Phase 1: ~11.4 km (Versova- Andheri-Ghatkopar), operational

        – Phase 2: ~124 km planned, multiple lines under construction

        – Additional extensions in progress

        Network Details Covers Delhi and adjoining satellite cities like Noida, Gurgaon, Faridabad, Ghaziabad; multi-modal

        integration

        175 km (planned), major urban & suburban corridors Connectivity across densely populated suburban and urban centres to reduce traffic congestion
        Technology Advanced tunnelling (TBMs), signalling, rolling stock by Hyundai Rotem, Bombardier (The Delhi Metro:Effective Project Management in Indian

        Public sector, 2017)

        Modern signalling and communication systems, use of Tunnel Boring Machines (TBM) for underground sections, elevated & underground lines, integrated ticketing system Modern steel-wheeled metro technology, combination of underground and elevated sections, advanced signalling and security

        systems

        Funding Central and State Government funds, Japanese International Cooperation Agency (JICA) loans, fare revenues (The Delhi Metro:Effective Project Management in Indian Public

        sector, 2017)

        Combination of equity from Government, loans from Asian Development Bank (ADB), European Investment Bank (EIB), Japan International Cooperation Agency (JICA), and fare revenue Government equity, Asian Development Bank (ADB) loans, central and state funding, land monetization
        Key Contractors Larsen & Toubro, Afcons Infrastructure, Hyundai

        Rotem, Bombardier, and multiple joint ventures

        Larsen & Toubro, Afcons, ICML, HCC Larsen & Toubro, Simplex Infrastructure, Tata Projects,

        Reliance Infrastructure, and others

        Challenges Land acquisition, coordinating multiple

        contractors, environmental clearances, resettlement

        Land acquisition delays, funding issues, regulatory approvals, coordination among multiple agencies Land acquisition, legal disputes, coordination

        between multiple agencies, delay in project clearances

        Escalation PRINCE2 tool for escalation process PRINCE2 tool for escalation process PRINCE2 tool for escalation process
        • Phase 2: Expanded network completed by 2017
        • Phase 3: Further expansions completed by 2018

        Table 3 Case Study Analysis

        (The Delhi Metro:Effective Project Management in Indian Public sector, 2017)

        (Annual report on delhi metro project, 2022) (Annual report of Namma Metro 2023-2024, 2024) (DPR of mumbai metro , 2018)

    3. Escalations in Case Studies

      Delhi Metro

      • Phase-IV corridors construction costs escalated by nearly 15%, increasing total costs from around Rs 10,479 crore to over Rs 12,048 crore.
      • Major escalation cause: Delays in environmental clearances and permissions to fell/translocate trees, which caused project delays up to 30 months in sections.
      • Other issues include contractor delays, TBM procurement and operation problems, and frequent management changes impacting tunnelling and excavation schedules.
      • Supreme Court acknowledged probable escalation but refused to halt ongoing Phase-IV work due to cost impact. (India Today, 2023) (TOI, 2023)

        Bengaluru Metro

      • Phase-2 project (75 km approx.) cost escalated about 52% from initial ~Rs 26,405 crore (2014) to nearly Rs 40,000 crore due to delays, pandemic impacts, and increased land acquisition costs.
      • Initial completion deadline of 2019 shifted to expected 2026.
      • Key drivers of escalation included land acquisition delays, pandemic-induced work stoppages, currency fluctuations, and scope extensions such as new depots and route extensions.
      • Funding approvals delays further exacerbate cost escalation risks. (Indian Express, 2024) (Swarajya, 2024)

        Mumbai Metro

      • Metro 3 project’s cost revised upward by more than Rs 10,000 crore, from approximately Rs 23,000 crore to Rs 33,000 crore due to delays in work, especially around the car shed dispute at Aarey Milk Colony.
      • Project stall lasting around two and a half years caused significant time and cost escalation.
      • Issues with depot relocation and repeated project deadlines push add to escalation pressures (Devagtha) (Mumbai Mirror, 2021)
        Phase Escalation Factors Description and impacts Type of escalation
        Pre- Construction phase Environmental clearances and legal approvals delays

        (Delhi Metro)

        Delays in tree felling and environmental permissions led to project start delays, affecting

        overall timeline and costs

        Regulatory/Legal Escalation
        Land acquisition delays (Bengaluru Metro) Significant delay in acquiring land properties

        pushed back mobilization and led to scope changes and cost escalation

        Administrative/Economic Escalation
        Depot location disputes (Mumbai Metro 3) Legal and political disputes over depot sites caused pre-construction standstills, delaying project kick-off and inflating costs Legal/Political Escalation
        Funding approval delays (Bengaluru Metro) Delay in receiving governmental funds and sanction caused schedule slippage and increased

        financing costs

        Financial/Administrative Escalation
        During Construction Contractor performance and delays (Delhi Metro) Problems in tunnelling, TBM procurement, and

        contractor management led to schedule slips and cost growth

        Operational/Contractual Escalation
        Work stoppages due to pandemic (Bengaluru Metro) COVID-19 lockdowns halted site work, delaying progress and increasing overhead costs External/Force Majeure Escalation
        Scope changes and extensions (Bengaluru

        Metro)

        Addition of new depots, extended routes, and design changes added to cost overrun during

        construction

        Scope/Design Change Escalation
        Prolonged depot work delays (Mumbai Metro 3) two and half years of stoppage in car shed construction directly escalated project cost and

        time

        Operational/Contractual Escalation
        Post Construction Project handover delays affecting operations (general) Delays in finalizing system commissioning and operational clearances can push cost escalation

        in post-completion phase. Specific data limited but common in large metros.

        Operational/Administrative Escalation
        Legal disputes over

        project scope and contracts (all metros)

        Post-construction contract disputes relating to

        changes and escalation claims sometimes inflate final costs or cause payment deferments.

        Legal/Contractual Escalation

        Table 4 Escalation observed in Case Studies

        The case studies of Delhi, Bengaluru, and Mumbai Metro show that escalation in metro projects is largely driven by a common set of issues across all phases: land acquisition delays, environmental and legal clearances, and depot location disputes in pre-construction; contractor performance problems, scope and design changes, and depot/structure delays during construction; and handover delays and legal/contract disputes in the post-construction stage. Together, these lead to significant cost overruns and time extensionsoften well beyond original baselines demonstrating that the absence of timely, structured escalation, clear thresholds, and coordinated decision-making allows local issues to grow into major project-wide escalations

  3. KEY FINDINGS
    1. Risk Severity Score Matrix
    2. Result of questionnaire floated
      Factor Dominant Response Approximate Agreement

      Level

      Environmental & legal delays Yes / Maybe 75%
      Land acquisition Yes / Maybe 80%
      Depot disputes Yes 70%
      Scope/design changes Yes 90%
      Depot/structure delays Yes 85%
      Contractor issues Yes 85%
      Handover delays Yes 80%
      Legal disputes Yes / Maybe 80%

      Table 5 Result from Questionnaire

    3. Escalation Heirarchy

    Analysing the data from questionnaire and the research,

    Rank Factor Chart 1 Chart 2 Score
    1 Environmental & Legal Approvals Environ & Legal Env. & legal 9 (severity)

    / 75%

    (agreement)

    2 Land Acquisition Land Acquisn Land acquis. 8 / 80%
    3 Contractor Performance Contract Perf Contractor 7 / 85%
    4 Scope/Design Changes Design Changes Scope changes 6 / 90%
    5 Depot/Structure Delays/Disputes Depot Disputes Depot delays/dis

    putes

    3 /

    85%/70%

    6 Legal Disputes/Handover Post- Legal Legal disputes/

    Handover

    2 /

    80%/80%

    Table 6 Escalations Hierarchy

    Unified Interpreted ranking of major delay and escalation factors in metro projects, blending both agreement and severity scores from Research and Questionnaire Data:

      • Scope/design changes (90%) highest contributor to cost and schedule escalation.
      • Depot/structure delays and contractor performance issues (85%) critical challenges during construction.
      • Land acquisition, handover delays, and legal disputes
      • (80%) administrative and approval-related constraints.
      • Environmental clearances (75%) and depot disputes (70%) still relevant pre-construction hurdles but relatively lower ranked.
  4. FRAMEWORK DEVELOPMENT

    A. Existing Framwwork

    The PRINCE2 (Projects IN Controlled Environments) framework is a leading project management methodology designed to provide a structured approach across the full project lifecycle. It is widely used for complex projects, especially in infrastructure, and emphasizes clear governance, stage-wise control, and defined responsibilities

    B. Proposed Framework Land acquisition is inherently unpredictable due to its dependence on individual willingness and various social and financial factors.

    The timelines and costs for acquiring land can vary widely, often because delays in compensation or legal approvals occur when these steps are managed one after the other.

    Parallel approval process for land acquisitionwhere legal clearances and compensation negotiations are conducted simultaneously rather than sequentiallycan significantly compress the overall timeline. This approach ensures that delays in one stream do not hold up the entire process, ultimately leading to faster acquisition and project progress. Adopting parallel tracks for clearance and negotiation enables more efficient coordination among legal, administrative, and compensation teams, reducing unnecessary bottlenecks and improving stakeholder satisfaction.
    Legal Clearances are often a major source of uncertainty and delay in infrastructure projects due to complex regulations, multi- level approvals, and overlapping authorities. The impact of these delays is compounded when clearances are pursued sequentially or if documentation is incomplete. Single Window Clearance Units, unified approval frameworks that bring environmental, traffic, and municipal permits into a single coordinated portal, bottlenecks are dramatically reduced.

    Single-window clearance reports a 40% reduction in approval timelines, injecting speed, predictability, and investor confidence into project delivery. This not only accelerates project launches but also minimizes cost overruns and fosters a culture of transparency and trust at every stakeholder level.

    Depot Disputes Critical facilities such as depots and viaducts are interdependent and cause cascading

    scheduling impacts.

    Early involvement of Legal & Urban Planning Department & Rapid ADR Mechanisms. conceptual

    planning stages, can ensure statutory

    PRE CONSTRUCTION
    Issue Cause Mitigation Measure
    compliance and alignment with city masterplans before advancing to expensive

    design development.

    Table 7 Pre Construction Phase Escalations & Mitigation Measures

    Situation- Land Acquisition for a metro Depot is planned for

    24 months, and the project cost to be 10,000 crores and expected pre construction escalations 20% with delays in mind.

    Under the proposed framework, could run a compensation negotiations and legal clearances in parallel using Single- Window Clearance, the Acquisition time can be cut down to 16 months and scalation can fall to 8% saving us 1200 crores and 8 months of time window.

    BMRCL might have adopted these techniques.

    Digital Construction Controls, Drone-based progress tracking, combined with 4D scheduling tools, provides real-time visibility into onsite progress and spatial alignment of structures. The integration of 3D design with live progress data allows project teams to visually identify delays, validate work quantities, and automate reporting.

    These digital tools transform reactive supervision into proactive control by offering

    evidence-based tracking of construction milestones.

     

    CONSTRUCTION
    Issue Cause Mitigation Measure
    Scope & Design changes a Design Freeze milestone before procurement ensures that all scope and design parameters are locked and approved.

    Change Control Board centralized review authority for design and scope changes creates accountability and control.

    Every modification request is reviewed against its cost and schedule implications, ensuring that only justified

    and beneficial changes are approved.

    Contractor Performance Irrespective of qualification standards, and scrutiny, the performance of the contractor on site at later stages can be seen a major drawback. Real Time Monitoring Systems, Digital dashboards that track workforce output, equipment utilization, and progress metrics create a transparent construction environment.

    Regular Joint Progress Reviews, integrated feedback loop promotes prompt conflict resolution over scope, funding, or logistics, ensuring that project momentum remains uninterrupted and aligned

    with targets

    Structure Delays Segmented Scheduling, micro-schedules dedicated to depots and structural tasks ensures that parallel workflows remain

    efficiently coordinated.

     

    Table 8 Construction Phase Escalations & Mitigation Measures

    Situation where tunnelling package of 5000 crores is planned for 30 months, due to changes and poor contractor monitoring, construction escalation reaching 12% and duration to be extending up to 36 months.

    If the project declares a design freeze before TBM launch,

    routes all further changes through Change control board, and tracking daily progress through digital dashboards, 4D models,

    stoppages of work are minimized, and cycle time per ring remains stable, but the escalation will drop to 6%, saving 6 months time line and 300 crores on package

    DMRC could have adopted these techniques.

    POST CONSTRUCTION
    Issue Cause Mitigation Measure
    Handover Delays Progressive Commissioning

    – Initiating testing and certifications for completed sections early This approach allows seamless integration between construction and operations teams, shortens commissioning durations, and enhances overall project readiness.

    Integrated Documentation System digital repository for all Operation & Maintenance (O&M) manuals, inspection reports, and certifications creates a single source of truth throughout the project lifecycle. This centralized system enhances traceability, simplifies audits, and supports long-term asset

    management by ensuring

    Table 9 Post construction Phase Escalation & Mitigation Measures

    Situation of an elevated metro line, civil works may finish but opening to public gets delayed because of O&M manuals, test certificates and safety approvals which are scattered across departments, which adds several months of Overhead and about 20% extra post construction cost.

    With the proposed framework, the operator would start progressive commissioning section wise and maintain a centralized digital repository of all manuals, test reports and certificates, which brings the post construction time line to save up to 2months and 5% of additional cost.

    C. Expected Results

  5. CONCLUSION

A robust escalation framework is essential for metro projects due to their scale, complexity, and multiagency interfaces. The study confirms that timely, structured escalation with clear roles, thresholds, and realtime monitoring strengthens project governance and protects cost and schedule targets.

Case evidence from Indian metros and literature synthesis show that major escalation driversland acquisition, environmental and legal approvals, contractor underperformance, design changes, depot disputes, and handover and legal bottleneckscan be mitigated through parallel approvals, early authority involvement, digital coordination, and disciplined change control. Embedding escalation as a proactive control across all phases makes metro delivery more resilient, costefficient, and timely, enabling these systems to better support urban transformation and sustainable development.

REFERENCES

  1. (n.d.). Retrieved from Indeed: https://ca.indeed.com/career- advice/career-development/escalation-process-for-projects
  2. (n.d.). Retrieved from IPMA: https://ipma.world/effective- escalation-in-projects/
  3. (n.d.). Retrieved from https://framework.scaledagile.com/escalation/
  4. (n.d.). Retrieved from Devagtha: https://devgatha.in/en/mumbai- metro/
  5. (2021, July). Retrieved from Mumbai Mirror: https://mumbaimirror.indiatimes.com/mumbai/other/metro- faces-another-delay-cost-escalation/articleshow/84515681.html
    every stakeholder has access

    to up-to-date, verified project data in one platform

     

  6. (2023, January). Retrieved from India Today: https://indianexpress.com/article/cities/delhi/projects-delayed- costs-go-up-for-delhi-metro-8408665/
  7. (2023, January). Retrieved from TOI: https://indianexpress.com/article/cities/delhi/projects-delayed- costs-go-up-for-delhi-metro-8408665/
  8. (2024, 09 19). Retrieved from DEV: https://dev.to/binoy123/navigating-escalation-how-to- effectively-address-issues-and-avoid-common-mistakes-5718
  9. (2024, December). Retrieved from Indian Express: https://www.newindianexpress.com/cities/bengaluru/2024/Dec/1 8/in-a-first-bmrcl-stares-at-cash-crunch
  10. (2024, January). Retrieved from Swarajya: https://swarajyamag.com/infrastructure/bengaluru-metro-phase- 2-cost-jumps-to-rs-40000-crore-52-per-cent-rise-from-original- estimate
    Phase Timeline (Typical) Timeline (Mitigation) Cost Overrun (Typical) Cost Overrun (Mitigation)
    Pre- Construction 24

    months

    1516

    months

    +1520% +510%
    Construction +2530% +1015% +1015% +510%
    Post- Construction 6 months 34 months +20% +05%

     

  11. A guide to the Project management Body of Knowledge. (2023). In PMBOK Guide.
  12. (2024). Annual report of Namma Metro 2023-2024.
  13. (2022). Annual report on delhi metro project.
  14. Chandrashekar Iyer, R. K. (2016). Impact of Delay and Escalation on Cash Flow and Prfitability in a Real Estate Project. Retrieved from https://www.sciencedirect.com/science/article/pii/S1877705816 301023
  15. Consulting, A. (n.d.). Retrieved from https://www.accuraconsulting.com/news-and-insights/cost- escalation-analysis-for-rail-and-tunnel
  16. (2021-2022). Delhi Metro Annual Report.
  17. (2018). DPR of mumbai metro .
  18. Insights, S. (2025, April). Retrieved from https://www.sphericalinsights.com/blogs/top-10-metro-rail- network-infrastructure-countries-and-their-scope-in-2025- statistical-insights
  19. ISO 31000. (2018). In Risk Management- Guidelines.
  20. Liz Gallacher, M. H. (2012). Prince2 Foundation:study guide.
  21. planta. (2025, 1 2). Retrieved from PLANTA: https://www.planta.de/en/blog/escalation-management-in- project-management-reasons-types-and-strategies/
  22. Sutherland, K. S. (2017). The Scrum Guide.
  23. (2017). The Delhi Metro:Effective Project Management in Indian Public sector.