Impact of Risk Management on Time Performance of Mixed-use Developments During Construction Phase in Nairobi Metropolitan Region, Kenya

DOI : 10.17577/IJERTV14IS080064

Download Full-Text PDF Cite this Publication

Text Only Version

Impact of Risk Management on Time Performance of Mixed-use Developments During Construction Phase in Nairobi Metropolitan Region, Kenya

Qs. Abednego Mwanzia Wambua

Department of Construction and Property Studies, TUK Nairobi, Kenya

Professor Dr. Qs. Sylvester M. Masu.

Department of Construction and Property Studies, TUK Nairobi, Kenya

Dr. Lucy Muthoni Nyabwengi.

Department of Construction and Property Studies, TUK Nairobi, Kenya

Abstract Mixed-use developments are increasingly shaping Kenyas urban development landscape. In particular, the Nairobi Metropolitan Region has witnessed rapid growth in such projects due to rising land scarcity, urban densification, and shifting real estate demands. However, the construction phase of mixed-use developments presents a complex range of risks that can significantly disrupt timelines and affect overall project success. These risks include political and legal uncertainties, financial instability, and technical challenges. Poor management of any of these risks can result in time overruns, which often cascade into cost escalations, quality compromises, and stakeholder dissatisfaction.

This study investigated the impact of risk management on the time performance of mixed-use developments during the construction phase within the Nairobi Metropolitan Region. The specific objectives were to analyze the effect of political and legal risk management, financial risk management, and technical risk management on time performance. The study employed a descriptive survey research design and adopted a mixed-methods approach. Quantitative data collected from 297 respondents working across 67 active mixed-use developments spread across Nairobi, Kiambu, Kajiado, Machakos, and Muranga counties. Structured questionnaires were used to gather data on the three risk management dimensions and their relationship with time performance. Additionally, qualitative data was collected through interviews with 30 key informants drawn from professionals involved in the 67 mixed-use developments to gain deeper insights and gather practical recommendations for enhancing time efficiency.

Data was analyzed using the Statistical Package for Social Sciences (SPSS) version 27 because it is well-suited for survey-based studies involving multiple variables, as it allows for efficient management of large datasets and offers a wide range of statistical techniques, including descriptive analysis, correlation, and standard/simultaneous multiple linear regression. Descriptive statistics were used to summarize the data, while standard multiple linear regression was employed to determine the influence of each type of risk management on time performance. The findings indicated that all three risk management domains had a statistically significant and positive effect on time performance. Financial risk management emerged as the most influential factor, highlighting the importance of budgeting, cost

control, and diversified funding in maintaining project timelines. Technical risk management also showed a strong effect, underscoring the need for effective planning, use of technology, and coordination among technical teams. Political and legal risk management had a smaller but still significant impact, with timely regulatory approvals and legal compliance contributing to improved time outcomes.

The study concluded that effective and proactive risk management is vital for enhancing timely project delivery and provided practical recommendations for developers, project managers, policymakers, and other stakeholders. These include improving stakeholder coordination, strengthening financial planning, leveraging technology, streamlining regulatory processes, and investing in technical capacity building.

Keywords risk management, mixed-used developments, time performance

  1. INTRODUCTION

    1. Background

      The construction industry plays a critical role in global economic development through its contributions to GDP, employment, and infrastructure (Brown et al., 2023). In 2023, the industry was valued at approximately USD 10.7 trillion, representing nearly 13% of global GDP, with China, the United States, and India being key players (The Business Research Company, 2023). The sector is projected to grow from USD 4.2 trillion to USD 13.9 trillion between 2022 and 2037 (Brown et al., 2023). In Africa, the construction industry is also expanding significantly, expected to surpass USD 400 billion by 2025, driven by urbanization, population growth, infrastructure needs, and investments from both local and international stakeholders, especially China (African Development Bank, 2025).

      In Kenya, the construction industry contributes approximately 7-10% of GDP and serves as a key employer, supporting 150,000 to 200,000 workers directly (Trading Economics, 2025; National Construction Authority, 2025). The industrys growth is fueled by infrastructure development, urbanization, and

      public-private partnerships. Moreover, the sector stimulates other industries through forward and backward linkages, creating demand for construction materials and professional services while enabling further economic growth (Brown et al., 2023).

      A growing trend in Kenya is the rise of mixed-use developments, which combine residential, commercial, office, and institutional spaces (Moos et al., 2018). These projects are complex and prone to various risks, including regulatory hurdles, financial constraints, and operational challenges (Kausar et al., 2024). Such complexity requires robust risk management strategies to mitigate potential delays (Ryckewaert et al., 2021).

      Time performance, defined as completing projects within planned schedules, is vital for mixed-use developments due to the involvement of multiple stakeholders and substantial investments (Brown et al., 2023; DiCesare et al., 2021; Geyer, 2024). Delays often lead to increased costs, strained relationships, and missed opportunities (Alshihre et al., 2022; Bibri et al., 2020; Ingle & Mahesh, 2022). Effective risk management in political/legal, financial, and technical domains is crucial. Political/legal risks include regulatory changes and disputes (Geyer, 2024; Chatterjee et al., 2018), financial risks involve funding and cost challenges (Fagerlid et al., 2021; Bibri et al., 2020), and technical risks relate to design and construction processes (Siraj & Fayek, 2019; Kusumastuti & Nicholson, 2018). This study examines how these risks affect the time performance of mixed-use developments in Nairobi Metropolitan Region.

    2. Research Problem

      Urbanization is driving increased demand for efficient land use, particularly in densely populated areas where land scarcity and high costs are prevalent (Bibri et al., 2020; Green, 2020; Mualam et al., 2019). In response, mixed-use developments have emerged as a viable solution, integrating residential, commercial, office, and institutional functions within compact urban spaces. These developments aim to address urban sprawl, promote sustainability, and enhance economic opportunities while optimizing limited land resources in Kenya and other parts of Africa. However, despite their benefits, mixed-use developments face numerous risks during the construction phase, including financial, regulatory, constructional, operational, and stakeholder-related challenges (Kusumastuti & Nicholson, 2018; Mualam et al., 2019).

      A persistent issue in Kenyas mixed-use developments is poor time performance, with many projects failing to adhere to planned schedules Ese & Ese, 2020; Runsewe, 2021). High- profile cases include Garden City Mall and Residences, delayed from 2015 to 2018 due to construction and logistical setbacks; Tatu City, experiencing slow progress due to regulatory and financial challenges; and Upper Hill Square, delayed beyond its 2017 target due to financing and construction issues (Ese & Ese, 2020; Runsewe, 2021). Other examples such as Two Rivers Mall, The Hub Karen, Britam Tower, Pinnacle Towers, and Avic International Africa Headquarters have similarly faced delays linked to financing, regulatory approvals, design complexities, and construction challenges.

      In light of these challenges, this study sought to examine how technical, financial, and political/legal risk management influence time performance in Kenyas mixed-use developments. The study aimed to contribute to the limited body of knowledge on how risk management practices affect project timelines in the context of developing countries.

    3. Research Objectives

      The main objective of this study was to investigate the impact of risk management on the time performance of mixed-use developments during the construction phase in the Nairobi Metropolitan Region. Specifically, the study aimed to analyze the effect of political and legal risk management, financial risk management, and technical risk management on the time performance of these developments, and provide practical recommendations to improve the time performance.

    4. Study Significance

    This study holds significance for practice, policy, research, and the construction industry in Kenya. For practitioners, particularly project managers and construction firms, the findings provide insights into effective risk management practices that can enhance the time performance of mixed-use developments. For policymakers, the study offers evidence on risk management within Kenyas unique regulatory and economic context, which can inform local construction policies and regulations. In terms of academic contribution, the study helps bridge the literature gap by offering insights specific to developing countries, addressing an area often overlooked in favor of developed nations contexts. Lastly, for Kenyas construction industry, the study identifies specific risk factors affecting time performance and offers practical guidance for reducing delays and improving project efficiency. These insights can support better project planning and scheduling, ensuring risks such as regulatory, financial, and technical challenges are anticipated and mitigated early in the project lifecycle.

  2. LITERATURE REVIEW

    1. Risks in Mixed-Used Developments

      Mixed-use developments present a wide range of risks due to their inherent complexity, as they aim to integrate residential, commercial, office, and other uses within a single project to promote sustainable urban living. These risks include financial, regulatory, design and construction, operational, market, sustainability, and legal risks. Financial risks arise from high capital requirements, funding challenges, and cost overruns linked to unforeseen construction issues and market fluctuations (Molaei et al., 2019; Kausar et al., 2024). Regulatory risks involve navigating complex zoning laws, securing permits, and adhering to building codes, all of which can delay project timelines and increase costs (Kausar et al., 2024; Shibani et al., 2022). Design and construction risks include integration challenges across diverse building functions, potential design flaws, construction delays, and quality control issues that can disrupt project delivery (Fagerlid et al., 2021).

      Operational risks relate to the post-completion management of these developments, including property maintenance, tenant coordination, and higher operating costs due to managing varied spaces (Molaei et al., 2019). Market risks stem from fluctuations in demand, consumer preferences, and competition, which can

      affect occupancy rates and profitability (Kausar et al., 2024). Sustainability risks focus on environmental impact, energy efficiency, and social integration, emphasizing the importance of green building practices and fostering community cohesion (Kausar et al., 2024; Molaei et al., 2019). Legal and contractual risks arise from disputes over contracts and regulatory non- compliance, requiring clear agreements and robust legal frameworks to mitigate potential conflicts (Pesämaa et al., 2018; Ryckewaert et al., 2021). Ultimately, effective risk management is essential for the success of mixed-use developments, requiring careful planning, stakeholder engagement, and adherence to best practices to achieve sustainable and timely project outcomes.

    2. Risk Management Process

      The risk management process for mixed-use developments involves identifying, assessing, mitigating, and monitoring risks throughout the project lifecycle. Risk identification is the first step, focusing on recognizing potential risks from the integration of various project components, such as financial uncertainties, regulatory challenges, construction complexities, and market fluctuations (Kausar et al., 2024; Ryckewaert et al., 2021). Common tools used include SWOT analysis and stakeholder brainstorming sessions, which help uncover a wide range of risks early on (Shibani et al., 2022; Pesämaa et al., 2018). Following identification, risk assessment evaluates the likelihood and potential impact of each risk through qualitative and quantitative methods like risk matrices, Monte Carlo simulations, and sensitivity analysis (Shibani et al., 2022). These methods help prioritize risks based on severity, which is crucial in complex projects such as mixed-use developments where multiple uncertainties overlap.

      Risk mitigation strategies aim to reduce the likelihood and impact of identified risks. These strategies vary depending on the nature of the risks and include detailed financial planning, proactive regulatory engagement, thorough design processes, and quality control measures (Kausar et al., 2024). Risk monitoring and control involve continuous oversight through project management tools like Building Information Modeling (BIM), audits, and inspections to ensure risks are managed effectively throughout the project (Pesämaa et al., 2018). Integrating risk management into overall project management ensures it is embedded at every stage rather than treated separately. Case studies like Hudson Yards and Kings Cross demonstrate the value of these approaches (Molaei et al., 2019; Ciaramella & DallOrso, 2021). Furthermore, stakeholder engagement and advanced technologies such as drones and IoT sensors enhance real-time risk tracking and management (Yang, 2022; Molaei et al., 2019). Environmental sustainability also adds layers of risk requiring compliance with green standards and thorough impact assessments (Siraj & Fayek, 2019; Ryckewaert et al., 2021).

    3. Risk Management and Time Performance

      1. Political and Legal Risk Management:

        Political and legal risk management is a critical aspect of ensuring the successful and timely execution of mixed-use developments. These projects face significant challenges due to complex zoning laws, regulatory compliance requirements, environmental standards, and stakeholder interests. Effective risk management begins with early engagement with local

        authorities and legal experts to understand and navigate regulatory frameworks, which helps avoid delays, penalties, or project termination (Nguyen et al., 2018; Yang, 2022). Zoning regulations often require variances or special permits, and delays in approvals can disrupt project schedules. Proactively working with zoning boards and using legal counsel can expedite this process (Ryckewaert et al., 2021; Brown et al., 2023). Stakeholder engagement is also essential, as mixed-use developments involve governments, commnities, investors, and residents. Involving stakeholders early promotes transparency, reduces opposition, and fosters support, which lowers the risk of legal or political challenges (Green, 2020). Moreover, public opposition related to environmental impact, traffic congestion, or social displacement can stall projects through protests or lawsuits. Developers can manage these risks by offering community benefits, conducting public consultations, and demonstrating positive socioeconomic outcomes (Kausar et al., 2024). Legal risks are further managed through robust dispute resolution mechanisms. Incorporating mediation and arbitration clauses in contracts helps resolve issues quickly without derailing timelines (Yang, 2022; Kimotho et al., 2023). Environmental compliance is another key area; thorough environmental impact assessments (EIAs) and adherence to regulations prevent delays due to non- compliance. Case studies such as KL Eco City in Malaysia, Marina Bay Sands in Singapore, and Raffles City Chongqing in China illustrate how proactive political and legal risk management, including stakeholder engagement, legal preparedness, and environmental due diligence, can enhance time performance. These international examples highlight best practices that can be replicated in similar contexts to ensure timely project delivery.

      2. Financial Risk Management

        Mixed-use developments are exposed to significant financial risks stemming from market fluctuations, cost overruns, funding challenges, and revenue uncertainties. Effective financial risk management (FRM) is essential to safeguard project viability and time performance. Accurate market analysis and demand forecasting are fundamental for identifying potential risks early in the project lifecycle (Nguyen et al., 2019; Brown et al., 2023; Chatterjee et al., 2018). Financial risk assessment methods, such as Monte Carlo simulations and sensitivity analyses, help developers evaluate the potential impacts of risks and prepare appropriate mitigation strategies (Siraj & Fayek, 2019; Thiongo & Muchelule, 2019). Mitigating financial risks requires robust strategies, including diversification of income streams, hedging, contingency planning, and sound financial structuring (Green, 2020). Securing diverse funding sources, through a mix of debt, equity, and public-private partnerships, helps ensure stability throughout the project lifecycle (Shibani et al., 2022; Green, 2020). Maintaining healthy cash flow and establishing contingency funds further strengthens resilience against unforeseen financial challenges.

        Effective FRM is directly linked to time performance, as financial uncertainties often lead to project delays through interruptions in funding or escalating costs (Leonidov et al., 2020). Case studies like Eko Atlantic City in Nigeria and Menlyn Maine in South Africa demonstrate that strategies such

        as phased development, green financing, insurance, and strong governance frameworks help mitigate financial risks and uphold project timelines (Ryckewaert et al., 2021; Molaei et al., 2019; Kausar et al., 2024).

        Stakeholder engagement, transparency, and sustainability measures further enhance financial resilience and mitigate delays (Green, 2020). Sustainable practices not only attract investors but also reduce operational costs, thereby supporting project schedules and financial performance (Nguyen et al., 2019; Thiongo & Muchelule, 2019).

      3. Technical Risk Management

        Technical risk management (TRM) is essential for the successful execution and timely completion of mixed-use developments, given their inherent complexity. These projects require the integration of diverse functions, residential, commercial, and recreational, within a single space, presenting risks related to design, construction coordination, technology, and maintenance (Maina & Mungai, 2023; Molaei et al., 2019). Early-phase design integration is crucial, with tools like Building Information Modeling (BIM) enabling collaboration and early detection of potential conflicts, thereby reducing delays (Kausar et al., 2024). BIM and Integrated Project Delivery (IPD) systems enhance construction coordination through real-time progress monitoring and improved communication among stakeholders (Ryckewaert et al., 2021; Siraj & Fayek, 2019).

        Technological advancements, such as prefabrication, modular construction, and IoT-enabled sensors, improve construction speed and quality while reducing weather-related risks (Ciaramella & DallOrso, 2021; Nurwin Fozia, 2022). These technologies support proactive issue identification, minimizing delays and enhancing time performance (Green, 2020). Furthermore, effective operational maintenance strategies utilizing predictive analytics reduce downtime post- construction, ensuring sustained performance (Molaei et al., 2019).

        Regulatory compliance also plays a pivotal role; early engagement with regulatory bodies helps avoid legal delays (Nguyen et al., 2019). Incorporating sustainable design through frameworks like LEED mitigates risks associated with energy efficiency and environmental standards (Nguyen et al., 2019; Brown et al., 2023). Risk assessment frameworks, such as FMEA, offer systematic approaches to identifying and mitigating technical risks (Maina & Mungai, 2023). Lastly, active stakeholder engagement ensures diverse perspectives inform risk mitigation strategies, reducing delays and enhancing time performance (Nurwin Fozia, 2022).

    4. Theoretical Framework

      This study is anchored on two key theories: Risk and Uncertainty Bearing Theory and Contingency Theory, both of which provide a robust framework for understanding risk management and its impact on the time performance of mixed- use developments. The Risk and Uncertainty Bearing Theory, developed by Knight (1921) and expanded by Keynes (1936), distinguishes between risk, which can be measured and managed through strategies like diversification, hedging, and insurance, and uncertainty, which requires flexibility,

      judgment, and scenario planning (Nurwin Fozia, 2022). In the construction sector, risks are often quantifiable, such as cost overruns, delays, or labor shortages, and are typically addressed through comprehensive risk identification, assessment, and mitigation using industry-standard tools like ISO 31000 and project management software (Kamarkor et al., 2024). Conversely, uncertainties arise from unpredictable factors such as regulatory changes or technological shifts and require adaptive strategies, including scenario planning and real options theory to enhance resilience (Scholz & Tietje, 2002; Trigeorgis & Reuer, 2017). Tools like BIM and IoT further strengthen risk management through real-time monitoring and better visualization. By applying this theory, construction firms can effectively manage both measurable risks and unforeseen uncertainties, improving project outcomes and sustainability. The Contingency Theory posits that there is no universal approach to management; optimal strategies depend on the specific circumstances of a project or organization (Comu et al., 2021; Green, 2020). Originating from the works of Lawrence and Lorsch (1967) and Fiedler (1967), the theory emphasizes the alignment between organizational structure, environment, and leadership style. In construction, this theory supports flexible management strategies tailored to the complexity and uncertainty of individual projects (Chatterjee et al., 2018). Adaptive leadership, as suggested by Fiedlers model, is crucial in navigating unpredictable environments (Kamarkor et al., 2024). Organizational structures that allow flexibility help firms respond efficiently to market demands and regulatory shifts (Oyieyo et al., 2019). Moreover, contingency theory enhances the effectiveness of risk management by aligning strategies with a projects specific risk profile and supporting sustainable practices influenced by regulatory and organizational factor (Ryckewaert et al., 2021). Overall, these theories guide construction firms in developing adaptive strategies to improve project performance and resilience.

    5. Conceptual Framework

    Figure 1 shows the conceptual framework for this study, which presents the independent variables (risk management) and the dependent variable (time performance of Mixed-use developments. It also shows the expected relationships between the independent variables and the dependent variable. From the conceptual framework, it was hypothesized that risk management (technical risk management, financial risk management, political and legal risk management) can lead to improvements in the time performance of Mixed-use developments.

    Figure 1: Conceptual Framework Source: Author, 2025

    The model was evaluated in this study is:

    C. Population and Sampling

    The study targeted mixed-use developments within the Nairobi Metropolitan Region, covering Nairobi, Kiambu, Kajiado, Machakos, and Muranga counties. A total of 67 approved mixed-use projects were identified through county government records, forming the studys population. Respondents included key stakeholders such as project managers, engineers, architects, quantity surveyors, and contractors, selected due to their involvement in risk management and time performance. A census approach was adopted, targeting five respondents per project, yielding a target sample size of 335. Additionally, stratified random sampling was used to ensure representation across construction companies, developers, engineering, architectural firms, and contractors for more precise and reliable results. Table 1 shows the respondents information.

    Table 1: Demographic Data of Respondents

    Frequency

    Percent

    Age Category

    18-29

    44

    15%

    30-39

    44

    15%

    40-49

    141

    47%

    50-59

    45

    15%

    60+

    23

    8%

    Total

    297

    100%

    highest level of education

    Diploma

    33

    11%

    Bachelors Degree

    126

    42%

    Masters Degree

    100

    34%

    PhD

    38

    13%

    Total

    297

    100%

    Gender

    Female

    82

    28%

    Male

    215

    72%

    Total

    297

    100%

    Position/Rol e in Project

    Project manager

    18

    6%

    Construction Engineer

    31

    10%

    Architect

    36

    12%

    Financial Analyst

    53

    18%

    Legal Advisor

    43

    14%

    Environmental engineer

    28

    9%

    Structural engineer

    19

    6%

    Materials engineer

    37

    12%

    Quantity surveyor

    32

    11%

    Total

    297

    100%

    years of Experience in Construction Project

    Less than 5 years

    53

    18%

    5-10 years

    95

    32%

    11-15 years

    111

    37%

    More than 15 years

    38

    13%

    Total

    297

    100%

    = + TRM + + PLRM+ (1)

    0 1 2 3

    Where

    0 Constant

    TP Time Performance of Mixed-use developments TRM Technical Risk Management

    FRM Financial Risk Management

    PLM Political and Legal Risk Management

  3. METHODOLOGY

    1. Research Design

      This study adopted a descriptive survey design to investigate the impact of risk management on the time performance of mixed- use developments. The design was appropriate as it enabled the collection of standardized, objective, and quantifiable data from a large pool of respondents, facilitating generalization to mixed- use developments in Kenya. The approach minimized researcher influence and ensured consistency in data collection. Additionally, the descriptive survey design allowed for efficient gathering of detailed data within a flexible and cost-effective framework, making it suitable for achieving the studys objectives (Bougie & Sekaran, 2019; Bell et al., 2022).

    2. Location of the Study

    This study focused on the Nairobi Metropolitan Region, comprising Nairobi, Kiambu, Kajiado, Machakos, and Muranga counties, selected for their rapid urbanization and growth in mixed-use developments. These developments integrate residential, commercial, and recreational spaces, offering sustainable urban solutions and reducing reliance on commuting. Prominent examples include Two Rivers Mall, Garden City, and Tatu City. Despite their benefits, projects like Upper Hill Square and Hazina Towers have faced significant delays due to financing, regulatory, and logistical challenges. These examples highlight the relevance of studying risk management and time performance within Nairobis dynamic urban development context (Ese & Ese, 2020; Runsewe, 2021).

    Source: Author, 2025

    1. Data Collection

      Data for this study were collected using structured questionnaires administered to 297 respondents from 67 mixed- use developments across Nairobi, Kiambu, Kajiado, Machakos, and Muranga counties. The questionnaires focused on four core areas: political and legal, financial, and technical risk management, and time performance, with responses measured on a 5-point Likert scale. The questionnaires were distributed digitally via Google Forms, with research assistants following up to ensure completeness. Additionally, qualitative data were collected through semi-structured interviews with 30 purposively selected professionals to gain deeper insights into improving time performance in mixed-use developments.

    2. Data Validity and Reliability

      To ensure validity, a pilot study involving 30 respondents from the construction sector was conducted to assess the clarity and relevance of the questionnaire, leading to minor adjustments for improved wording and flow. Additionally, expert reviews enhanced content validity. An adequate sample size was also used to ensure external validity. The study engaged a total of 297 respondents drawn from various professional backgrounds involved in mixed-use development projects within the Nairobi Metropolitan Region. For reliability, Cronbachs alpha was calculated after data collection to measure internal consistency, with a threshold of 0.7 deemed acceptable. Table 2 shows the Cronbachs alpha for the variables.

      Table 2: Cronbachs alpha for variables

      td>

      0.845

      Variable

      Number of Items

      Cronbachs alpha

      Political and Legal Risk Management

      10

      0.879

      Financial Risk Management

      10

      0.921

      Technical Risk Management

      10

      Time Performance

      10

      0.897

      Source: Author, 2025

    3. Data Analysis

    Data was analyzed using SPSS version 27. Descriptive statistics, including frequencies, means, and standard deviations, summarized the data. Standard multiple linear regression was applied to assess the effects of political/legal, financial, and technical risk management on the time performance of mixed-use developments. The model tested assumptions of linearity, independence, and normality, with results presented through charts and tables. The regression output included model summaries, ANOVA, and coefficients. Qualitative interview data underwent thematic analysis, identifying recurring patterns. Findings from both methods were integrated to provide comprehensive insights and support the study objectives through a mixed-methods approach.

  4. FINDINGS

    1. Political and Legal Risk Management

      The descriptive statistics on political and legal risk management provide insights into how these risks are perceived and managed during the construction of mixed-use developments in Nairobi Metropolitan Region. Using a five-point Likert scale, the overall mean score was 3.46 (SD = 1.08), indicating a moderately positive perception of risk management effectiveness. Key strengths identified included timely acquisition of permits (M = 3.63, SD = 1.404) and strong relationships with local authorities (M = 3.63, SD = 1.423). Additionally, public sector engagement and understanding of zoning laws were viewed favorably. However, lower mean scores were reported for considering political stability prior to project initiation (M = 3.20, SD = 1.042) and involving legal counsel early (M = 3.35, SD = 1.211), suggesting gaps in pre-construction planning and legal risk foresight. The findings highlight that while some aspects of political and legal risk management are well-prioritized, inconsistencies remain across projects. Table 2 shows these findings.

      Table 2: Descriptive Statistics for Political and Legal Risk Management

      Mean

      SD

      The project team conducted thorough due diligence regarding local regulations before beginning construction.

      3.51

      1.381

      All necessary permits and approvals were obtained in a timely manner.

      3.63

      1.404

      The project had strong relationships with local authorities, facilitating smoother operations.

      3.63

      1.423

      Political developments were closely monitored, and adjustments were made as necessary.

      3.49

      1.326

      Legal counsel was involved in the project from the start, ensuring compliance with regulations.

      3.35

      1.211

      Legal risks were managed effectively, minimizing delays in project implementation.

      3.35

      1.211

      Political stability in the projects location was considered before starting the project.

      3.20

      1.042

      The project team had a clear understanding of zoning laws, which minimized legal complications.

      3.45

      .829

      Local government support for the project was strong and helped in overcoming legal

      challenges.

      3.58

      .976

      Changes in government policies during the project were anticipated and managed effectively.

      3.45

      .829

      Overall score for political and legal risk management

      3.4640

      1.08242

      Valid N (listwise)

      Source: Author, 2025

    2. Financial Risk Management

      The descriptive statistics for financial risk management in mixed-use developments within Nairobi Metropolitan Region indicate a generally positive but inconsistent implementation across projects. The overall mean score was 3.51 (SD = 1.17), reflecting moderate agreement on the effective management of financial risks. The highest-rated practices included strict cost control (M = 3.63, SD = 1.22) and clear communication with stakeholders (M = 3.63, SD = 1.22), highlighting the importance of financial discipline and transparency. Robust project scheduling (M = 3.58, SD = 1.26) and comprehensive risk assessments (M = 3.54, SD = 1.24) were also noted as key strengths. However, lower mean scores for financial forecasting (M = 3.39, SD = 1.30), avoidance of penalties (M = 3.35, SD = 1.29), and contingency planning (M = 3.43, SD = 1.10) suggest these practices are less consistently applied. Variability in securing diverse funding sources (M = 3.51, SD = 1.41) further points to differences in project approaches. Overall, while financial risk management practices show strength in certain areas, inconsistencies remain, indicating the need for more standardized and comprehensive financial governance frameworks to ensure resilience across all projects. Table 3 shows these findings.

      Table 3: Descriptive Statistics for Financial Risk Management

      Mean

      SD

      Detailed cost estimates and budgeting were conducted at the beginning of the project.

      3.49

      1.405

      The project secured diverse sources of funding, ensuring adequate capital throughout.

      3.51

      1.414

      Strict cost control measures were implemented to monitor and prevent budget deviations.

      3.63

      1.224

      The project schedule was robust enough to avoid costly delays.

      3.58

      1.263

      Communication with investors and stakeholders was clear and timely, ensuring financial risks were minimized.

      3.63

      1.224

      Financial performance was regularly monitored throughout the project.

      3.49

      1.133

      The project had contingency plans in place to manage unexpected financial challenges.

      3.43

      1.101

      Financial forecasting was conducted regularly to ensure the project stayed within budget.

      3.39

      1.298

      The project avoided financial penalties related to contract breaches or delays.

      3.35

      1.286

      All financial risks were assessed and appropriately mitigated throughout the project lifecycle.

      3.54

      1.244

      Overall score for financial risk management

      3.508

      1

      1.168

      65

      Valid N (listwise)

      Source: Author, 2025

    3. Technical Risk Management

      The descriptive statistics for technical risk management in mixed-use developments within Nairobi Metropolitan Region indicate a moderate level of implementation, with variability across projects. The overall mean score was 3.31 (SD = 1.169), suggesting that while technical risk management is acknowledged, its application is inconsistent. The highest-rated item was technical training of project teams (M = 3.48, SD = 1.219), highlighting the recognition of human capital development in managing technical risks. Projects generally maintained schedules despite technical challenges (M = 3.45, SD = 1.262), indicating some resilience through planning and adaptability. Other well-rated practices included regular risk assessments (M = 3.39), adaptive management (M = 3.36), and innovativeconstruction techniques (M = 3.35), reflecting proactive risk mitigation efforts. However, lower scores were observed for the use of advanced technologies like BIM (M = 3.20), feasibility studies (M = 3.21), and technical competence of contractors (M = 3.22), suggesting gaps in technological adoption and expertise assurance. The lowest score was for coordination between design and engineering teams (M = 3.09), indicating persistent challenges in interdisciplinary collaboration. Table 4 shows these findings.

      Table 4: Descriptive Statistics for Technical Risk Management

      Mean

      SD

      A comprehensive feasibility study was conducted before project initiation.

      3.21

      1.341

      Advanced technologies such as Building Information Modeling (BIM) were employed to

      foresee potential technical issues

      3.20

      1.316

      The project was planned in detail, reducing the likelihood of technical challenges.

      3.33

      1.368

      Regular risk assessments were conducted to identify and mitigate technical issues.

      3.39

      1.220

      Adaptive management practices were used to address unforeseen technical challenges effectively.

      3.36

      1.197

      The project remained on schedule despite technical difficulties encountered during construction.

      3.45

      1.262

      The project employed innovative construction techniques to manage technical complexities.

      3.35

      1.199

      Coordination between design and engineering teams helped minimize technical delays.

      3.09

      1.006

      Contractors and subcontractors had the necessary

      technical expertise to complete the project successfully.

      3.22

      1.047

      Technical training was provided to ensure project

      teams could effectively handle any technological or engineering challenges.

      3.48

      1.219

      Overall score for technical risk management

      3.307

      7

      1.1689

      3

      Valid N (listwise)

      Source: Author, 2025

    4. Time Performance

      The descriptive statistics on time performance of mixed-use developments in the Nairobi Metropolitan Region reveal generally positive, though moderate, perceptions of schedule management, adaptability, and efficiency. The overall mean score was 3.62 (SD = 1.27) on a 5-point Likert scale, indicating satisfactory but improvable performance. The highest-rated aspect was maintaining project schedules without additional budgetary resources (M = 3.79, SD = 1.53), reflecting perceived cost efficiency despite construction uncertainties. Efficient resource utilization (M = 3.71) and adaptability to scope changes (M = 3.66) were also rated positively, highlighting flexibility and planning strength. Other areas, such as timely deliverables (M = 3.64) and obtaining regulatory approvals on schedule (M

      = 3.64), showed similarly favorable outcomes. Communication and project monitoring scored moderately well (M = 3.62 and M

      = 3.55, respectively). However, the lowest-rated item was responsiveness to delays (M = 3.45), indicating room for improvement in agility and contingency planning. Overall, findings suggest reasonable time performance but highlight opportunities to strengthen rapid response strategies. These findings are shown in Table 5.

      Table 5: Descriptive Statistics for Time Performance

      M

      SD

      The project adhered to its original schedule.

      3.51

      1.414

      Deliverables were completed on time throughout the project lifecycle.

      3.64

      1.496

      The project was able to adapt to changes in scope or unforeseen circumstances without significant

      schedule delays.

      3.66

      1.462

      Resources were utilized efficiently to meet project deadlines.

      3.71

      1.490

      The project maintained its schedule without requiring additional budgetary resources.

      3.79

      1.532

      Regulatory approvals were obtained within the scheduled timeline.

      3.64

      1.450

      Communication between the project team and stakeholders helped ensure the timely completion of the project.

      3.62

      1.315

      The timeline was clearly defined and realistic from the onset of the project.

      3.62

      1.270

      There was effective tracking and monitoring of the projects schedule throughout its lifecycle.

      3.55

      1.302

      The project team responded swiftly to delays or bottlenecks, preventing schedule disruptions.

      3.45

      .829

      Overall score for Time Performance

      3.6182

      1.2693

      Valid N (listwise)

      Source: Author, 2025

    5. Impact of Risk Management on Time Performance

      The study employed multiple linear regression to examine how political and legal, financial, and technical risk management affect time performance in mixed-use developments within the Nairobi Metropolitan Region. The model revealed a strong positive relationship (R = 0.856) with 73.4% of the variance in time performance explained by the three predictors (R² = 0.734). The ANOVA results showed the model was statistically significant (F = 1371.555, p < 0.001), confirming that these risk management practices significantly influence project timelines. Financial risk management had the greatest impact ( = 0.735, p

      < 0.001), indicating that effective financial strategies, including budgeting and cost control, are critical for timely project delivery. Technical risk management also had a significant, though moderate, influence ( = 0.329, p < 0.001), reflecting the importance of managing design, technology, and construction methods. Political and legal risk management showed the smallest effect ( = 0.274, p < 0.001), suggesting its role, while significant, is less pronounced.

      The regression equation derived was:

      TP = 0.053 + 0.274(PLRM) + 0.735(FRM) + 0.329(TRM) +

      Where TP is Time Performance, PLRM is Political and Legal Risk Management, FRM is Financial Risk Management, TRM is Technical Risk Management.

      The findings highlight that financial risk management is the most critical determinant of time performance, followed by technical and political/legal factors. This underscores the importance of prioritizing financial and technical strategies to mitigate delays and enhance project timelines in Nairobis mixed-use developments. Table 6 shows these findings.

      Table 6: Regression Coefficients

      Model

      Unstandardized Coefficients

      Standardized Coefficients

      t

      Sig.

      B

      Std. Error

      Beta

      1

      (Constant)

      0.053

      .065

      0.816

      .042

      PLRM

      0.274

      .049

      0.202

      0.022

      .000

      FRM

      0.735

      .048

      0.677/p>

      15.254

      .000

      TRM

      0.329

      .051

      0.303

      6.397

      .000

      Source: Author (2025)

    6. Recommendations to Improve Time Performance

    The qualitative findings highlighted several strategies to improve time performance in mixed-use developments within the Nairobi Metropolitan Region. A key recommendation was the need for early and structured stakeholder engagement to minimize delays caused by poor communication and conflicting priorities among developers, financiers, contractors, and regulators. Regular meetings and centralized decision-making platforms were cited as effective in aligning interests and ensuring accountability. Participants also emphasized the need for regulatory reforms to address approval bottlenecks by streamlining processes through integrated digital platforms, setting clear timelines for permit approvals, and enhancing coordination among regulatory bodies.

    Additionally, the study underscored the importance of strengthening risk management, project planning, technology adoption, and resource coordination. Proactive risk assessments, scenario planning, and risk registers were recommended to anticipate disruptions. Robust planning tools such as Critical Path Method (CPM), Work Breakdown Structures (WBS), and Earned Value Management (EVM) were endorsed for more accurate scheduling. Embracing technologies like Building Information Modeling (BIM), drones for monitoring, and digital project management platforms were seen as crucial to improving oversight and accountability. Participants further recommended better resource management through timely procurement and buffer stocks for critical materials, alongside institutionalizing post-project reviews, professional training, and continuous learning to build industry capacity.

  5. CONCLUSION

This study established that political and legal risk management has a significant yet moderate positive impact on the time performance of mixed-use developments within the Nairobi Metropolitan Region. Projects that proactively undertook early due diligence, secured permits promptly, maintained relationships with regulatory bodies, and engaged legal counsel early in the project cycle were less likely to experience time delays. Though this area of risk management had the smallest influence among the three domains studied, it remained statistically significant. These findings align with existing literature, which underscores the importance of regulatory compliance, stakeholder engagement, and legal preparedness in ensuring timely project completion (Yang, 2022; Green, 2020). Best practices identified included early involvement of communities, investors, and regulatory consultants to mitigate potential political and legal hurdles (Kausar et al., 2024; Shibani et al., 2022). The studys conclusions reinforce Risk and Uncertainty Bearing Theory (Knight, 1921) and Contingency Theory (Comu et al., 2021), highlighting the need for proactive,

context-specific strategies to navigate the political and legal complexities inherent in construction projects.

Financial risk management emerged as the most significant predictor of time performance in mixed-use developments within Nairobi. Projects that prioritized strong financial planning, secured diverse funding streams, maintained consistent financial oversight, and established contingency reserves were more likely to stay on schedule. These findings are in line with previous research emphasizing the disruptive effects of poor funding, delayed payments, and weak financial controls on construction timelines (Odoyo et al., 2022). The study highlighted the value of financial forecasting, cash flow monitoring, and regular audits in minimizing delays. Effective communication with key stakeholders was also noted as essential in avoiding disputes that could lead to time overruns. The findings support both Risk and Uncertainty Bearing Theory and Contingency Theory, reaffirming that proactive, context- specific financial strategies significantly enhance project resilience. Technical risk management also had a significant positive effect, although less impactful than financial risks. Practices such as detailed feasibility studies, early identification of risks, the use of Building Information Modeling (BIM), and cross-functional coordination were critical in avoiding delays. Consistent with literature (Ali & Nsairat, 2020; Nguyen et al., 2018), poor technical planning and communication often led to rework and delays. Barriers such as limited access to advanced technologies and fragmented team structures were noted, suggesting a need for further investment in digital tools, collaboration, and capacity building.

Based on these findings, the study provides practical recommendations for key stakeholders involved in mixed-use developments. Developers should integrate comprehensive risk management strategies from project inception, with thorough feasibility studies assessing political, legal, financial, and technical risks. Early engagement with legal, regulatory, and community stakeholders is vital to prevent delays, while diversified funding models and contingency reserves enhance financial stability (Valero, 2024). Developers and project managers are encouraged to adopt digital project management platforms for real-time tracking of schedules, resource allocation, and compliance status to ensure greater transparency and timely decision-making. Project managers should employ advanced planning tools such as Gantt charts, CPM, and BIM while embedding technical risk management through regular site audits and fostering effective communication among architects, engineers, and contractors (Shibani et al., 2022; Kabirifar & Mojtahedi, 2019). Additionally, policymakers are urged to digitize and streamline approval processes, offer incentives for timely completion, and enhance regulatory oversight to reduce bureaucratic inefficiencies (Pesämaa et al., 2018; Oyieyo et al., 2019).

Another implication of the findings is that financial institutions and investors should adopt risk-informed evaluation frameworks and require robust risk management before funding projects. Structured financing models tied to milestones, performance bonds, and escrow accounts are recommended to safeguard investments and minimize delays (Valero, 2024; Pesämaa et al., 2018). Professional bodies and academic institutions should champion ongoing training in financial planning, legal compliance, and digital tools, alongside

promoting knowledge-sharing platforms. Encouraging a culture of collaboration, transparency, and continuous learning through joint planning sessions and after-action reviews can help identify and address emerging risks effectively (Oyieyo et al., 2019). For future research, scholars are encouraged to expand studies beyond Nairobi to other urban centers, conduct longitudinal analyses, and investigate organizational cultures role in risk management. Further exploration of digital technologies, performance metrics, and policy interventions will provide deeper insights into enhancing time performance in complex construction projects.

REFERENCES

  1. African Development Bank. (2023). African economic outlook 2025. https://www.afdb.org/en/knowledge/publications/african-economic- outlook

  2. Alshihre, F., Chinyio, E., Nzekwe-Excel, C., & Daniel, E. I. (2022). Pursuing alignment of clients and contractors perceptions of client satisfaction in Saudi Arabian projects. Built Environment Project and Asset Management, 13(3), 341358. https://doi.org/10.1108/BEPAM-05-

    2022-0065

  3. Bibri, S. E., Krogstie, J., & Kärrholm, M. (2020). Compact city planning and development: Emerging practices and strategies for achieving the goals of sustainability. Developments in the Built Environment, 4, 10001. https://doi.org/10.1016/j.dibe.2020.100021

  4. Bougie, R., & Sekaran, U. (2019). Research methods for business: A skill- building approach (8th ed.). Wiley.

  5. Brown, J. L., Martin, P. R., Sprinkle, G. B., & Way, D. (2023). How return on investment and residual income performance measures and risk preferences affect risk-taking. Management Science, 69(2), 13011322. https://doi.org/10.1287/mnsc.2022.4398

  6. Chatterjee, K., Zavadskas, E. K., Tamoaitien, J., Adhikary, K., & Kar,

    S. (2018). A hybrid MCDM technique for risk management in construction projects. Symmetry, 10(2), 46.

    https://doi.org/10.3390/sym10020046

  7. Ciaramella, A., & DallOrso, M. (2021). Urban regeneration and real estate development: Turning real estate assets into engines for sustainable socio-economic progress. Springer.

  8. Comu, S., Elibol, A. Y., Yucel, B., & Bogazici University. (2021). A risk assessment model of commercial real estate development projects in developing countries. Journal of Construction Engineering, Management & Innovation, 4(1), 5267. https://doi.org/10.31462/jcemi.2021.01052067

  9. DiCesare, R., Toor, J., Wolfstadt, J., et al. (2021). Using return on investment operational and Monte Carlo modeling techniques to predict financial performance in a tertiary care outpatient clinic. Urology Practice. https://doi.org/10.1097/UPJ.0000000000000235

  10. Ese, A., & Ese, K. (2020). The city makers of Nairobi: An African urban history. Routledge. https://doi.org/10.4324/9781003018162

  11. Fagerlid, C., Andersen, B., & Dalseide, A. M. (2021). Engaging with mixed-use design: The case of the urban library in Oslo. In Architectural anthropology (pp. 131150). Routledge.

  12. Green, J. (2020). A holistic understanding of mixed-use theory in practice: Analyzing the factors of success in three Kansas City mixed-use developments [Masters thesis, Kansas State University]. https://hdl.handle.net/2097/40673

  13. Ingle, P. V., & Mahesh, G. (2022). Construction project performance region for Indian construction projects. International Journal of Construction Management, 22(8), 14431454. https://doi.org/10.1080/15623599.2020.1721177

  14. Kabirifar, K., & Mojtahedi, M. (2019). The impact of engineering, procurement and construction (EPC) phases on project performance: A case of large-scale residential construction project. Buildings, 9(1), 15. https://doi.org/10.3390/buildings9010015

  15. Kamarkor, A. M. B. P., Sang, P. K., & Nzuki, D. (2024). Technological factors and performance of roads construction projects in Nairobi County, Kenya. East African Journal of Business and Economics, 7(1). https://doi.org/10.37284/eajbe.7.1.1960

  16. Kausar, A., et al. (2024). Evaluating the challenges and impacts of mixed- use neighborhoods on urban planning: An empirical study of a megacity, Karachi, Pakistan. Discover Sustainability, 5(1), 24. https://doi.org/10.1007/s43621-024-00195-5

  17. Keynes, J. M. (1936). The general theory of employment, interest, and money. Macmillan.

  18. Kimotho, M. W., Lango, D. B., & Senelwa, D. A. (2023). Influence of project risk management on performance of government funded housing construction projects in Nairobi City County, Kenya. International Journal of Social Sciences Management and Entrepreneurship, 7(1). https://www.sagepublishers.com/index.php/ijssme/article/view/251

  19. Knight, F. H. (1921). Risk, uncertainty, and profit. Houghton Mifflin.

  20. Leonidov, A., Tipunin, I., & Serebryannikova, E. (2020). On evaluation of risky investment projects. Investment Certainty Equivalence. https://doi.org/10.48550/arXiv.2005.12173

  21. Maina, L. G., & Mungai, D. A.-M. W. (2023). Risk management practices and performance of infrastructural projects in Nakuru County, Kenya. International Journal of Social Sciences Management and Entrepreneurship, 7(1).

    https://sagepublishers.com/index.php/ijssme/article/view/246

  22. Molaei, M., Bosch-Rekveldt, M., & Bakker, H. (2019). Extending the view on project performance. Administrative Sciences, 9(3), 65. https://doi.org/10.3390/admsci9030065

  23. Moos, M., Vinodrai, T., Revington, N., & Seasons, M. (2018). Planning for mixed use: Affordable for whom? Journal of the American Planning Association, 84(1), 720. https://doi.org/10.1080/01944363.2017.1406315

  24. Nguyen, A., Mollik, A., & Chih, Y.-Y. (2018). Managing critical risks affecting the financial viability of publicprivate partnership projects: Case study of toll road projects in Vietnam. Journal of Construction Engineering and Management, 144(12), 05018014.

    https://doi.org/10.1061/(ASCE)CO.1943-7862.0001571

  25. Nguyen, L. D., Le-Hoai, L., Tran, D. Q., Dang, C. N., & Nguyen, C. V. (2019). Effect of project complexity on cost and schedule performance in transportation projects. Construction Management and Economics, 37(7), 384399. https://doi.org/10.1080/01446193.2018.1532592

  26. Nurwin Fozia. (2022). Risk identification and supply chain performance in construction industry in Kenya. https://doi.org/10.5281/ZENODO.6983001

  27. Odoyo, O. A., et al. (2022). [Insert complete title when available].

  28. Oyieyo, P. A., Rambo, C. M., & Ndiritu, A. (2019). Construction risks and completion of public-private partnership project in Kenya: A case of Sondu-Miriu Hydroelectric Power Project. International Journal of Project Management, 9(4).

  29. Pesämaa, O., Larsson, J., & Eriksson, P. E. (2018). Role of performance feedback on process performance in construction projects: Client and contractor perspectives. Journal of Management in Engineering, 34(4), 04018023. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000619

  30. Runsewe, D. (2021). Top mixed-use developments in Nairobi, Kenya. Estate Intel. https://estateintel.com/news/top-mixed-use-developments- in-nairobi-kenya

  31. Ryckewaert, M., Zaman, J., & Boeck, S. D. (2021). Variable arrangements between residential and productive activities: Conceiving mixed-use for urban development in Brussels. Urban Planning, 6(4), 152

    164. https://www.cogitatiopress.com/urbanplanning/article/view/4274

  32. Scholz, R., & Tietje, O. (2002). Embedded case study methods: Integrating quantitative and qualitative knowledge. SAGE.

  33. Shibani, A., Hasan, D., Saaifan, J., et al. (2022). Financial risk management in the construction projects. Journal of King Saud University

    – Engineering Sciences. https://doi.org/10.1016/j.jksues.2022.05.001

  34. Siraj, N. B., & Fayek, A. R. (2019). Risk identification and common risks in construction: Literature review and content analysis. Journal of Construction Engineering and Management, 145(9), 03119004.

    https://doi.org/10.1061/(ASCE)CO.1943-7862.0001685

  35. The Business Research Company. (2023). Global construction market report and strategies to 2032. https://www.thebusinessresearchcompany.com/report/construction- market

  36. Thiongo, D. M., & Muchelule, D. Y. (2019). Effect of building information modelling on construction projects risks management in Kenya. https://papers.ssrn.comabstract=3585634

  37. Trading Economics. (2025). Kenya GDP from construction. https://tradingeconomics.com/kenya/gdp-from-construction

  38. Trigeorgis, L., & Reuer, J. J. (2017). Real options theory in strategic management. Strategic Management Journal, 38(1), 4263. https://doi.org/10.1002/smj.2593

  39. Valero, A. (2024). Appraisal of mixed-use developments through multiple criteria decision making: Insights from Shanghais megacity context. Cogent Business & Management, 11(1), 2332500.

    https://doi.org/10.1080/23311975.2024.2332500

  40. Yang, M. (2022). Risk management of prefabricated building construction based on fuzzy neural network. Scientific Programming, 2022(1), 2420936. https://doi.org/10.1155/2022/2420936

Qs. Abednego Mwanzia Wambua

Student- Master of Construction Project Management – TUK- On-Going

Bachelor of Quantity Surveying-TUK Diploma in Building Engineering-TUK Professional Quantity Surveyor- IQSK

Registered & practicing Quantity SurveyorBORAQS Consulting Quantity Surveyor.

Professor Dr. Qs. Sylvester M. Masu.

Doctor Of Philosophy (PhD)- Construction Management- UON

Professor of Quantity Surveying and Construction Management, Department of Construction and Property Studies (DCPS), TUK

Dr. Lucy Muthoni Nyabwengi.

Doctor of Philosophy (PHD)- Urban Management-UON. Master of Urban Management- Urban Management-UON Bachelor of Arts (BA)- Land Economics-UON Current Designation: Lecturer, Department of Construction and Property Studies (DCPS)