A Study on Delayed Highway Projects in the UT of Jammu & Kashmir (India)

DOI : 10.17577/IJERTV9IS100037

Download Full-Text PDF Cite this Publication

Text Only Version

A Study on Delayed Highway Projects in the UT of Jammu & Kashmir (India)

Peerzada Mohsin Shafi

(Doru Shahabad Anantnag)

Department of Civil Engineering, R.I.M.T Univesity Punjab

Abstract Construction delay is a common problem and is one of the main reasons for project failure. Our country, India is no exception to it. This study investigated the main causes of delay in highway construction projects in UT of J&K, India. A questionnaire survey was conducted to consider the time performance of construction projects in UT of J&K, India to identify the causes of delay and their important index for delay factors. A total 78 causes of delay were identified during the research. The delay factors were grouped into eight major groups. The top-10 list was dominated by the factors of Limited Construction area, Poor ground Conditions, Late in approving sample materials, Late land handover by the owner, Poor site Management, Improper Construction Methods, Rework due to unaccepted quality, Frequent equipment breakdown, Shortage of Construction material and Incapable Inspectors. The remaining factors on the list were poor qualification of the contractor technical staff and project team, conflict between contractor and consultant, Poor site arrangement, lack of involvement of design team during construction stage, delay in obtaining permits from provincial/municipality, and distribution to public activities. Recommendations to manage the delay factors were presented. Significant relationships, between the delay factors and the project objectives also were observed and discussed.

Keywords:–Construction Delay; Financial Problems; Improper Study

  1. INTRODUCTION

    Construction delays are very common in most projects everywhere in the world. Delay could be defined as an act or event that extends the time required to performance the tasks under a contract. It usually shows up as additional days of work or as delayed start of an activity (G. Sweis et al 2007). According to Assaf et al (2006) in construction, delay could be

    defined as the time overrun either beyond completion date specified in contract, or beyond the date that the parties agreed upon for delivery of a project. It is a project slipping over its planned schedule and is considered as common problem on construction projects. This study is an attempt to fill the gap by carrying out research on the delay analysis of infrastructure projects with a focus on examining the factors that influence

    delays and their effects on project time, cost, and quality. The target respondents were engineers from contractor and consultant firms involved in construction projects. Time, cost and quality are the basic of successful construction. Time and cost had parallel relationship with the increasing of the time there will be the increase in the cost. Thus, the control of time is really important for any project. The time that is already discussed is the period which is the schedule for the activities from beginning until finish the process of planning.

    Delays in projects have a direct bearing on the overall cost of construction. For example, from 2010 to 2015, the cost of cement (per bag) increased by 74%, steel increased by 34%, bricks increased by 69%, sand increased by 240% and skilled labour (on a per day basis) increased by 96%. It is therefore, understandable, that the cost overrun in delayed projects has resulted in approx. 24.77% increase in the original cost of the projects, amounting to 1, 09,359 Crores. Delays in a project also increase the likelihood of disputes between the parties and needless to say, these disputes may derail the project. Infrastructure development is one of the core elements in Indias growth story and the union governments Achhe Din and Sab Ka Saath,Sab Ka Vikaas vision. In the last two decades, India has pumped billions into mega projects in the country in aviation, industrial development, smart cities, railways, roads and energy. However, the scale of these projects also means that some of that some of them are running behind schedule by years while also seeing massive cost overruns.

    The measures were identified that could be implemented at the early stages to avoid project life cycle problems and to speed up implementation of project activities without compromising the quality of work and project. The study of several condition leads to a cause of unsettled disputes, frontrunners to arbitration cases/court cases. The delay in completion of the project, further attribute delayed benefits of the projects to the country, loss of precious time to deals with the disputed issues and heavy over-run of project cost.

    By keeping important steps in mind during the preparatory phases of project planning is healthy execution of the contracts. Preparatory phases prior to invitation of tender have a proper concept of the work with accurate planning and proper design for desired outcomes of the project within time frame. Careful planning and giving attention in detailed aspects of contract management and corrective measures adopted within the framework of the contract can save time and money. Consistent review of progress and plans, co- ordinations, close monitoring, adherence to safety plans, tight operational management, good industrial relations, and strict financial control will help in future projects.

  2. RESEARCH BACKGROUND

    Considering the importance of analyzing delays in construction, many studies have been carried out to identify the factors that contribute to their causes. Some focus on general construction projects (Sweis et al. 2008; El Razek et al. 2008; Sambavisan and Soon 2007; Lo et al. 2006; Chan and Kumaraswamy 1997), whereas others focus specifically on large projects (Haseeb 2011; Toor and Ogunlana 2008; Assaf and Al-Hejji 2006).

    The large number of research papers on the idea of delays does not mean that the topic is saturated. It does, however, indicate the significance of the topic in the construction industry and the individuality of construction projects; therefore, it is a topic worth exploring.

    Similar study was carried in the Riyadh province of Saudi Arabia. (Abd el-kharashi and others 2008) and in the Egypt (Ayman H Nassar 2016). They used the questionnaire survey to trace the time performance of the project.

    Several studies were done to search out and identify the causes of delay in several countries. Around 35 such research work on delayed construction projects of the various parts of the world has been reviewed. Many researches are done on this issue. However, this study was carried to gather most causes of delay in highway construction projects of UT of J&K in India, its impact factors on the project and to urge some recommendation to reduce these delays and their effects. This study updated the present situation, after the changes everywhere the globe in construction industry especially in India.

  3. METHODOLOGY

    The various parameters of the project were studied with doctrinal and Empirical approach in phased manner. The research work was carried out in wide variety of data collected through the various concerned offices located in the UT of J&K. The data was collected through the personal visits, email etc. from the concerned.

    This research is on the basis of a survey designed to gather all necessary information in an effective way. The survey presents various delay causes generated on the basis of related

    research work on construction delay together with input, revision, and modification by some construction parties. A questionnaire was developed to evaluate the importance index f the identified causes.

  4. DATA COLLECTION

    In making the questionnaire consultation with the working professionals were held to prepare the set of questions to be asked in the questionnaire

    To analyze the data, an approach using the importance index (Assaf and Al-Hejji 2006) was adopted, in which initially it was necessary to calculate the Relative Importance Index using formulas as follows:

    Relative Important index (RII) = W/ (A.N) Where W = weighting given to each factor by the respondents which ranges from 1 to 4

    Where '1' is 'not important' and '4' is 'very important', A = Highest weight (i.e. 4 in this case)

    N = Total number of respondents (45)

    In this study, the relationship among different parties or factors was measured by Spearmans Rank Correlation coefficient. It offered an advantage of not requiring the normality assumption or homogeneity of variance assumption. The subjected can be compared, as results have one or two outliers, their influence can be negated. In this study, the relationship among different parties or factors was measured. The coefficient can be computed as follows:

    rs = 1- 6 d2 /N(N2-1)

    rs = Spearmans rank correlation coefficient between two parties,

    d = The difference in ranking between ranks assigned to variables for each cause (owner and consultants, owner and contractors, consultant and contractors), and

    N = The number of pairs of rank for all the delay factor and eight the main categories of delays, respectively.

  5. RESULTS Important Index of Delay Factors

S No.

Category

Effects of Delay Factor on

Relative Importance Index

Over all Rank

1

Project Group

Award the project to the lowest bidder

20

53

2

Disturbance to public activities

70.67

09

3

Limited construction area

56.00

25

4

Inconvenient site access

70.66

10

5

Poor ground condition

70.00

11

6

Poor terrain condition

75.34

04

7

Poor soil condition

63.34

20

8

Impact on people's land along the construction project

57.34

24

9

Accidents during construction

30.00

43

10

Ineffective penalties caused by delay

35.34

37

11

Long distance to borrow pits

34.00

38

12

Quantity increase over contract

42.66

33

13

Unreasonable project time frame

28.66

46

S No.

Category

Effects of Delay Factor on

Relative Importance Index

Over all Rank

14

Owner Group

Late progress payment

78.00

01

15

Late in decision making

67.34

14

16

Poor communication between owner and other parties

66.00

16

17

Financial problems of owner

77.34

02

18

Late in approving sample materials

70.66

10

19

Change orders during construction

40.66

34

20

Late in approving the site to contractor

48.00

31

21

Delay in issuing completion certificate

26.00

51

22

Undefined scope of working

48.66

31

23

Late land handover by owner

38.00

35

24

late issuing of approval documents by owner

32.66

42

25

Difficulties in financing project

60.66

22

26

Unreasonable project time frame

28.66

46

27

Contractor Group

Poor communication between contractor and other parties

69.34

12

28

Conflict between contractor and consultant

74.66

06

29

Poor site arrangement, management, and supervision

75.00

05

30

Inadequate contractor experience

52.66

29

31

Improper construction methods

34.00

38

32

Rework because of unaccepted quality

43.34

32

33

Ineffective construction schedule

27.34

49

34

Poor qualifications of the contractor technical staff and project team

76.00

03

35

Frequent change of subcontractor/supplier

24.30

52

36

Conflict between contractor and other parties

35.34

37

37

Delay in commencement

36.00

36

Where

S No.

Category

Effects of Delay Factor on

Relative Importance Index

Over all Rank

38

Materials and Equipment Group

Frequent equipment breakdowns

62.00

21

39

Shortage of equipment, machinery, and tools

60.66

22

40

Inadequate modern equipment

66.66

15

41

Slow mobilization of equipment

67.34

14

42

Shortage of construction material

60.00

23

43

Change in types and specifications during construction

54.00

27

44

Slow delivery

32.66

41

45

Damage in storage while needed on site

64.00

18

46

Laborers Group

Personal conflict between laborers and management team

34.00

38

47

Personal conflict among laborers

28.00

48

48

Low productivity of laborers

65.34

17

49

Unskillful equipment operator

59.34

23

50

Insufficient laborers

33.34

40

51

Personal conflict between laborers and management team

26.66

50

52

Labor injuries

20.00

53

53

Labor disputes and strikes

29.80

44

54

Consultant Group

Inflexibility of consultant

28.66

46

55

Poor communication between consultant and other parties

34.00

39

56

Delay in performing inspection

32.66

41

57

Incapable inspectors

56.66

25

58

Lack of experience of consultant

70.00

11

59

Delay in approving major changes in the project

30.66

42

60

Incompetent project manager/team leader

66.66

15

61

Late sending progress claims to owner/client

64.66

19

62

Improper study of design affects estimates

77.34

02

63

Insufficient inspectors

68.00

13

S No.

Category

Effects of Delay Factor on

Relative Importance Index

Over all Rank

38

Materials and Equipment Group

Frequent equipment breakdowns

62.00

21

39

Shortage of equipment, machinery, and tools

60.66

22

40

Inadequate modern equipment

66.66

15

41

Slow mobilization of equipment

67.34

14

42

Shortage of construction material

60.00

23

43

Change in types and specifications during construction

54.00

27

44

Slow delivery

32.66

41

45

Damage in storage while needed on site

64.00

18

46

Laborers Group

Personal conflict between laborers and management team

34.00

38

47

Personal conflict among laborers

28.00

48

48

Low productivity of laborers

65.34

17

49

Unskillful equipment operator

59.34

23

50

Insufficient laborers

33.34

40

51

Personal conflict between laborers and management team

26.66

50

52

Labor injuries

20.00

53

53

Labor disputes and strikes

29.80

44

54

Consultant Group

Inflexibility of consultant

28.66

46

55

Poor communication between consultant and other parties

34.00

39

56

Delay in performing inspection

32.66

41

57

Incapable inspectors

56.66

25

58

Lack of experience of consultant

70.00

11

59

Delay in approving major changes in the project

30.66

42

60

Incompetent project manager/team leader

66.66

15

61

Late sending progress claims to owner/client

64.66

19

62

Improper study of design affects estimates

77.34

02

63

Insufficient inspectors

68.00

13

The computation of the Relative Importance index presented in Table 1 shows that the project group of late progress payment, which had the highest importance index (78.00), had an outstanding index value compared to other delay factor. This factor had more than a 10-point difference from the second-ranked factor, financial problems of owner (77.34) and improper study of design affects estimated quantity (77.34), which indicated the high significance of the late progress payment in delaying construction work. Other external factors were supposed as low in importance, with an index below 60.0. Further discussion was focused on the top- 10 delay factor.

The group importance index was calculated as the average of the Relative Importance index for the delay factors in the group. For example, in the project group, the group importance index is the average of the importance indices of its constituting causes as follows; Award the project to the lowest bidder(20), Disturbance to public activities(70.67), Limited construction area(56.00), Inconvenient site access, Inconvenient site access(70.66), Poor ground condition(70.00), Poor terrain condition(75.34), Poor soil condition(63.34), Impact on people's land along the construction project(57.34), Accidents during construction(30.00), Ineffective penalties caused by delay(35.34), Long distance to borrow pits(34.00), Quantity increase over contract(42.66), and Unreasonable project time frame(28.66), resulting in an average of 50.31, which is its group importance index.

S No.

Category

Effects of Delay Factor on

Relative Importance Index

Over all Rank

64

Design Group

Incomplete design

54.66

26

65

Design changes during construction

69.34

12

66

Unclear and inadequate details in drawings

56.00

25

67

Lacks of involvement of design team during construction stage

73.34

07

68

Delay in approving drawing, specifications, or instructions

54.00

27

69

Mistakes or errors in design

52.66

29

70

External Factor Group

Political situation

69.34

12

71

Fluctuation of exchange rate, material, equipment, machines

30.66

42

72

Changing of bankers policy for loans

38.00

35

73

Working during rainy season

48.66

30

74

Natural disaster

25.34

<>49

75

Changes in government regulations and laws

66.66

15

76

Delay in obtaining permits from provincial/municipality

73.33

08

77

Weather condition

29.33

45

78

Monopoly

53.33

28

S No.

Category

Effects of Delay Factor on

Relative Importance Index

Over all Rank

64

Design Group

Incomplete design

54.66

26

65

Design changes during construction

69.34

12

66

Unclear and inadequate details in drawings

56.00

25

67

Lacks of involvement of design team during construction stage

73.34

07

68

Delay in approving drawing, specifications, or instructions

54.00

27

69

Mistakes or errors in design

52.66

29

70

External Factor Group

Political situation

69.34

12

71

Fluctuation of exchange rate, material, equipment, machines

30.66

42

72

Changing of bankers policy for loans

38.00

35

73

Working during rainy season

48.66

30

74

Natural disaster

25.34

49

75

Changes in government regulations and laws

66.66

15

76

Delay in obtaining permits from provincial/municipality

73.33

08

77

Weather condition

29.33

45

78

Monopoly

53.33

28

The ranked groups of delay causes and their corresponding importance index are shown in Table 2.

Table 2

Group Importance Index for Overall Results

Rank

Group of Delay Causes

Group Importance Index

1

Design group

60.00

2

Material and equipment group

58.42

3

Owner group

53.94

4

Consultant group

52.93

5

Project group

50.31

6

Contractor group

49.33

7

External factor group

48.29

8

Laborers group

37.06

EFFECTS OF DELAY FACTORS ON TIME, COST, AND QUALITY

The presentation of a construction project generally can be measured according to the three project objectives of time, cost, and quality. Therefore, the impact of any risks to the project also should be reflected in these three factor From the mean values, it was shown that, in general, the respondents assigned more weight to the effect of time relative to cost and quality. This was reasonable, considering that delays are more related to time than to the other two project objectives. Hence, people in their opinion tended to communicate the effect of delay factors more to time than to cost or quality, which may not always be a true consideration.

The top-10 list for all three objectives in Table 3 is control by delay factors that are in the top-10 list of the importance index. This should make construction engineers aware that

each objective may have assured unique factors that considerably control the purpose. As shown in Table 3, disturbance to public activities again were ranked among the top listed delay factors, especially in affecting quality and time. Because construction projects are outdoor construction projects, disturbance to public activities, which expose construction work to public for a long period, have a substantial impact on quality. Therefore, disturbance to public activities was positioned at the top of the list. These two delay factors were considered to have slightly less effect on cost compared to the other two project objectives.

TABLE 3

Top-10 Delay factor and Their Effect on Time, Cost, and Quality

7

mobilizati on of equipment

6

of constructio n material

0

ution to public activiti es

6

0

8

Shortage of constructio n

Material

68.0

0

Incapable inspector

76.0

0

Shorta ge of constr uction materi al

74.6

6

0

9

Late land handover by owner

68.0

0

Late land handover by owner

76.0

0

Delay in perfor ming inspect ion at constr uction site

74.6

6

R

a n k

Time delay

factor

Time

mean

Cost delay

factor

Cost

mean

Quality

delay factor

Qual

ity mea n

1

0

Poor ground condition

67.3

4

Frequent equipment breakdown

76.0

0

Incapa ble inspect or

74.6

6

0

1

Improper

construction methods

72.34

Shortage of

equipment, machinery, and tools

78.00

Imprope

r construc tion methods

78.6

6

each objective may have assured unique factors that considerably control the purpose. As shown in Table 3, disturbance to public activities again were ranked among the top listed delay factors, especially in affecting quality and time. Because construction projects are outdoor construction projects, disturbance to public activities, which expose construction work to public for a long period, have a substantial impact on quality. Therefore, disturbance to public activities was positioned at the top of the list. These two delay factors were considered to have slightly less effect on cost compared to the other two project objectives.

TABLE 3

Top-10 Delay factor and Their Effect on Time, Cost, and Quality

7

mobilizati on of equipment

6

of constructio n material

0

ution to public activiti es

6

0

8

Shortage of constructio n

Material

68.0

0

Incapable inspector

76.0

0

Shorta ge of constr uction materi al

74.6

6

0

9

Late land handover by owner

68.0

0

Late land handover by owner

76.0

0

Delay in perfor ming inspect ion at constr uction site

74.6

6

R

a n k

Time delay

factor

Time

mean

Cost delay

factor

Cost

mean

Quality

delay factor

Qual

ity mea n

1

0

Poor ground condition

67.3

4

Frequent equipment breakdown

76.0

0

Incapa ble inspect or

74.6

6

0

1

Improper

construction methods

72.34

Shortage of

equipment, machinery, and tools

78.00

Imprope

r construc tion methods

78.6

6

Late in approving sample materials was one factor related to the Owner group in the top- 10 list of the importance index. Although Late in approving sample materials was positioned

R

a n k

Time delay factor

Tim e mea n

Cost delay factor

Cost mea n

Qualit y delay factor

Qual ity mea n

0

2

Frequent equipment Breakdow n

71.3

4

Late in approving sample materials

77.3

4

Late in approv ing sample materi als

76.0

0

0

3

Late in approving sample sample materials

71.3

4

Delay in performin g inspection at constructio n site

77.3

4

Rewor k becaus e of unacce pted quality

75.3

4

0

Limited

70.0

Limited

76.6

Poor

75.3

4

constructio

0

constructio

6

qualifi

4

n area

n area

cation

of the

contra

ctor

techni

cal

staff

and

project

team

0

Delay in

69.3

Improper

76.6

Freque

75.3

5

performin

4

constructio

6

nt

4

g

n

equip

inspection

methods

ment

at

breakd

constructio

own

n site

0

Low

69.3

Rework

76.6

Shorta

75.3

6

productivit

4

because of

6

ge of

4

y of

unaccepte

equip

laborers

d

ment,

quality

machi

nery,

and

tools

0

Slow

68.6

Shortage

76.0

Distrib

74.6

only as second in importance, this delay factor has a high

impact on cost, quality and time because it is positioned second in terms of its effect on cost, third for its effect on time, and second for its effect on quality. Delay factor related to the contractors on the top-10 list of the importance index, poor qualifications of the contractor technical staff and project teams, was seen to have a more considerable impact on quality because it was in the sixth rank.

To obtain a more comprehensive understanding of the relationship between the Relative Importance index and the project objectives of cost, time, and quality, the relationships of the top-10 delay factors and their impact on these objectives were analyzed and are presented in Table 4. Overall, there were significant associations between the delay factors on time, cost, and quality. These results indicate that delay problems not only are about time, they also significantly affect the quality and cost of road construction projects.

Relationship between Top-10 Delay Factors and Time, Cost, and Quality

S. No.

Delay Factor

RRI

RRI in Time

RRI in Cost

RRI in Quality

1

Limited construction area

56.00

70.00

76.66

68.66

2

Poor ground condition

70.00

67.34

51.34

49.34

3

Late in approving sample materials

70.66

71.34

77.34

76.00

4

Late land handover by owner

38.00

68.00

76

74.66

5

Poor site arrangement, management, and supervision

75.00

58.66

64

64.00

6

Improper construction methods

34.00

72.66

76.66

78.66

7

Rework because of unaccepted quality

43.34

62.66

76.66

75.34

8

Frequent equipment breakdowns

62.00

71.34

76.00

75.34

9

Shortage of construction material

60.00

68.00

76.00

74.66

10

Incapable inspectors

70.00

52.00

76.00

74.66

R

a n k

Time delay factor

Tim e mea n

Cost delay factor

Cost mea n

Qualit y delay factor

Qual ity mea n

0

2

Frequent equipment Breakdow n

71.3

4

Late in approving sample materials

77.3

4

Late in approv ing sample materi als

76.0

0

0

3

Late in approving sample sample materials

71.3

4

Delay in performin g inspection at constructio n site

77.3

4

Rewor k becaus e of unacce pted quality

75.3

4

0

Limited

70.0

Limited

76.6

Poor

75.3

4

constructio

0

constructio

6

qualifi

4

n area

n area

cation

of the

contra

ctor

techni

cal

staff

and

project

team

0

Delay in

69.3

Improper

76.6

Freque

75.3

5

performin

4

constructio

6

nt

4

g

n

equip

inspection

methods

ment

at

breakd

constructio

own

n site

0

Low

69.3

Rework

76.6

Shorta

75.3

6

productivit

4

because of

6

ge of

4

y of

unaccepte

equip

laborers

d

ment,

quality

machi

nery,

and

tools

0

Slow

68.6

Shortage

76.0

Distrib

74.6

only as second in importance, this delay factor has a high

impact on cost, quality and time because it is positioned second in terms of its effect on cost, third for its effect on time, and second for its effect on quality. Delay factor related to the contractors on the top-10 list of the importance index, poor qualifications of the contractor technical staff and project teams, was seen to have a more considerable impact on quality because it was in the sixth rank.

To obtain a more comprehensive understanding of the relationship between the Relative Importance index and the project objectives of cost, time, and quality, the relationships of the top-10 delay factors and their impact on these objectives were analyzed and are presented in Table 4. Overall, there were significant associations between the delay factors on time, cost, and quality. These results indicate that delay problems not only are about time, they also significantly affect the quality and cost of road construction projects.

Relationship between Top-10 Delay Factors and Time, Cost, and Quality

S. No.

Delay Factor

RRI

RRI in Time

RRI in Cost

RRI in Quality

1

Limited construction area

56.00

70.00

76.66

68.66

2

Poor ground condition

70.00

67.34

51.34

49.34

3

Late in approving sample materials

70.66

71.34

77.34

76.00

4

Late land handover by owner

38.00

68.00

76

74.66

5

Poor site arrangement, management, and supervision

75.00

58.66

64

64.00

6

Improper construction methods

34.00

72.66

76.66

78.66

7

Rework because of unaccepted quality

43.34

62.66

76.66

75.34

8

Frequent equipment breakdowns

62.00

71.34

76.00

75.34

9

Shortage of construction material

60.00

68.00

76.00

74.66

10

Incapable inspectors

70.00

52.00

76.00

74.66

  1. CONCLUSION

    The key aim of the research was to find out the main reasons of the delay in highway Construction projects in the UT of J&K.. After conducting the research it was found that the top- 10 list was dominated by the factors of Limited Construction area, Poor ground Conditions, Late in approving sample materials, Late land handover by the owner, Poor site Management, Improper Construction Methods, Rework due to unaccepted quality, Frequent equipment breakdown, Shortage of Construction material and Incapable Inspectors. The remaining factors on the list were poor qualification of the contractor technical staff and project team, conflict between contractor and consultant, Poor site arrangement, lack of involvement of design team during construction stage, delay in obtaining permits from provincial/municipality, and distribution to public activities.

    It was found that Consultants gave more weight to delays caused by contractors than did the contractors themselves, which is reasonable. Frequent equipment breakdown was ranked second by the consultants, but it was ranked fifth rank by contractor. Similarly, poor site arrangement, management, and supervision, which were ranked fourth rank by consultants, were placed seventh by the contractor.

    From the consultants perspective, there were no causes of delays by owners on the top- 10 list, but there were two concerns from the contractors point of view: late progress payment and financial problems of owner. This finding follows the logical practice in which contractors, in general, have a tendency to blame the owner or consultants for some delays or problems in the project, and vice versa. In this case, the contractors did not consider that the consultants contributed significantly to delays, as no factors from the consultants side were on the top-10 list of contractor. The blame was allotted more to the owner that did not pay the interim payment on time, possibly because of financial or cash flow problems.

    The presentation of the construction project was measured according to the three project objectives of time, cost, and quality. Therefore, the impact of any risks to the project was reflected in these three factors. It was observed that, in general, the respondents assigned more weight to the effect of time relative to cost and quality. This was reasonable, considering that delays are more related to time than to the other two project objectives. Hence, people in their opinion tended to communicate the effect of delay factors more to time than to cost or quality, which may not always be a true consideration.

  2. RECOMMENDATIONS

Causes of delay and its effect on time, cost, and quality in construction projects are always likely obstacles to project success. The study reported in thispaper established that there are a number of causal factors which need to be sufficiently dealt with if time overrun, cost escalation, and quality shortfalls are to be minimized on the construction projects.

A correlation coefficient between contractor and owner; owner and consultant; and contractor and consultant respectively 0.39, 0.89 and 0.74. A correlation of the responses of each party showed the contractor and owner to have non matching opinions concerning the causes of delay,

while the consultant held an intermediate position. The study concluded with the following points in order to avoid delays in the construction projects:

  • Project delivery and Client satisfactory enhancement factors needs to be optimized.

  • Construction projects must be meticulously planned.

  • Construction clients must ensure that adequate funds are available before executing the project.

  • Important positions in the construction firms must be filled with the technically competent individuals.

ACKNOWLEDEMENT

The author would like to thank his friends and especially parents for always supporting me.

REFERENCES

  1. Assaf, S. A., and Al-Hejji, S. (2006). Causes of delay in large construction project. Int. J. Project Manage., 24(4), 349357.

  2. G. Sweis, R. Sweis, A. Abu Hammad, A. Shboul (2007), Delay in construction projects: The case of Jordan International Journal of Project Management 26 (2006) 665-674.

  3. El Razek, M. E., Basssioni, H. A., and Mobarak, A. M. (2008). Causes of delay in building construction projects in Eygpt.134(11), 831841.

  4. Adel Al-Kharashi and Martin Skitmore (2009). Causes of delays in Saudi Arabian public sector construction Projects, Journal of Construction Management and Economics, Vol. 27, pp. 323

  5. Lo, T. Y., Fung, I. W. H., and Tung, K. C. F. (2006). Construction delays in Hong Kong civil engineering projects. J. Constr. Eng. Manage., 132(6), 636 649.

  6. Lo and Yeung, 2004: V. H. Y. Lo and A. H. W. Yeung, Practical framework for strategic alliance in Pearl River Delta manufacturing supply chain: A total quality approach, International Journal of Production Economics 87 (3) (2004), pp. 231-240.

  7. Long, N. D., Ogunlana, S., Quang, T., and Lam, K. C. (2004). Large Construction projects in developing countries: A case study from Vietnam. Int. J. Project Manage., 22(7), 553561.

  8. Mahamid, I., Bruland, A., and Dmaidi, N. (2012). Causes of delay in road construction projects. J. Manage. Eng., 28(3), 300310.

  9. Majid, I. A. (2006). Causes and effect of delays in Aceh construction industry. Masters thesis, Univ. of Technology Malaysia, Johor Bahru, Malaysia.

  10. Semple, C., Hartman, F., and Jearges, G. (1994). Construction claims and disputes: Causes and cost/time overruns. J. Constr. Eng. Manage., 120(4), 785 795.

  11. Toor, S. U. R., and Ogunlana, S. O. (2008). Problems causing delays in major construction projects in Thailand. Constr. Manage. Econ., 26(4), 395408.

  12. Alaghbari, W., Kadir, M. R. A., Salim, A., and Ernawati, A. (2007). The significant factors causing delay of building construction projects in Malaysia. Eng. Constr. Archit. Manage. J., 14(2), 192 206.

  13. Albinu, A. A., and Jagboro, G. O. (2002). The effects of construction delays on project delivery in Nigerian construction industry. Int. J. Project Manage., 20(8), 593599.

  14. Atkinson R. (1999) Project management: cost, time and quality, two best guesses and phenomenon, its time to accept other success criteria, International Journal of Project management, 17(6),pp. 337- 342

  15. Al-Khalil, M. I., and Al-Ghafly, M. A. (1999). Delay in public utility projects in Saudi Arabia. Int. J. Project Manage., 17(2), 101 106.

  16. Al-Momani, A. (2000). Construction delay: A quantitative analysis. Int. J. Project Manage., 20(1), 5159.

  17. AlSehaimi, A., Koskela, L., and Tzortzopoulos, P. (2013). Need for alternative research approaches in construction management: Case of delay studies. J. Manage. Eng., 0000148.

  18. Anastasopoulos, P. C., Labi, S., Bhargava, A., and Mannering, F. L. (2011). Empirical assessment of the likelihood and duration of highway project time delays. J. Constr. Eng. Manage., 138(3), 390 398.

  19. Arditi D, Akan GT Gurdamar S. Reasons for delays in public projects in Turkey. Constr Manage Econ 1985;3:171-81.