🏆
Global Research Authority
Serving Researchers Since 2012

Optimizing Manufacturing Supply Chains Through SAP-Based Material Planning At Danfoss Systems Private Limited

DOI : 10.17577/IJERTCONV14IS120013
Download Full-Text PDF Cite this Publication

Text Only Version

Optimizing Manufacturing Supply Chains Through SAP-Based Material Planning At Danfoss Systems Private Limited

Tejas Dale

MBA, School of Business, Indira University,

Pune, India 411033 tejasdale19@gmail.com

Dr. Nitin Joshi

Associate Professor and Area Chair

– MBA, School of Business, Indira University,

Pune, India 411033 nitinjoshi.sob@indirauniversity.edu

.in

Dr. Manisha Maddel Associate Professor & Guide, School of Business,

Indira University,

Pune, India-411033 manisha.maddel@indiraisbs.edu.in ORCID: 0009-0008-1720-2959

Abstract In dynamic supply chains, material planning and inventory management play pivotal roles in ensuring uninterrupted manufacturing and cost reduction. The importance of integrating Enterprise Resource Planning (ERP) systems with Material Requirements Planning (MRP) tools for inventory management is emphasized in the existing literature, as it aids in optimizing inventory levels and managing supplier performance while tracking procurement. The aim of this study is to analyse the material planning processes of Danfoss Systems Private Limited, Pune, a global supplier of hydraulic solutions to achieve supply continuity. The main aim is to analyse the existing planning process, evaluate the extent of use of SAP/MRP and pinpoint supply constraints such as supplier delays, quality delays etc., and make practical recommendations. The methodology used in this study is a qualitative approach in applied industrial research which is carried out during a period of 2 months. The data was gathered by direct process observation, cross functional interaction and analysis of secondary data in SAP Materials Management transactions, Purchase Order (PO) Log and Non Conformance Report (NCR).

The results show that although SAP is providing the necessary real-time material information, it is not enough that the components are physically received to be ready for production because of the quality checks that must be performed and pending NCRs. Continuous tracking of open POs, shipment visibility, and proactive supplier expediting are all critical to overcoming recurring material shortage issues. The study results that the material planning system is a very integrated center of the system and the continuity of supply depends on the cross- functional smoothness of coordination between

procurement, quality, and logistics. Manual shortage tracking can be replaced by automated, centralized dashboards (like SAP Power BI) that track shortages across the supply chain to improve supply chain resilience. Further, the weekly follow up with suppliers, along with daily cross functional review of quality held inventory will help material release in a much quicker time, reduce risks of supply, and enhance overall operational efficiencies.

Keywords: Material Planning, Inventory Management, SAP ERP, Supply Chain Efficiency, Material Shortages.

  1. INTRODUCTION

    Operational efficiency, inventory management and supply chain optimization are essential factors that enables the manufacturing industry to compete in today's industry. Businesses are constantly confronted with various challenges such as changing customer requirements, increasing inventory expenses and unforeseen delays from suppliers that make it difficult to manage inventory optimally. Therefore, it is crucial for manufacturing to plan materials to ensure that the appropriate amount of material is on hand at the appropriate time. Material planning is a key step that bridges the gap between production needs and the control of materials, procurement and logistics. With the help of Enterprise Resource Planning (ERP) systems such as SAP or Material Requirements Planning (MRP) software, companies can determine the need for materials, track purchase orders and monitor stock levels to avoid any production delays.

    Danfoss Systems Private Limited is based at Pimpri, Pune, in the field of hydraulic power and control solutions, providing essential components to key Original Equipment Manufacturers (OEMs) for the agriculture, construction and mobile machinery sectors. The facility faces continuous

    supply chain issues due to the dynamic nature of the global sourcing process despite its structured material planning and inventory management system.The structured material planning and inventory management practices in the facility are still facing ongoing supply chain issues due to the dynamic nature of global sourcing. Danfoss commonly deals with the challenges of different lead times between domestic and international suppliers, materials on hand quality checks and materials that are not usable until they have been installed in the system. These factors may cause shortages in materials, too much inventory to carry, and constant supplier claims for expediting to avoid failing planned production schedules.

    This study will perform an operational evaluation of the material planning and inventory management processes at Danfoss Systems to find opportunities for better supply continuity and improve the overall operational processes. The study focuses on the transactions used in SAP ERP specifically: ME21N, MB52 and MD04 to control material requirements, material receipts and open purchase orders. The paper discusses important issues associated with material shortages, such as On-Time Delivery (OTD) performance by suppliers, ABC classifications of inventory and quality held materials. The overall goal of the research is to offer practical and data-based suggestions to increase material availability, optimize material control and optimize the overall efficiency of the supply chain in the organization.

  2. LITERATURE REVIEW AND THEORITICAL BACKGROUND

    1. Literature Review

      Enterprise Resource Planning (ERP) systems have regularly been shown to transform manufacturing supply chains, a fact consistently emphasized in academic literature. This research by Palewatta and Perrera (2017) and Kurniawan et al. (2025) highlights the fact that ERP implementation can substantially cut down the inbound logistics costs, lower product lead times and enhance inventory control. In particular, Sambhaji et al. (2022) and Jayachandran (2014) have argued that using SAP ERP tools is essential to ensure deliveries are on schedule and materials are automatically managed within the complex manufacturing environment. Additionally, Sengottuvelu (2020) and Pratiwi (2025) explain that the combination of Material Requirements Planning (MRP) and a good digital inventory management system improves the production planning process and helps to overcome critical material shortages.

      The need for cross-functional alignment also keeps recurring, as recent studies have shown that digital ERP solutions can drive critical supply chain integration and flexibility, which, in turn, have a direct impact on business performance (Anjum et al., 2023; Pattanayak et al., 2019). Together, this literature highlights the need to move beyond isolated tracking and

      towards an integrated, SAP-driven approach for effective material planning. These basic studies are directly applicable to this research, which focuses on using ERP data, cross- functional coordination and proactive supplier expediting to overcome supply bottlenecks and ensure manufacturing continuity.

    2. Theoritical Background

    Material planning and inventory control are essential for uninterrupted production and availability of materials on time, while keeping a hold of excess materials. At the heart of this process is Material Requirements Planning (MRP), which uses production plans, existing stock levels and rder arrival dates to anticipate any material shortages. Today in modern manufacturing, these processes are well-integrated with Enterprise Resource Planning (ERP) systems such as SAP. SAP has integrated data from different functional areas and uses specific transactions to track stock availability (MB52, MMBE), material requirements (MD04), purchase orders (ME21N, ME2M) and goods receipt (MIGO).

    In addition to internal planning, supply continuity is dependent on good supplier management and logistics. Supplier performance is strongly measured by On-Time Delivery (OTD) rates and regular expediting and follow-ups reduce production shortfalls. Additionally, by working with logistics firms such as DHL, ACPL, and Blue Dart, you can track both domestic and international shipments, providing visibility on incoming materials. But being physically in hand does not mean that the production is ready materials need to be quality checked. There is a direct link between Quality holds and Non-Conformance Reports (NCRs) on rejected materials and the amount of usable inventory, and this requires a close watch on quality management and communication with suppliers to close the financial transaction. In conclusion, combining these theoretical concepts with continuous improvement techniques and Root Cause Analysis (RCA) enables companies to systematically determine the root causes of supply delays and quality holds, further optimizing their supply chains.

  3. MATERIALS AND METHODS

    1. Research Objectives

      The overall objective of this research is to critically review and improve the material planning and inventory management process based on SAP to maintain Continuous Manufacturing Supply Chain.

      1. Study of the current material planning systems and business processes at Danfoss Systems Private Limited.

      2. Measurement of the effectiveness of SAP and Material Requirements Planning (MRP) systems in monitoring inventory levels, material needs and lack of materials.

      3. Critical Analysis of Material Availability Purchase Order Execution Evaluation, Supplier Delivery Commitment, Inbound Shipment Flow.

      4. Root Cause Analysis and classification for the root causes of the supply chain disruptions, particularly material shortages, supplier delays and quality related inventory holds.

      5. Data driven recommendations to optimize inventory control, supply continuity, and overall supply chain efficiency. Data Collection and Research Design.

    2. Data Analysis

      This study is project based, applied industrial research design with qualitative approach and quantitative approach. The research is undertaken over a period of two months from 15 May 2026 to 15 July 2026 at Danfoss Systems Private Limited, thus covering the entire material flow process. The primary data gathered consisted of direct process observation, supplier expediting activities and cross functional process discussion with Production Planning, Procurement and Quality departments. To analyze all the details, secondary data was systematically gathered from SAP ERP system comprising a purchase order, inventory report, shipment load, Goods Receipt documentation, Non Conformance Reports, etc.

    3. Data Analysis and Quality Assessment

    The method used in this research is using the SAP Materials Management (MM) module to evaluate the inventory visibility and procurement execution. MD04 (Requirement Planning) and MB52 (inventory monitoring) SAP transactions were used to analyze the difference between system-available inventory and material requirements. One of the most important parts of this evaluation is the inspection phase: the actual delivery of the product is not a measure of production readiness. All materials received are thoroughly checked for compliance, with non-conforming materials quarantined or recorded as Non-Conformance Reports (NCRs). Taking these temporary holds into consideration with the Root Cause Analysis (RCA), the study identifies these delays in inspections and materials rejection that temporarily affect the amount of inventory in use, forcing cross-functional resolution in a very short time.

  4. DATA ANALYSIS AND DISCUSSION

    TABLE I.

    comprehensive Analysis of Current Material Planning Stages and Workflow

    Process Stage

    Core Activity

    Purpose and Strategic Function

    Production Planning

    Production requirement identification

    Identify and map exact material requirements based on OEM demand.

    MRP

    Material requirement analysis

    Run MRP to identify potential material shortages automatically.

    Inventory

    Stock availability check

    Verify currently available, usable stock within the plant.

    Procurement

    Purchase Requisition / PO processing

    Arrange required material by generating official supplier orders.

    Supplier Coordination

    Confirmation and follow-up

    Monitor supplier production status and verify delivery commitments.

    Logistics

    Shipment tracking

    Track domestic/international shipments to monitor incoming material.

    Goods Receipt

    Material physical receipt (GRN)

    Formally record the arrival of materials at the Danfoss facility.

    Quality

    Inspection / Quality Hold

    Verify material quality before authorizing its use in manufacturing.

    Production Support

    Material release for production

    Ensure quality- cleared material is immediately available for assembly.

    The material planning process at Danfoss Systems Private Limited is analyzed and it is concluded that it is an integrated process in which different departments are involved instead of a process carried out in isolation. The workflow is sequential in nature, as described in the table, and starts with

    the production requirements and ends with the release of the

    C

    quality-cleared material onto the manufacturing floor.

    Important to note from this observation is that the availability of materials is not a reflection of just stock-on-hand. Rather, it is very dependent on a cycle of incoming purchase orders, supplier commitments, tracking in shipment, and rigorous quality controls. As a result, if there are any delays or logistical issues at an earlier stage in the process, they will ripple down the production chain and reinforce the critical

    need for smooth collaboration between the production, procurement, logistics, and quality teams.

    TABLE II.

    THE STRATEGIC USE OF SSAP ERP TRANSACTIONS IN

    MATERIAL PLANNING.

    SAP

    Transaction Code

    Primary Function

    Application in Shortage and Inventory Monitoring

    MD04

    Material Requirements

    Provides real-time visibility into material requirements and overall availability.

    MB52

    Stock Information

    Displays detailed current stock information across different storage locations.

    MMBE

    Stock Overview

    Offers a comprehensive overview of stock availability and inventory status.

    ME2M

    Purchasing Document

    Tracks open Purchase Orders categorized specifically by material numbers.

    ME23N

    Purchase Order Details

    Allows planners to drill down into specific Purchase Order details and terms.

    MB51

    Material Movements

    Tracks historical and current material movements within the supply chain.

    MIGO

    Goods Receipt

    Executes and records the formal receipt of goods entering the facility.

    Material Planning department is the operational core of Enterprise Resource Planning tools and the most vital is the SAP Materials Management (MM) module. The observed SAP transactions are linked to a single point of view of the entire procurement and inventory lifecycle. For example, with tools such as MD04 planners can keep track of the materials needed at any given time using the production schedule, and with MB52 and MMBE they can get up-to-the- minute information about available materials. Moreover, the ME2M and ME23N can track purchase orders, so that the

    procurement status of critical components is always available.

    The digital integration is crucial as it moves the planning team away from being reactive and into a proactive mode. The specific assignment of these transactTion codes enables the material planners to quickly locate material shortages and to receive notification of material movement and goods receipt for materials quickly, thus reducing the risk of impendence of

    production.

    TABLE III.

    Multi-Variable Analysis of Material Availability, Procurement, and Logistics

    Category

    Parameter / Status

    Observation and Impact on Planning

    Inventory

    Available Stock

    Immediately usable for production; represents true

    current supply.

    Inventory

    Quality Hold

    Physically present but temporarily unavailable pending

    inspection.

    Inventory

    Rejected Material

    Not available for production; requires NCR and credit note

    follow-up.

    Category

    Parameter / Status

    Observation and Impact on Planning

    Procurement

    Open PO

    Represents expected future supply; monitored strictly

    through SAP.

    Procurement

    Supplier Confirmation

    Followed up regularly to ensure expected delivery

    aligns with demand.

    Procurement

    Critical/Delayed Material

    Requires immediate expediting and direct supplier

    intervention.

    Logistics

    Domestic Shipments

    Faster turnaround; requires consistent tracking via logistics

    partners.

    Logistics

    International Shipments

    Longer lead times; requires distinct coordination and

    earlier follow-ups.

    A detailed study of component availability, order status and logistics has shown that a component does not become

    available for production as soon as it is physically received. Being able to see inventory is a subtle issue materials can be physically posted on site but in the process of a required quality hold or awaiting resolution of a Non-Conformance Report (NCR). The material planning team proactively follows up on open purchase orders and actively checks supplier confirmations to reduce these variables. Furthermore, strong logistics partner relationship management and international/external shipments ensure that any risk of shipment delay is identified early. This full end- to-end visibility of available inventory, procurement agreement and inbound logistics helps the organisation have a clear view of available hydraulic components so it can trigger the right expediting procedures when needed and prevent the production floor from receiving unnecessary components.

    TABLE IV.

    Identified Issue

    Primary Challenge Category

    Possible Root Causes and Contributing Factors

    Material Shortage

    Supply Chain Disruption

    Supplier manufacturing delays or insufficient incoming supply volume.

    Delivery Delay

    Logistics / External

    Domestic or international logistics issues; transportation bottlenecks.

    Material Unavailability

    Internal Process Hold

    Materials halted in the system due to mandatory quality inspection holds.

    Rejected Material

    Quality Non- Conformance

    Parts failed specifications; initiates a complex NCR and credit process.

    PO Pending

    Procurement Bottleneck

    Lack of initial supplier confirmation or delayed procurement follow-up.

    Delayed Closure

    Cross- Functional Gap

    Poor coordination among suppliers,

    ROOT CAUSE ANALYSIS OF SUPPLY CONTINUITY CHALLENGES

    Procurement, and Quality teams.

    The study, based on direct observation and cause analysis, found a number of interconnected issues commonly pose threats to supply continuity. The largest problems are with external factors such as late deliveries from suppliers or any uncertainty associated with incoming shipments. The major internal challenges are when received materials are quarantined during quality inspection holds and materials are turned down because they are not in conformance, thus reducing the materials available for use. Material planning is dependent on external vendor and internal departments such as quality and procurement having tasks completed in time and if that does not happen, then it has a knock on effect. The constant problems also show that material shortages seldom occur in isolation and usually result from previous coordination failures and the need for constant monitoring, proactive expediting, and speedy solution of the overdue purchase orders and NCRs.

    There are strategic recommendations for improving supply chain efficiency listed below and summarized in TABLE V.

    TABLE V

    Strategic Recommendations for Enhancing Supply Chain Efficiency

    Recommenda tion

    Underlyi ng Reason

    Implementat ion Approach

    Expected Outcome

    Strengthen SAP

    Monitoring

    Improves visibility of actual material status.

    Regularly review MRP, stock data, and PO information via SAP.

    Better planning and faster identificati on of shortages.

    Improve PO Follow-up

    Reduces uncertaint y regarding incoming supply.

    Track open POs and supplier commitments consistently.

    Improved overall material availabilit y.

    Strengthen Shipment Tracking

    Identifies potential delivery delays early.

    Maintain regular domestic and import shipment tracking routines.

    Better visibility of inbound materials.

    /tr>

    Improve Quality Coordination

    Quality- held materials delay productio n.

    Regularly review quality holds and NCR status with the Quality team.

    More accurate mapping of usable inventory.

    Standardize Shortage Tracking

    Enables quicker action on critical materials.

    Maintain a structured, uniform shortage tracking format.

    Faster expediting and significant ly reduced supply risk.

    Enhance Cross- Functional Sync

    Material planning relies on multiple departme nts.

    Schedule regular syncs between PPC,

    Procurement, Logistics, and Quality.

    Better informatio n flow and overall planning efficiency.

    The suggested improvements are aimed at boosting the system's visibility, streamlining tracking processes, and improving communication between different stakeholders to overcome the identified operational challenges. By regularly analysing data from stocks and stock orders, the use of SAP can be optimised to a great extent, which means that uncertainty about the materials to be received is minimised. In addition, having a consistent approach to tracking a shortage and following up with suppliers and incoming shipments will enable the planning team to alert to any potential delays, in advance of the effect on production. Improvements in coordination with the quality department to speed the processing of held or non-conforming materials are also essential. In the end, these practical and progressive measures from tracking every detail to aligning departments will help the organization to build a more resilient supply chain, better control stock levels and ensure materials are always available for production.

  5. FINDINGS, CONCLUSIONS AND SUGGESSIONS

    1. Findings

      The study shows that material planning is a vital link function that helps to ensure continuity of supply and uninterrupted production at Danfoss Systems Private Limited. One of the main results is that Enterprise Resource Planning systems like SAP and Material Requirements Planning (MRP) offer valuable visibility on material requirements, current stock levels, and procurement statuses in real time. The research is a cautionary tale, however, that relying on system data alone is not enough: regular follow-up of open Purchase Orders

      (POs) and proactive follow-ups with suppliers are essential to ensure that material is available or that shortages are avoided. The analysis expressly states that the materials at the facility may not be immediately ready for production, as parts often have to be quality inspected, and are frequently placed in a "hold" while Non-Conformance Reports (NCR) are processed, thereby temporarily but significantly reducing usable materials. In addition, stringent shipment monitoring for both domestic and international supply chain partners was crucial for predicting delivery issues and possible supply shortages early on. In sum, the results demonstrate that to overcome complicated supply chain issues like delayed supplier deliveries, unpredictable shipping timelines, and quality concerns about materials, it is vital to have strong alignment across functions. The overall success of the material planning system is highly dependent on the effective, continuous flow of information and coordination between Production Planning and Control (PPC), Procurement, Quality, Logistics and supplier networks. If the operational approach is not integrated, the impact of the material shortages and keeping optimal inventory control is always a challenge.

    2. Conclusions

      Based on the results of the study, it can be concluded that material planning is a pivotal and central position between production requirements and available materials in Danfoss Systems Private Limited. The results show that using only physical stock is not enough for continuous manufacturing; a continuous supply only happens when SAP and Material Requirements Planning (MRP) tools are used in an effective and integrated manner, combined with strict external monitoring. The material planning department can effectively prevent production delays through systematic monitoring of open purchase orders, proactively coordinating with suppliers, tracking incoming shipment statuses, and keeping track of the status of quality checks. The project was successful Cin achieving its key objectives, which included: Promoting the practical implementation of theoretical operations and supply chain management concepts to address real-world industrial problems, including supplier delays, logistic uncertainties, and required quality holds. Finally the study suggests that to further improve supply chain resilience, the organization needs to strategically upgrade its work by standardizing the tracking of shortages, increasing cross-functional communication between the procurement, logistics and quality functions and maximizing the visibility of data in SAP. Implementing these practical recommendations will help with proactive planning decisions, reduce inventory carrying costs, reduce supply risks, and greatly improve the manufacturing supply chain's overall operational efficiency.

    3. Suggestions

      There is a need for Danfoss to have a centralised, automated dashboard to track shortages, directly connected to SAP to boost supply chain efficiency. This practical digital improvement allows everyone concerned to have a real-time view, so that the Material Planning and Production Planning and Control (PPC) teams can match incoming stock with the production schedule. Further, Procurement needs to implement a standard weekly follow-up procedure with Suppliers to clearly validate their Purchase Orders and delivery agreements, which helps to avoid unpleasant delays. Logistics should have a proactive tracking procedure in place that is unique for domestic and overseas goods received. In addition, the Quality department should perform cross functional reviews of the quality-held items and Non Conformance Reports (NCRs) daily to expedite material release and avoid the potential of material becoming unusable because it has been held in quality. Creating these formal, inter-departmental communication processes helps to ensure that data moves correctly, reducing supply threats.

    4. Conclusions of the study

      The study's results have many implications for several actors in the Danfoss value chain. The Material Planning and Production (PPC) teams benefit from this by transforming their process from a reactive expediting approach to a proactive scheduling model, streamlining the manufacturing process and minimizing downtimes.

      The Procurement department is heavily involved and the research has pointed out that issuing a PO is not enough, there must be continuous follow-ups with suppliers to ensure the On-Time Delivery (OTD). Stiffer checks on performance for Suppliers, and more open communication about their production statuses.

      In addition, the Quality department is now more accountable for the effective processing of material in "hold" and Non- Conformance Reports (NCRs) it is not enough to receive a material and the material has to be ready for production. In the end, these cross-functional, integrated practices ensure that Management and OEM Customers can expect lower inventory holding costs, lower supply chain risk and product on time and in full for their customers.

    5. Future Scope of the study

There are several opportunities to further digitize and optimize material planning framework at Danfoss Systems Private Limited in the future. Future research could explore the creation of integrated Power BI dashboards that would improve the accessibility of material and inventory tracking in real-time. It also seems like there is a lot of opportunities to leverage automated monitoring of Open Purchase Orders and stock shortages to limit manual expediting. Further research

might then look into the direct incorporation of supplier deliverydata into primary planning systems to further analyse supplier performance and delivery trend. Moving forward, future projects are required to involve increased digital integration between cross-functional teams, namely Production Planning and Control (PPC), Procurement, Quality and Logistics. Last but not least, a more detailed analysis of inventory optimisation with the use of larger inventory data sets can give more detailed and data-driven insights into how to optimise carrying costs while keeping the supply chain going.

ACKNOWLEDGMENT

I would like to thank the management and operational staff of the host organization for providing me with such a valuable internship project for the summer where they mentored and offered technical and operational assistance. I would also like to express my gratitude to my academic advisor and industry mentor who was always so supportive and encouraging that I was able to complete this research study successfully.

Disclaimer: This academic paper represents the personal opinions of the author, and is not necessarily the opinion of the host organisation. Proprietary and confidential information has been carefully redacted.

REFERENCES

  1. Anjum, K., Mirza, J., ur-Rashid, T., & Wakeel, A. (2023). Process re- design and automation using Enterprise Resource Planning system for manufacturing industry. MATEC Web of Conferences, 381, Article 01013. https://doi.org/10.1051/matecconf/202338101013

  2. A study on inventory management and control: Case study at WABCO India. (2017).

  3. Bansal, S. (2003). Supply chain planning: Theory and practice of Advanced Planner and Optimizer in supply chain domain.

  4. Case study article: Material management and inventory planning of a manufacturing company. (2019).

  5. Connecting MRP, MRP II and ERPSupply chain production planning via optimization models. (2005).

  6. Devarashetty, P. K. (2022). Supply chain optimization through SAP Advanced Planning and Optimization (APO) and Global Available-to- Promise (GATP). Journal of Artificial Intelligence, Machine Learning and Data Science. https://doi.org/10.51219/jaimld/pavan-kumar- devarashetty/377

  7. Implementation and optimization system ERP in inventory control. (2016). https://doi.org/10.5935/2447-0228.20160020

  8. Jayachandran, S. (2014). ERP implemented in fabtech industry using SAP. International Journal of Innovative Research in Science, Engineering and Technology, 3(11). https://doi.org/10.15680/IJIRSET.2014.0311025

  9. Kurniawan, I., Saraswati, T., & Ongkopratama, P. D. P. (2025). Enhancing production planning and inventory control with a web- based system: A case study in an Indonesian packaging manufacturer company. Jurnal Teknik Industri, 26(1), 105126. https://doi.org/10.22219/JTIUMM.Vol26.No1.105-126

  10. Mahalakshmi, V., & Venkateswaran, N. (2011). ERP application in India: An overview. International Journal of Enterprise and Innovation Management Studies, 1(3).

  11. Manohar, A., Kumar B. J., A., & Vijaya Kumar, H. L. (2019). A comparative study on supply chain key performance indicators of ERP software solution-aided apparel export units with non-ERP apparel export units. International Journal of Engineering Research & Technology, 8(6).

  12. Ocaña Valle, C. R. (2017). Optimización del proceso de compras e importación en una empresa manufacturera de autopartes: Indima, mediante el soporte de un MRP [Bachelor's thesis, Universidad de Las Américas]. Repositorio Digital Universidad De Las Américas.

  13. Ooi, C. W., Idrus, R., & Abdullah, N. L. (2017). Extended ERP for inventory management: The case of a multi-national manufacturing company.

  14. Palewatta, I. T., & Perrera, H. S. C. (2017). Inventory optimization using ERP to reduce final product lead time, inventory value and inbound logistics cost for MTO, FMCG company. International Journal of Multidisciplinary Studies, 3(2), 7.

    https://doi.org/10.4038/ijms.v3i2.7

  15. Pattanayak, S. K., Roy, S., & Satpathy, B. (2019). Does integration of business processes and ERP improves supply chain performances? Evidence from Indian capital goods industry.

  16. Pratiwi, N. D. (2025). Penerapan sistem ERP dalam perencanaan produksi dan pengendalian persediaan di PT Konimex.

  17. Sambhaji, J. S., Lakshminarasimhan, S. N., & Ganiger, B. (2022). Studies on effective usage of SAP ERP tool to control materials planned delivery time in oil and gas industries. Journal of Mines, Metals and Fuels, 70(8A), 112116. https://doi.org/10.18311/jmmf/2022/32025

  18. Sengottuvelu, C. (2020). Material requirement planning and inventory management: A case study of paint manufacturing unit in India.

  19. Soni, A., & Choudhary, V. (2013). Exploration & optimizing of internal supply chain management for manufacturing industry: Using SAP-LAP.

  20. Takahashi, K., & Nakamura, N. (2001). Production planning and inventory control in a company manufacturing PC parts: A case study. Production Planning & Control, 12(3).

  21. The effect of digital ERP implementation, supply chain integration and supply chain flexibility on business performance. (2024). International Journal of Data and Network Science, 8, 23992414. https://doi.org/10.5267/j.ijdns.2024.5.017