Global Peer-Reviewed Platform
Serving Researchers Since 2012

Risk Management for Improving Safety in Building Construction

DOI : 10.5281/zenodo.20441027
Download Full-Text PDF Cite this Publication

Text Only Version

Risk Management for Improving Safety in Building Construction

Rajeshwar Naik Lunavath

Civil Engineering Department

Proconstruct Intelligence Ltd, 164 Strathmore Crescent, Newcastle Upon tyne, Ne4 8UA

Abstract

The main aim of this paper is to identify safety risk factors in building construction projects and use of risk management techniques to reduce the impacts of these risk factors. A survey was conducted consist the set of 30 respondents who are working as project managers, engineers and officers in the field of building construction. The responses received were analyzed using Relative Ranking Index (RRI) analysis and various Multi Criteria Decision Making (MCDM) methods. The aim is to explore the main factors that are responsible towards safety risk. Lists of factors in building construction are identified from library resources, literature reviews and 65 major safety risk factors were identified. In risk assessment, a safety questionnaire was designed to assess the top risk factors and to investigate the application of risk management tools. Using RRI method the 65 major factors were prioritized, the top factors having RRI value greater than or equal to 0.75 are considered. Out of 65 major factors 16 factors were above 0.75, these 16 factors were prioritized using Analytical Hierarchy Process (AHP) creating a Hierarchy having 3 levels namely: 1) Goal 2) High level criteria and 3)Low level criteria and ranked accordingly. There were five key risks identified namely:1) Management processes towards safety 2) Attributes toward safety 3) Fatality at working 4) Individual performance 5) Risk processes.

In this present study, a case-study was presented with utilizing these 16 major safety factors for identifying the maximum risk exposed on the project. This analysis was done by using Multi Criteria Decision making methods which include Analytical Hierarchy processes (AHP), Technique for Order Preference by Similarity to Ideal Solution (TOPSIS), Multi Attribute Utility Theory (MAUT).

Keywords: safety risk, risk management, construction safety, decision making

  1. INTRODUCTION

    The construction industry has raised its heights in developing buildings with modern equipments and labor source. Building Construction is very unsafe workplace where most commonly serious and non-fatal vocational injuries occur due to its unique nature. The construction industry has to be given particular in providing Health and safety to the workers, as the construction industry itself is a high risk prone area to get accidents occurred. Although remarkable improvements have been made in safety and health performance in many countries, the construction industry continues to lag behind most of other industries. Building projects are sometimes allied with poor performance and lack of control during the construction phase leading to hurt and fatality making it one of the most dangerous industries. The Aim is to determine the major factors and for measuring risk management in the construction industry to promote safe working environments at building construction sites.

    The Occupational Safety and Health Act (1970) is established to provide guidelines for safe worksite practices and to ensure the safety of the workers. The citations that are

    issued to the worker by Occupational Safety and Health Administration (OSHA) providing safety. Satish B. Mohan et.al (2002)

    R.A. Haslam, S.A.Hide, Gibb, et al. (2004), said that the hierarchy of causal influences, illustrate that accidents occur as a result of the poor interaction between workers or work team, workplace and materials/personal protective equipment that originate due to deficit in the construction design and process, risk management, project management, client and economic influences, or safety training and education. Goran Janakovi et.al (2011) described that increasing the effectiveness of OHS increases the safety of an organization as its important. Safety performance indicators measure the changes in the level of safety connected to, response, preparedness and accident prevention over time, which result from the actions taken to reduce appropriate risks.

    Chia-Fen Chi et.al (2004) presented the contributing factors that are leading to fatal occupational falls in construction industry. Individual factors included age, gender, experience, and the use of personal protective equipment (PPE).Primary and secondary prevention measures been used to

    prevent falls or to mitigate the consequences of falls.

  2. AN OVERVIEW OF CONSTRUCTION SAFETY

    PERFORMANCE IN DEVELOPING COUNTRIES

    The construction industry plays a most important in the economy of developing countries and is generally regarded as one of the most essential area in terms of its impact on health and safety (H&S), In the developing countries H&S awareness and performance is low, and has to be improved. Construction in developing countries like India and Pakistan is more labor demanding in the developed areas of the globe, involving 2.5-10 times as many workers per activity. Farooqui (2008). Typically workers tend to be unskilled and migrate in a group, with or without their families, throughout the country in search of employment. But they are usually divided into various fractions. Communication problems related to difference in language, culture and relation tend to inhibit safety on the work site.

    Patrick X. W. Zou et.al (2009) described that the main perception of safety risks came from human-and/or procedure related issues, with low/no safety education. To lower the construction safety the government should develop collective legislation and safety protection procedures, and enforce

    safety education and training to all site participants.

  3. SAFETY RISK FACTORS IN BUILDING CONSTRUCTION SITES

    The risk factors included in this chapter were obtained from:

    A literature review of the factors influencing safety in the construction sites, discussions with safety experts in building construction sites. The characteristics of the construction industry are similar to those of other countries in term of regulations, project types, weather conditions, management systems, labor workforce, etc.

    Goran Janackovic et.al (2011) defined the structure of safety factors, performances and indicators into four groups Technical, Human, Organizational and Environmental. Behzad Esmaeili et.al (2015) Quantified safety risks and performed comparative analyses of different safety risks, out of different risks 22 safety risk attributes that lead to struck-by incident were identified and their relative risks were quantified. The attribute-based safety risk data fills a knowledge gap that has long prevented the integration of empirical safety data with technological models.

    Lopez-Arquillos et.al (2014) presented an investigation of the activities and related

    safety risks in different vertical formwork activities in civil engineering construction. By using the methodology of staticized groups, 12 activities and 10 safety related risks 14 were identified and validated by experts. Every safety risk identified was quantified for each activity.

    The literature review was used to identify the risk factors that affect safety in building construction sites. Several risk factors were identified. Similar risk factors were merged together. Few risk factors were deleted, and few new risk factors were added based on the suggestions made by safety experts and professionals in construction industry. Sixty five safety risk factors in building constructin were finally selected.

  4. RISK MANAGEMENT

    The risk management is a structured process which proactively manages the risk events, reduces potential threats, providing proper measures to improve the value for money in construction. To control the level of risk and mitigate its effects, risk management should be applied. The risk management process requires risk identification, analysis and assessment, as the first steps for planning and implementing risk response strategies.

    P. Jaskowski et.al (2011)

    The elements of construction risk management are:

    1) identify and classify risk sources, 2) assess risk sources in order to come up with a logical understanding about them, 3) respond to risk sources to give decisions on how to deal with each one of them, and 4) control risk sources throughout the project life cycle.

      1. Risk Identification

        The potential risks are identified by recognizing, filtering, and ranking them in a profile. The risks of different types are placed in different categories by considering their predetermined characteristics.

        Martins Claudia Garrido et. al.,(2011) defined Risk identification is an essential step before risk assessment. It is important to consider the different risk sources present in the project and the different risk classifications with a clear distinction between risk sources and effects.

      2. Risk Assessment

        Krantikumar Mhetre et al., (2016) defined the most effective and widely used ones are qualitative and quantitative risk assessments. The choice of the appropriate approach depends on the project type and size, available information, available cost and time, and analyst expertise.

        S. M. Renuka et.al (2014) defined a number of systematic models have been proposed for use in the risk evaluation phase of the risk management process. Out Among different approach models AHP model is more effective, because of its systematic approach to structuring risk assessment problems by providing hierarchical approach.

      3. Risk Response, monitoring and control

    Risk response is the establishment of a strategy to mitigate the potential threats and maximize the potential opportunities. Risk monitoring and control is essential to ensure the achievement of the desired effects of the risk response implementation throughout the project life cycle.

    Hamzah Abdul Rahman et.al (2013) defined the output of risk monitoring and control will give lessons for future decision makers. The success of the risk response is assessed on an ongoing basis throughout the project to correct any deviation of the implemented strategy and to realign it with the project objectives. It is necessary to loop back to the risk assessment stage, whenever risks change their nature or new risks arise during the project.

  5. METHODOLOGY

    The risk influencing safety factors Identification were done through literature review and discussions with experienced ones in the building construction field. The literature review was used to identify the risk factors that affect safety in the construction sites. Seventy five risk factors were identified. Some similar risk factors were merged together and few risk factors were deleted, and few new risk factors were added based on the suggestions made by experienced ones in the construction industry. Sixty five safety risk factors were finally selected.

    A survey is a pre formulated written set of questions to which respondent record their answers, usually define the type of barrier. This survey was done on total of 30 respondents and the questionnaire forms were distributed among the respondent of survey consists of 2 Project Managers, 3 Assistant Executive Engineers, 16 Site Engineers, 3 Ph.D. Scholars, 4 m.tech students, 2 Safety Engineers. Face to face meetings, phone discussions and email communication were conducted with concerned professionals.

    Relative Ranking Index (RRI) is adopted in the selection of criteria using five-point

    Likerts scale. Respondents were asked to indicate the level of importance of these barriers on a five-point Likerts scale. 1 means barrier is Unimportant, 2 means of little importance, 3 means Moderately Important, 4 means Important, and 5 means is Very Important. The identified risks in building construction are few sample of potential hazards and can be seen on every building construction site.

    1. Relative Ranking Index (RRI)

      Relative Important Index (RRI) is a technique used for analysis and ranking of safety factors from the feedback given by various respondents. The RRI can be calculated using the following equation

      Where, w is the weight assigned by respondent to the factor (ranging from 1 to 5);

      X is frequency of each weight age.

      A is the highest weight (5 in this study);

      N is the Number of respondents in the survey.

      The contribution of each of the risk factor to overall in building construction was examined using RRI method and the ranking of the factors in terms of their weights as perceived by the respondents were done.

      Table 5.1: Safety factors considered in survey and their Responses from Respondents using RRI method

      S/No

      Safety Risk Factors

      RRI

      1

      Commitment of management towards contractor safety

      0.86

      2

      Safety Education: orientation and specialized training

      0.78

      3

      Worker involvement at construction site

      0.7533

      4

      Overall accident/incident investigations (workday case)

      0.68

      5

      Safety meetings for supervisors (internal)

      0.7

      6

      Overall drug and alcohol testing

      0.66

      7

      Planning Safety: pre-project and pre-task

      0.7333

      8

      Worker Evaluation

      0.6867

      9

      Staffing for safety on projects

      0.7333

      10

      Management of the risks to the health

      0.66

      11

      Health and welfare, environment of work.

      0.6467

      12

      Adequacy to the innovations of the processes

      0.6067

      13

      Inquiries of accidents and incidents

      0.66

      14

      Implementation of new installations and new equipment

      0.68

      15

      Maintenance of the installations and equipment

      0.6667

      16

      System functioning towards emergency

      0.7867

      17

      Developing safety policies

      0.7333

      18

      Appointing safety responsibilities to safety manager

      0.8267

      19

      Communication between management& workers on site

      0.7867

      20

      Safety Meetings for workers & supervisors (External)

      0.7333

      21

      Safety plans and records

      0.72

      22

      Safety rewards/incentives

      0.6733

      23

      Safety training

      0.76

      24

      Provision of plant and equipment maintenance

      0.68

      25

      Employment of safety officer and safety supervisor

      0.84

      <>26

      Provision of safe working environment

      0.6933

      27

      Conduction of site safety inspections and supervision

      0.74

      28

      Size of project

      0.62

      29

      Number of subcontractors

      0.5467

      30

      Complexity of project

      0.6267

      31

      Safety knowledge

      0.7533

      32

      Safety Attitude

      0.74

      33

      Investment made towards safety

      0.6467

      34

      Workers’ compensation insurance

      0.6867

      35

      Providing First aid box

      0.8533

      36

      Providing medical treatment

      0.7533

      37

      Providing sick ward for injured workers

      0.7067

      38

      Working at heights

      0.7867

      39

      Working with machinery

      0.7333

      40

      Working with noisy machinery

      0.68

      41

      Working near to swinging machinerys

      0.6933

      42

      Working without wearing personal protective

      equipment

      0.8133

      43

      Working with scaffolding

      0.7867

      44

      Manual handling and lifting operations

      0.74

      45

      Falling into an excavation pit

      0.6333

      46

      Working under high voltage overhead power lines

      0.7133

      47

      Working in confined spaces

      0.72

      48

      Working near to falling objects

      0.78

      49

      Hazards due to electrical Items/works

      0.6467

      50

      Emphasis on tool box meetings

      0.7267

      51

      Conducting safety audits and management reviews

      0.7533

      52

      Individual involvement on worksite

      0.8333

      53

      Maintaining record of previous accidents

      0.6733

      54

      Lack of financial allocation for safety management

      0.6933

      55

      Risk management

      0.7867

      56

      Risk evaluation at stage of construction

      0.7333

      57

      Risk identification, Risk control and Risk control

      measures to be implemented

      0.8

      58

      Implementing Risk assessment and procedures

      0.78

      59

      Conducting risk assessments before initiating any

      activity

      0.76

      60

      Compliance with the Risk Factors enlisted in the

      Code/Manual

      0.8267

      61

      Mock drill for safety due to possible risks

      0.7533

      62

      Compensation for loss if lives

      0.7467

      63

      Hindrance due to language problem

      0.6133

      64

      Lack of co-ordination between workers

      0.6867

      65

      Agreement between Workers & Contractors for

      Compensation towards major risk.

      0.7533

      Major safety factors

      The top factors having RRI value greater than or equal to 0.75 are considered as Major safety Factors. There are 16 factors considered as main factors when considered

      above 0.75, the 16 factors were further prioritized using AHP analysis and were ranked according to their weight age. These major factors are listed in following Table:5.2

      Table 5.2: Major factors according to RRI

      S/No

      Safety Risk Factors

      RRI

      1

      Commitment of management towards contractor safety

      0.86

      2

      Safety Education: orientation and specialized training

      0.78

      3

      System functioning towards emergency

      0.78

      4

      Appointing safety responsibilities to safety manager

      0.83

      5

      Communication between management and workers on

      site

      0.78

      6

      Safety training

      0.76

      7

      Providing First aid box

      0.85

      8

      Employment of safety officer and safety supervisor

      0.84

      9

      Working at heights

      0.78

      10

      Working without wearing personal protective

      equipment

      0.81

      11

      Working with scaffolding

      0.78

      12

      Safety knowledge

      0.75

      13

      Individual involvement on worksite

      0.83

      14

      Risk management

      0.79

      15

      Risk identification, Risk control and Risk control

      measures to be implemented

      0.8

      16

      Compliance with the Risk Factors enlisted in the

      Code/Manual

      0.83

      5.1 Analytic hierarchy process (AHP) for prioritizing the major factors

      The Analytical Hierarchy Process (AHP) is one of Multi Criteria Decision Methods (MCDM) developed by Saaty in 1970s is a technique to solve complex problem. Thomas L. Saaty (2008).

      As seen in the Table 5.2 there were similar RRI values which makes difficult in ranking them. To prioritize these top 16 factors at a time using AHP would be difficult so further

      analysis was made creating a hierarchy consisting of Goal, High level criteria and Low level criteria further AHP analysis was done. A structured questionnaire was prepared and survey was carried out using pair wise comparison. The high level of criteria are 1) Attributes toward safety 2) Management processes towards safety 3) Fatality at working 4) Individual performance 5) Risk processes.

      Figure 5.1: Hierarchy showing Goal, high and low level criteria

      Table 5.3: Ranking of factors from AHP analysis using weights

      High level criteri a

      Relative Weight

      Leve l 1 Fact ors

      Relativ e Weight

      Aggre gation of weigh

      ts

      Pri ori ty

      F1

      0.2695

      C1

      0.334

      0.091

      5

      C2

      0.667

      0.18

      1

      F2

      0.3065

      C3

      0.331

      0.102

      3

      C4

      0.203

      0.063

      6

      C5

      0.167

      0.052

      9

      C6

      0.142

      0.044

      10

      C7

      0.091

      0.028

      12

      C8

      0.063

      0.02

      14

      F3

      0.184

      C9

      0.527

      0.097

      4

      C10

      0.332

      0.062

      7

      C11

      0.139

      0.026

      13

      F4

      0.1761

      C12

      0.667

      0.118

      2

      C13

      0.334

      0.059

      8

      F5

      0.0718

      C14

      0.541

      0.039

      11

      C15

      0.258

      0.019

      15

      C16

      0.201

      0.015

      16

  6. CASE STUDY

    Risk factors Assessment

    In this chapter the Risk assessment was made taking the top sixteen criteria as shown in (Table 5.4) and four project Alternatives (Table 6.1) using various multi criteria decision methodologies like Analytic Hierarchy Process (AHP), Technique for Order Preference by Similarity to an Ideal Solution (TOPSIS) and Multi Attribute

    Table 5.4: Ranking of factors from AHP analysis

    Criteria

    Safety Risk Factors

    C1

    Safety Education: orientation and specialized training

    C2

    Safety knowledge

    C3

    System functioning towards emergency

    C4

    Working at heights

    C5

    Commitment of management towards contractor safety

    C6

    Appointing safety responsibilities to safety manager

    C7

    Working without wearing personal protective equipment

    C8

    Individual involvement on worksite

    C9

    Communication between management and workers on site

    C10

    Safety training

    C11

    Risk management

    C12

    Providing First aid box

    C13

    Working with scaffolding

    C14

    Employment of safety officer and safety supervisor

    C15

    Risk identification, Risk control and Risk control measures to be implemented

    C16

    Compliance with the Risk Factors enlisted in the Code/Manual

    Utility Theory (MAUT) for both Addition and Multiplication are compared and the features of these models are discussed. The use of MCDM methods in decision making problems provides the response collected and making them converted into weights. The level of risk in these four projects was identified using the four MCDM methods. Below table 6.1 shows the details of the projects taken in the case study:

    Table 6.1: Details of four projects taken in the case study

    S.No

    Details

    Project A

    Project B

    Project C

    Project D

    1.

    Name of work:

    Construction of Academic Building (Basement+G+6) For Materials and Metallurgical Engineering Department For National Institute Of Technology (NIT) at Warangal, Telangana, including internal Water Supply. Sanitary installations, Drainage, Electrical In34stallations, Lifts, Firefighting and Fire alarm system.

    Construction of Academic Building (Basement+G+6) For Chemical Engineering Department For National Institute Of Technology (NIT) at Warangal, Telangana, including internal Water Supply.

    Sanitary installations, Drainage, Electrical Installations, Lifts, Firefighting and Fire alarm system.

    Construction of Public utility building (Cellar+G+4) For Hospitality at Warangal, Beside Venkatarama Theatre. Including, Electrical Installations, Lifts, Firefighting and Fire alarm system. No. Of rooms 75 No. Of Beds 165

    Construction of Dr.B.R.Ambedkar Learning And 450 Nos. Capacity Auditorium With Steel Structure For National Institute of Technology (NIT) Warangal, Telangana.

    2.

    Name of the Contractor:

    M/s Sivanssh infrastructure Development Pvt. Ltd. 002 Gauri Apartments, 57, Hilton Lane, Meera Bai Marg, Lucknow 226 001.

    M/s Sivanssh infrastructure Development Pvt.

    Ltd. 002 Gauri

    Apartments, 57, Hilton Lane, Meera

    Bai Marg, Lucknow 226 001.

    Hari Babu, AGILE Infrastructure Pvt. Ltd.

    Shri. Shaik Akbar

    3.

    Client:

    CPWD

    CPWD

    Dr. N. Samuel

    CPWD

    4.

    ECPT

    Rs.48,11,92,339/-

    Rs.49,67,54,383/-

    Rs.8,96,00,000/-

    Rs.10,73,71,397/-

    5.

    Time allowed:

    600 Days

    600 Days

    910 Days

    450 Days

    6.

    Date of

    Commencement:

    15/01/2015

    15/01/2015

    01/05/2014

    03/02/2016

    7.

    Stipulated Date of Completion:

    05/09/2016

    05/09/2016

    01/12/2016

    28/04/2017

    8.

    No. of Workers

    260+

    300+

    60+

    60+

    Identifying level of risk in project alternatives using the top 16 criteria

    C1 C2 C3 C4 C5 C6 C7 C8 C9

    C10

    C11

    C12

    C13

    C14

    C15

    C16

    Criteria

    Alternatives

    Project A

    Project A

    Project A

    Project A

    Goal

    Figure 6.1 Hierarchy showing goal, criteria and alternatives of case study taken

    1. Analytic hierarchy process (AHP)

      AHP is able to assist decision maker in making complex decision. AHP is used in various area such as education, engineering, government, industry, management, manufacturing, personal, political, and social and sports. It is a multi-criteria decision analysis methodology that allows subjective as well as objective factors to be considered in the process which is precisely what is needed.

      Steps involved in AHP:

      1. Breaking down the decision problem into a hierarchy

      2. Comparing the elements in each level in pairs using Saaty’s scale, the number of needed

        Comparison for (n) criteria is given by n*(n-1)/2.

        Intensity

        Definition

        1

        Equal importance

        3

        Moderate importance of one over another

        5

        Essential or strong importance

        7

        Demonstrated importance

        9

        Extreme importance

        2,4,6,8

        Intensities values between the two adjacent judgments

        Table 6.2: Intensities of Relative Importance for Pair wise Comparison

      3. Calculating the average relative weight vector.

      4. Calculating the relative weights of the alternatives with respect to each criterion.

      5. Evaluating the consistency of the resulting weights find the Eigen vectors and the principal Eigen values (max)

      6. Verify consistency index and ratio.

      CI = (max 1) / (n 1)

      Inconsistency is calculated using the consistency ratio (CR),

      CR = CI/RI

      Where RI is a random number index, the values of which are shown in Table below:

      Table 6.3: Random consistency Index

      Size of the Matrix

      1

      2

      3

      4

      5

      6

      7

      8

      9

      10

      Random Consistency

      0

      0

      0.58

      0.9

      1.12

      1.24

      1.32

      1.41

      1.45

      1.49

      Table 6.4: overall priorities of alternatives

      Criteria

      Weight age

      Project A

      Project B

      Project C

      Project D

      C1

      0.036

      0.9105

      0.1738

      0.3324

      0.1738

      C2

      0.062

      0.375

      0.125

      0.125

      0.375

      C3

      0.071

      0.0624

      0.3151

      0.4151

      0.2083

      C4

      0.08

      0.0576

      0.3852

      0.3140

      0.2442

      C5

      0.062

      0.3872

      0.0921

      0.1353

      0.3862

      C6

      0.071

      0.1482

      0.6264

      0.0805

      0.1462

      C7

      0.08

      0.7091

      0.1267

      0.094

      0.0721

      C8

      0.054

      0.375

      0.125

      0.125

      0.375

      C9

      0.027

      0.4677

      0.2259

      0.0801

      0.2263

      C10

      0.054

      0.1609

      0.1369

      0.3511

      0.3511

      C11

      0.045

      0.5502

      0.1971

      0.0719

      0.1808

      C12

      0.071

      0.375

      0.125

      0.125

      0.375

      C13

      0.08

      0.5479

      0.3084

      0.0911

      0.0523

      C14

      0.062

      0.1463

      0.3435

      0.3112

      0.1990

      C15

      0.071

      0.2619

      0.1240

      0.1529

      0.4610

      C16

      0.08

      0.1454

      0.4578

      0.1640

      0.2327

      Overall priorities

      0.3324

      0.2568

      0.1864

      0.2518

      RANK

      1

      2

      4

      3

      From above table by using total score, Rank 4. Calculate the weighted normalized

      of alternative can be determined. Ranking of all alternatives are shown in Table 6.5.

      Table 6.5: Ranking of alternatives based on

      decision matrix V vij

      mn

      vij wij.rij , i 1,2….,m, j1,2, … ,n,

      ij

      Total score Where w is the relative weight of the jth

      j

      Project

      Relative Closeness

      Rank

      A

      0.3324

      1

      B

      0.2568

      2

      C

      0.1864

      4

      D

      0.2518

      3

      n

      criterion, and w 1

      j1

      1. Determine the ideal and negative-ideal solutions.

        1 2

        A* v*,v*,. ,v*mmax

        j vij

        j b ,min

        j vij

        j c ,

    2. Technique for Order Preference by Similarity to an Ideal Solution (TOPSIS) Method.

      Steps involved in TOPSIS:

      1. Construct normalized decision matrix.

        A v,v,….,v* min j vij j b ,max j vij j c

        m

        1 2

        Where b and c are the sets of benefit criteria and cost criteria, respectively.

        1. Calculate the Euclidean distances of each alternative from the positive ideal solution and the negative ideal solution.

          D* n (v v*)2 , i 1, 2,… , m,

          Where Pi is the priority of criteria i given by

          i

          j1

          i n

          ij j

          decision maker.

      2. Form the decision matrix between

        D

        ij

        (v

        j1

        j

        2

        v ) , i

        1,2,… ,m,

        alternatives and criteria based on the Decision maker responses.

        1. Calculate the relative closeness of each alternative to the ideal solution. The relative closeness of the alternative Ai with respect

      3. Normalize the decision matrix to A* is defined as

      mn

      X xij

      using the equation below

      RCi

      Di

      *

      ; 0 RCi 1; i 1,2, ,m

      rij

      xij ,i 1, 2,…., m; j 1, 2,….n Di Di

      The larger index value means the better

      where rij is the normalized criterion rating. performance of the alternative.

      C5

      3

      2

      3

      3

      C6

      4

      5

      4

      3

      C7

      5

      4

      2

      3

      C8

      4

      3

      2

      4

      C9

      5

      4

      4

      3

      C10

      4

      5

      3

      2

      C11

      4

      5

      4

      3

      C12

      2

      4

      3

      4

      C13

      5

      4

      5

      4

      C14

      5

      5

      4

      3

      C15

      2

      4

      3

      4

      C16

      5

      4

      2

      3

      C4

      Criteria

      Priority (pi)

      Normalized

      p

      Priority P = i

      i p

      i

      C1

      4

      0.0353982

      C2

      7

      0.0619469

      C3

      8

      0.0707964

      9

      0.0796461

      C5

      7

      0.0619469

      C6

      8

      0.0707964

      C7

      9

      0.0796461

      C8

      6

      0.0530974

      C9

      3

      0.0265487

      C10

      6

      0.0530974

      C11

      5

      0.0442478

      C12

      8

      0.0707964

      C13

      9

      0.0796461

      C14

      7

      0.0619469

      C15

      8

      0.0707964

      C16

      9

      0.0796461

      1. Rank the alternatives according to the relative closeness to the ideal solution. Table 6.6: Normalized Decision Matrix

        Alternatives

        /criteria

        A

        B

        C

        D

        C1

        0.553

        0.553

        0.442

        0.442

        C2

        0.452

        0.566

        0.452

        0.566

        C3

        0.458

        0.458

        0.611

        0.458

        C4

        0.493

        0.616

        0.37

        0.493

        C5

        0.539

        0.36

        0.539

        0.539

        C6

        0.493

        0.616

        0.493

        0.37

        C7

        0.681

        0.545

        0.273

        0.409

        C8

        0.597

        0.448

        0.299

        0.597

        C9

        0.616

        0.493

        0.493

        0.37

        C10

        0.545

        0.681

        0.409

        0.273

        C11

        0.493

        0.616

        0.493

        0.37

        C12

        0.299

        0.597

        0.448

        0.597

        C13

        0.553

        0.442

        0.553

        0.442

        C14

        0.578

        0.578

        0.462

        0.347

        C15

        0.299

        0.597

        0.448

        0.597

        C16

        0.681

        0.545

        0.273

        0.409

        Table 6.8: Normalized Priorities for Criteria

        Table 6.7: Decision matrix between alternatives and criteria

        Alternatives/crit eria

        A

        B

        C

        D

        C1

        5

        5

        4

        4

        C2

        3

        4

        3

        4

        C3

        3

        3

        4

        3

        C4

        4

        5

        3

        4

        Table 6.9: Weighted Normalized Decision Matrix

        Alternatives

        /criteria

        A

        B

        C

        D

        C1

        0.0

        0.02

        0.016

        0.016

        C2

        0.027

        0.036

        0.027

        0.036

        C3

        0.033

        0.033

        0.044

        0.033

        C4

        0.04

        0.05

        0.03

        0.04

        C5

        0.034

        0.023

        0.034

        0.034

        C6

        0.036

        0.044

        0.036

        0.027

        C7

        0.055

        0.044

        0.022

        0.033

        C8

        0.033

        0.025

        0.017

        0.033

        C9

        0.017

        0.014

        0.014

        0.01

        C10

        0.03

        0.037

        0.023

        0.015

        C11

        0.023

        0.028

        0.023

        0.017

        C12

        0.022

        0.043

        0.032

        0.043

        C13

        0.045

        0.036

        0.045

        0.036

        C14

        0.036

        0.036

        0.029

        0.022

        C15

        0.022

        0.043

        0.032

        0.043

        C16

        0.055

        0.044

        0.022

        0.033

        The Ideal and Negative ideal solutions formed with maximum and minimum values respectively in the columns of normalized weighted decision matrix as follows

        A*= {0.02, 0.27, 0.044, 0.05, 0.34, 0.027, 0.055,

        0.033,

        0.017, 0.037, 0.028, 0.043, 0.045, 0.036, 0.043,

        0.055}

        A- = {0.016, 0.36, 0.033, 0.03, 0.023, 0.044, 0.022,

        0.017,

        0.01, 0.015, 0.017, 0.022, 0.036, 0.022, 0.022, 0.022}

        The separation of each alternative from the ideal alternative ( D* ) and the anti-

        alternative ( D* ) are determined in terms of Euclidean distances using respectively.

        D* = {0.393065, 0.39598, 0.39598, 0.388844}

        D- = {0.06245, 0.06, 0.036056, 0.047958}

        Table 6.10: Ranking of project alternatives

        Project

        Relative

        Closeness

        Rank

        A

        0.137098

        1

        B

        0.131585

        2

        C

        0.083455

        4

        D

        0.109794

        3

    3. Validation of Multi-Attribute Utility Theory Additive Model

      A utility function is a device which quantifies the preferences of a decision maker by assigning a numerical index to varying levels of satisfaction of a criterion. All decisions involve choosing one, from several, alternatives. Typically, each alternative is assessed for desirability on a number of scored criteria. What connects the criteria scores with desirability is the utility function. The most common formulation of a multi-criteria utility function is the additive model.

      Steps involved in Additive Model:

        1. Setting the Objective and Establishing the Attributes for the Goal

        2. Creating Quantitative Figures of the Attributes

        3. Deriving the Utility Functions of Each

          Attribute

          Alternatives

          /criteria

          A

          B

          C

          D

          C1

          0.03

          0

          0

          0.03

          C2

          0.06

          0

          0.06

          0.03

          C3

          0.07

          0

          0

          0

          C4

          0.08

          0

          0

          0.08

          C5

          0

          0

          0

          0

          C6

          0.03

          0

          0

          0

          C7

          0

          0

          0

          0.08

          C8

          0

          0.54

          0

          0

          C9

          0.01

          0

          0.02

          0.01

          C10

          0.05

          0.05

          0

          0.02

          C11

          0.04

          0.04

          0.04

          0

          C12

          0

          0

          0

          0.03

          C13

          0.04

          0

          0

          0

          C14

          0.06

          0

          0.06

          0.04

          C15

          0

          0

          0.07

          0.07

          C16

          0.08

          0

          0

          0

          Overall priority

          0.57

          0.54

          0.26

          0.41

          x x

          k wj Where wj is the weight age of

          j n

          wj

          j 1

          jth attribute.

          5) Deriving the Multi-Attribute Utility Function each Alternative

          n

          Ui k1 u1 xi1 k2 u2 xi2 kn un xin k j u j xij

          j 1

          Table 6.11: Overall Utility Values of projects

          u x ij j

          j ij

          x x

          j j

        4. Calculating the Weighting Factors of Each Attribute

      Table 6.12: Overall Utility Values of projects

      Project

      Overall Utility

      Rank

      A

      0.137098

      1

      B

      0.131585

      2

      C

      0.083455

      4

      D

      0.109794

      3

    4. Validation of Multi-Attribute Utility Theory Multiplicative Model

The following are the steps involved in MAUT Multiplicative Model for ranking alternatives.

  1. Construct pay-off Matrix from Decision

    Makers responses

  2. Calculate range for each attribute

    To determine the utility value, there are six steps.

    1. Identify significant design attributes and generate alternative designs

    2. Find the range for each attribute and verify relevant attribute conditions

    3. Use the lottery to determine the user’s preference

    4. Evaluate Single Attribute Utility (SAU) function and trade-off preferences

    5. Combine SAUs into Multi-Attribute Utility function (MAU)

    6. Select alternative with the highest MAU value by ranking the alternative.

    Multiplicative Equation:

  3. Ranking of scaling constants of the

    U x 1 n 1 K k u (x )1

    criteria

    K

    j1

    j j j

  4. Determination of indifference points

  5. Derivation of single and multi-attribute utility functions

  6. Determination of values of scaling constants

  7. Ascertaining the attitude of the decision maker based on overall scaling constant.

  8. Ranking of the alternatives based on the utility values. Highest utility alternative is best.

Building the Utility Function:

Where xj is the performance level of attribute,

u j xj is the SAU for attribute j ,

k j is the single attribute scaling constant, and

K is the normalizing constant which scales

0 U x 1

Alternativ

es/criteria

A

B

C

D

U1(C1)

0.983

0.966

1

0.983

U2(C2)

0.929

0.994

1

0.989

U3(C3)

0.976

0.971

1

0.999

U4(C4)

0.963

0.960

1

0.994

U5(C5)

0.971

0.980

1

1

U6(C6)

0.968

0.969

1

0.994

U7(C7)

0.967

0.972

1

0.996

U8(C8)

0.978

0.986

1

0.997

U9(C9)

0.981

0.971

1

0.999

U10(C10)

0.976

0.993

1

0.991

U11(C11)

1

0.966

0.988

0.995

U12(C12)

1

0.985

0.975

0.987

U13(C13)

0.971

1

0.989

0.983

U14(C14)

0.971

1

0.976

0.997

U15(C15)

0.974

1

0.979

0.996

U16(C16)

0.985

0.98

1

0.998

Table 6.13: Utility function of project alternatives

Table 6.14: Ranking of projects based on Overall Utility

Project

1 KU Ai

Overall

Utility U A

i

Ranking

A

0.65481

0.50482

1

B

0.72629

0.40028

2

C

0.90824

0.13418

4

D

0.89401

0.15499

3

From the four MCDM methods, it is observed that the Project A was given the first ranking and is exposed to low risk. The results from all the methods are presented

Table 6.15: Ranking of the projects Based on four MCDM methods

Model

Rank for Projects

A

B

C

D

AHP

I

II

IV

III

TOPSIS

I

II

IV

III

MAUT Addition

I

II

IV

III

MAUT Multiplication

I

II

IV

III

CONCLUSIONS

The conclusions made from the study are as follows:

  1. Sixteen major factors in building construction were identified and prioritized based on RRI analysis and different MCDM methods. The criteria with RRI value >

    0.75 are considered.

  2. The AHP, TOPSIS, MAUT methods has been introduced and applied in assessing the Importance of safety factors. Risk factors significant to different projects were identified and incorporated in this assessment.

  3. The AHP model was developed which consist three layers hierarchy and sixteen major influence factors. The sequence of importance of second level in construction safety influence factor are: 1) Management processes towards safety 2) Attributes toward safety 3) Fatality at working 4) Individual performance 5) Risk processes.

  4. The sequence of risk level in case study is identified as Project-C > Project-D > Project-B > Project-A.

  5. Conducting similar studies at the organization level is useful to prioritize criteria and sub criteria pull out outcome of safety training programs and to initiate measures to overcome deficiencies.

  6. The practice of safety risk management must be enhanced in building construction, further seminars, training and workshops should be carried out in construction companies to address the problems early.

REFERENCES

  1. Behzad Esmaeili, Matthew R. Hallowell, Balaji Rajagopalan (2015) Attribute-Based Safety Risk Assessment. I: Analysis at the Fundamental Level ASCE J. Constr. Eng. Manage. 2015.141.

  2. Cheng Siew Goh, Hamzah Abdul-Rahman (2013). The Identification and Management of Major Risks in the Malaysian Construction Industry Journal of Construction in Developing Countries, 18(1), 1932.

  3. Chia-Fen Chia, Tin-Chang Changa, Hsin-I Tingb (2005). Accident patterns and prevention measures for fatal occupational falls in the construction industry. Applied Ergonomics 36 (2005) 391

    400.

  4. Farooqui, R.U, Arif F., Rafeeqi, S.F.A, (2008). Safety Performance in Construction Industry of Pakistan. First International Conference on Construction in Developing Countries (ICCIDCI) Advancing and Integrating Construction Education, Research and Practice August 4-5, 2008, Karachi, Pakistan, pp. 74-78.

  5. Goran Janackovic, Suzana Savic, Miomir Stankovic (2011). Multi-Criteria Decision Analysis In Occupational Safety Management Systems. International Conference Safety of Technical Systems in Living and Working Environment, Faculty of Occupational Safety in Ni, October 2011.

  6. Haslam R.A., Hide S.A. & Gibb A.G.F, Gyi D.E., Pavitt T., Atkinson S., Duff A.R. (2004). Contributing factors in construction accidents. Applied Ergonomics 36 (2005) 401415.

  7. Jaskowski P., Biruk S. (2011). The Conceptual Framework For Construction Project Risk Assessment. (Vol.2), September.

  8. Javad Dodangeh et.al (2009) Best project selection by using of Group TOPSIS Method. IACSIT Spring Conference 2009 International Association of Computer Science and Information Technology.

  9. Krantikumar Mhetre, Konnur B.A., Amarsinh B. Landage (2016). “Risk Management in Construction Industry” International Journal of Engineering Research Volume No.5, Issue Special 1 pp : 153-155.

  10. Lopez-Arquillos, Rubio-Romero, Gibb, Gambatese (2014). Safety Risk Assessment For Vertical Concrete Formwork Activities In Civil Engineering Construction. A Journal of Prevention, Assessment & Rehabilitation, 49:2, 183-192.

  11. Martins Claudia Garrido1, Morano Cássia Andréa Ruotolo, Ferreira Miguel Luiz Ribeiro, Haddad Assed Naked (2011). “Risk identification techniques knowledge and application in the Brazilian construction.” Journal of Civil Engineering and Construction Technology Vol. 2(11), pp. 242-252, November 2011.

  12. Patrick X. W. Zou and Guomin Zhang (2009). Comparative Study on the Perception of Construction Safety Risks in China and Australia (ASCE) J. Constr. Eng. Manage. 2009.135:620-627.

  13. Renuka S.M., Umarani C., Kamal S. (2014). A Review on Critical Risk Factors in the Life Cycle of Construction Projects. Journal of Civil Engineering Research 2014, 4(2A): 31-36.

  14. Satish B. Mohan and Bryan D. Niles (2002). Effectiveness of the Occupational Safety and Health Administration. Citations practice periodical on structural design and construction / may / 85-89.

  15. Thomas L. Saaty (2008). Decision making with the analytic hierarchy process. International Journal Services Sciences, Vol. 1, No. 1.