A Study on Analysis of Cross Drainage Work

DOI : 10.17577/IJERTV10IS020177

Download Full-Text PDF Cite this Publication

Text Only Version

A Study on Analysis of Cross Drainage Work

Rajbahadur and Neeraj Kumar

Assistant Professor,

Dept. of Civil Engineering, IFTM University Moradabad, U.P., India

Abstract – Present paper deals analysis of aqueduct and siphon aqueduct hydraulic structures. An attempt is made to design aqueduct and siphon aqueduct manually and results are observed with given loading condition.

In an Aqueduct, the canal bed level is above the drainage high flood level (HFL).

In a Siphon aqueduct, the canal bed level is below the drainage high flood level (HFL).

Key Words: Aqueduct, Siphon aqueduct, Super passage, Siphon super passage, Level crossing, Outlet and Inlet crossing.

  1. INTRODUCTION

    When a natural drain crosses or intercepts an irrigation canal, it becomes necessary to construct some suitable structure to carry forward the canal safely. As these works are constructed for crossing the drainage, these structures are known as Cross Drainage Works (CD Works).

    Canals are generally aligned on the watershed so that they meet minimum number of drain. However, before watershed is reached, they usually cross a number of drainage lines. At the watershed itself cross a number of local drainage. A canal system taking off from a large river may irrigate area comprising a number of do-abs or area between different streams.

    In this paper we are discussed the analysis of cross drainage works.

  2. TYPES OF CROSS DRAINAGE WORKS There are four following types of cross drainage works:

    1. When the irrigation canal over the drainage

      This is further divided into;

      1. An aqueduct

      2. A siphon aqueduct

    2. When the drainage over the canal.

      This is further divided into;

      1. A super passage

      2. A siphon.

    3. When drainage and canal at same level

      This is further divided into;

      1. A level crossing

      2. An inlet and outlet crossing Figure -1

  3. STRUCTURAL DESIGN APSECTS

        1. For the construction of various components of an aqueduct prestressed concrete or reinforced cement concrete or masonry or a combination of these may be used depending upon the desired ease of construction and relative economy.

        2. A suitable arrangement for supporting the section of the aqueduct may be decided depending upon the nature of

          foundation, difference between HFL of the drain and bed of canal and height between bed of canal and bottom of stream/drain and the afflux allowable in the drain. An economical span can be worked out by a judicious combination of the substructure and superstructure of the aqueduct. Multi-duct canal sections can also be adopted.

        3. To carry the service/inspection road across the drainage a suitable arrangement may be provided. For economical reason a causeway may also be considered. In case a road bridge is provided over the aqueduct it should be designed for at least IRC class A loading.

  4. DESIGN FOR CROSS DRAINAGE WORK:

    DATA FOR DESIGN

    For working out the design of an aqueduct, the following specific design data should be available.

    Hydraulic Data (Canal)

    Full supply discharge = 34 m3/sec Full supply level (R.L.) = 218.5 m Canal bed level (R.L.) = 216 m Canal bed width (R.L.) = 20 m

    Trapezoidal canal section = 1.5:1 (H: V) Canal water depth = 1.7 m

    Hydraulic Data (Drainage)

    High flood discharge = 320 m3/sec High flood level = 212 m

    High flood depth = 3 m General ground level = 215 m Clear span between piers = 9 m Pier thickness = 1.5 m Solution:

    R.L. of canal bed level is higher High Flood Level of drainage. So we adopt aqueduct type cross-drainage work. Step- I Design of drainage water way

    By Laceys regime perimeter,

    P = 4.75 Q

    Where,

    Q= high flood discharge (320 m3/sec) P = 4.75 320 =84.97 85 m

    Using 10 bays of 9 m each, clear water way =10×9 =90 m Using 9 pier of 1.5 m each, length occupied by piers = 9×1.5 = 13.5 m

    Total length of water way = 90+13.5= 103.5 m

    Step- II Design of canal water way

    Bed width of canal = 20 m

    Let the width flumed to 10.0 m Providing a splay of 2:1 in contraction, The length of contraction transition

    = (20-10)/2 x 2 = 10.0 m

    Providing a splay of 3:1 in expansion, The length of expansion transition

    = (20-10)/2 x 3 = 15.0 m

    Length of the flumed rectangular portion of the canal between abutments= 103.5 m

    In transitions, the sides slopes of the canal section will be warped in the plan from original slope of 1.5:1 (H: V)

    Step III: Head loss and bed levels at different sections At Section 4-4:

    Where the canal returns to its original section, we have area

    of trapezoidal canal section. Area, A = (B + 1.5 y) y

    = [20 + (15×1.7) × 1.7 = 38033 m2.

    Velocity, V4 = Q /A

    = 34 / 38.33 = 0.887m/ sec.

    Velocity Head = (V4)2 / 2g

    = (0.887)2 / (2 × 9.81)

    = 0.040 m.

    R.L. of canal bed level = 216.0 m.

    R.L. of water surface at section 4-4

    = 216.0 + 1.7 = 217.7 m

    R.L. of T.E.L. at section 4-4

    = 217.7 + 0.040 = 217.74 m

    At Section 3-3

    Keeping the same depth of 1.7 m. throughout the channel, we have at section 3-3

    Bed width = 10 m.

    Area of channel = 10×1.7 = 17m. Velocity (V3) = 34/17 = 2.00 m/sec

    Velocity head = (V3)2 /2g = (2.00)2 / 2×9.81

    = 0.203 m.

    Loss of head in expansion from section 3-3 to section 4-4

    = 0.3 [(v3)2 (V4)2] / 2g

    = 0.3 [(2.0)2 (0.887)2] / (2×9.81)

    = 0.049 m.

    R.L. of T.E.L. at station 3-3

    = R.L. of T.E.L. at 4-4 + Loss in expansion

    = 217.74 + 0.049 = 217.789 m.

    R.L. of water surface at station 3-3

    = R.L. of T.E.L. at 3-3 Velocity head = 217.789 0.203 = 217.586 m.

    R.L. of bed at 3-3 = 217.586 1.7

    = 215.886 m.

    At Section 2-2:

    From section 2-2 to 3-3, the cross section is same so area and velocity of sections are same. But from section 2-2 to 3-3 which may calculated by Mannings formula as equal to

    HL

    = (n2V2L) / R4/3

    HL

    = (n2V2L) / R4/3

    Where, n = rugosity co-efficient

    = 0.016 for concrete trough L = length of trough

    = 103.5 m.

    V = velocity on trough

    = Q/A

    = 34/17 [Where, A = (10×1.7 = 17)]

    = 2 m/sec

    R = A/P = 17/13.4 = 1.27 m.

    [Where, P = 10+ (2×1.7) = 13.4 m)]

    Hence, HL = [(0.016)2 × (2)2 ×103.5] / (1.27)4/3

    = 0.077 m.

    R.L. of T.E.L. at station 2-2

    = R.L.of T.E.L. at 3-3 + Friction loss in trough

    =217.586+0.077 = 217.663 m.

    R.L. of water surface at station 2-2

    = R.L. of T.E.L. at 2-2 Velocity head

    = 217.663 0.203 = 217.46 m.

    R.L. of bed at 2-2 = 217.46 1.7

    = 215.76 m.

    At Section 1-1:

    Loss of head in contraction transition from 1-1 to 2-2 section

    = 0.2 [(V2)2 – (V1)2 ] / 2g

    = 0.2 [(2)2 (0.887)2] / (2×9.81)

    = 0.033 m.

    R.L. of T.E.L. at station 1-1

    = R.L. of T.E.L. at 2-2 + Loss in contraction

    =217.663+0.033 = 217.696 m.

    R.L. of water surface at station 1-1

    = R.L. of T.E.L. at 1-1 Velocity head

    = 217.663 0.040 = 217.656 m.

    R.L. of bed at 1-1 = 217.656 1.7

    = 215.956 m.

    Figure 2

    Step-IV Design of Transitions

    1. Contraction Transition

      Figure 3

      By using Mitras hyperbolic transition equation, we can be designed the width of transition

      Bx = (Bn .Bf. Lf) / [Lf Bn x (BnBf)] Where, Bn=20 m,

      Bf=10 m and Lf=10 m

      Putting the above values in equation, we can find

      Bx= (20×10×10) / [200 – x (20-10)]

      Bx is depend on the values of x as mentioned above figure, the values of x varies from 0 to 10 m right to left.

      Table -1

      x, (meter)

      0

      2.5

      5

      7.5

      10

      Bx = (20×10×10) 200-x[20-10]

      (meter)

      10

      11.4

      13.3

      16

      20

      The contraction transition can be easily plotted with the help of these values.

    2. Expansion Transition

    Figure 4

    By using Mitras hyperbolic transition equation, we can be designed the width of expansion,

    Bx= (Bn .Bf. Lf)/Lf Bn-x[Bn-Bf]

    Where Bn=20 m, Bf=10 m, and Lf=15 m

    Putting the above values in equation, we can find Bx= (20×10×15)/300-x[20-10]

    Bx is depend on the values of x as mentioned above figure, the values of x varies from 0 to 15 m left to right.

    Table -2

    x, (meter)

    0

    3

    6

    9

    12

    15

    Bx= (20×10×15) 300-x[20-10]

    (meter)

    10

    11.1

    12.5

    14.2

    16.6

    20

    The expansion transition can be easily plotted with the help of these values.

    Step-V Design of Trough

    Figure 5

    The trough shall be divided into two equal components of 5m each and separated by an intermediate wall of 0.3 m thickness.

    A free board of 0.8 m above the normal water depth of 1.7 m is sufficient; hence bottom level of the road slab over the left component can be kept at 1.7 + 0.8 =2.5 m above the bed level of the trough.

    The trough section will be constructed in monolithic reinforced concrete and can be designed by structural method.

  5. CONCLUSION

    From the analysis, for the given data following points are concluded:

    1. For rectangular cross section, Perimeter is 85 m and total length of water way is 103.5m for the design of drainage water way.

    2. In plan section, the length of contraction and expansion are 10 m & 15 m at transition respectively for the design of drainage water way.

    3. In this study analysis, we designed the Head losses,

      R.L. of canal bed level, water surface and T.E.L at different sections as mentioned above in Step III.

    4. By using Mitras hyperbolic transition equation, we calculated the values of width at interval of 2.5 m at the contraction transition and at the interval of 3 m at the expansion transition.

  6. ACKNOWLEDGEMENT

    We are pleased to publish the paper titled A study on analysis of cross drainage work. We are highly thankful to our guide for providing guidance as required. We also thankful to our college staff for giving opportunity to carry out the work.

  7. REFERENCES:

    1. Modi, P.N.: Irrigation, Water Resources and Water Power Engineering. Standard Book House.

    2. Garg, S.K.: Irrigation Engineering and Hydraulic Structures. Khanna Publishers.

    3. Punmia, B.C. and Pande, B.B. Lal: Irrigation and Water Power Engineering. Laxmi Publication

    4. https://www.irjet.net/archives/V3/i4/IRJET-V3I4460.pdf

    5. https://www.scribd.com/document/391026409/14-cross-drainage- works-pdf

Leave a Reply